HomeMy WebLinkAboutAgreement for Demolition & Site Clearance-12/12/2011AGREEMENT FOR DEMOLITION AND SITE CLEARANCE
GROUP 175-D-CDBG-12-12-11
THIS AGREEMENT made this 12th day of December, 2011, by and between BENTON'S
SAND & GRAVEL, INC., a corporation organized and existing under the laws of the State of
Iowa, hereinafter called the "CONTRACTOR", and the CITY OF WATERLOO, IOWA,
hereinafter called the "CITY".
WITNESSETH, that the Contractor and the City for the consideration stated herein mutually
agree as follows:
ARTICLE 1. STATEMENT OF WORK. The Contractor shall furnish all supervision, technical
personnel, labor, materials, machinery, services, and perform and substantially complete all work
within 45 days after receipt of Notice to Proceed, all work required for the Demolition and Site
Clearance in an efficient and workmanlike manner as follows: DEMOLITION OF BUILDINGS
ON, AND CLEARANCE OF SITES of all parcels as enumerated in Bid Schedule attached to
and forming a part of this Contract, within the City of Waterloo Demolition Project 175-D-
CDBG-12-12-11 all in strict accordance with the Contract Documents for Demolition and Site
Clearance including all Addenda thereto,
Numbered 1 and Dated November 28, 2011
Numbered 2 and Dated December 2, 2011
ARTICLE 2. THE CONTRACT PRICE. The Local Public Agency will pay the Contractor
for the performance of the Contract in current funds, subject to additions and deductions
as provided in the Section "Changes in the Work" under General Conditions, Part I, and subject
to all other conditions set forth in the Contract Documents, the sum of
TWENTY EIGHT THOUSAND, FIVE HUNDRED FIFTY-FIVE AND NO/100 DOLLARS
($28,555.00), in addition to and above the value of such salvaged materials specified to become
the property of the Contractor, and in accordance with the contractor's bid.
ARTICLE 3. CONTRACT. The executed Contract Documents shall consist of the following:
a.
b.
c.
d.
e.
This Agreement
Addenda
Invitation to Bid
Instructions to Bidders
Signed copy of Bid
f. General Conditions
Part I, II, and III
g. Special Conditions
h. Technical Specifications
i. Drawings as listed in the
Schedule of Drawings
AGR -1
THIS AGREEMENT, together with the other documents enumerated in this Article 3, which said
other documents are as fully a part of the Contract as if hereto attached or herein repeated, forms
the Contract between the parties hereto. In the event that any provision in any component part of
this Contract conflicts with any provisions of any other component part, the provision of the
component part first enumerated in this Article 3 shall govern, except as otherwise specifically
stated.
NOTICE TO PROCEED. After execution of the Agreement, a Notice to Proceed will be issued
to the contractor, whereupon the contractor shall proceed with his/her work in accordance with
the Contract time established in the Pre -Construction Meeting.
ARTICLE 4.
IN WITNESS WHEREOF, the parties hereto have caused this Agreement to be executed in three
(3) original copies on the day and year first above written.
BENTON'S SAND & GRAVEL, INC.
905 CENTER STREET]
CEDAR FALLS, IA 50613-1407
Contractor Name
CITY OF ATERLOO
By:
rnest G. Clark, Mayor
ATTEST:
(for individual or partnership)
By:
ATTEST:
By:
Suzy S . ares City Clerk
AGR -2
CITY OF WATERLOO ITEMIZED UNIT PRICE SCHEDULE GROUP NO. 175-D-CDBG-12-12-11
CDBG - DEMOLITION PROGRAM
BASE BID
STREET ADDRESS
MAIN BUILDING OTHER NET
STORY HOT. & TYPE BASEMENT BUILDINGS BID PRICY
2170 Burton Avenue
Former Van Eaton School None
Burton/Midiand Building (Approx. 9,300 SF)
None S 28,555.00
BASE BID TOTAL $ 28,555.00
BF -4 (1)