HomeMy WebLinkAboutPeters Construction - FY16 W 2nd, Cedar and W. 3rd Street-5/8/2017CHANGE ORDER NO. 6
Owner City of Waterloo Date: 04/26/2017
Project FY 2016 W 2nd, Cedar and W 3rd Streets Improvemeents
Owner's Contract No. 912 Contractor: Peters Construction
Date of Contact Start 20 -Jun -16 Contract Amount:
$ 810,810.00
You are directed to make the following changes In the Contract Documents. Description:
Unit Estimated
Unit Price Quantity Cost
6.1 (5) MODIFIED SUBBASE CY 37.44 883 3,305 95
6-2 (6) STND OR SLIP FORM PCC PAVEMENT, CLASS C, CLASS 3 DURABILITY, 6 IN. SY 36.95 43 7 1,614.72
6-3 (7) STND OR SLIP FORM PCC PAVEMENT, CLASS C, CLASS 3 DURABILITY, 9 IN. SY 62.79 301.3 18,918.63
6-4 (10) REMOVAL OF UGHT POLES & FOOTINGS (Modified to Remove/Reinstall) EA 3056.7 10 3,056.70
6.5 (20) INTAKE, SW -603, TOP ONLY EA 2354.63 1.0 2,354.63
6-6 (27) REMOVAL OF PAVEMENT SY 8.6 481.6 4,141.76
6-7 (30) SIDEWALK, P.C. CONCRETE, CLASS C, CLASS 3 DURABILITY, 5 IN. SY 33.7 29.7 1,000.89
6-8 (41) ELECTRICAL CIRCUITS (Modified to Each Price) EA 2300 1.0 2,300.00
6-9 (42) HANDHOLES AND JUNCTION BOXES EA 662.5 1.0 862.50
6-10 (45) PAINTED PAVEMENT MARRING, WATERBORNE OR SOLVENT BASED STA 50.72 6.0 304,32
6-11 (46) PAINTED SYMBOLS AND LEGENDS, WATERBORNE OR SOLVENT -BASED EA 48.3 2.0 96.60
6-12 (47) TRAFFIC CONTROL L5 1150 1.0 1,150.00
6.13 (48) MOBILIZATION LS 5232.5 1.0 5,232 50
6-14 (49) DETECTABLE WARNINGS SF 33.81 14 0 473.34
6-15 (52) PERIMETER AND SLOPE SEDIMENT CONTROL DEVICE, 12 IN. DIA. LF 4.05 250 0 1,012,50
6-16 (53) REMOVE PERIMETER AND SLOPE SEDIMENT CONTROL DEVICE, 12 IN. DIA. LF 0.76 250.0 190,00
6-17 (54) INTAKE PROTECTION EA 91.05 4.0 364.20
6-18 (55) REMOVAL OF INTAKE PROTECTION EA 24.15 4.0 96.60
6-19 (65) SOD SY 11.29 215.0 2,427.35
TOTAL ADDITIONS $ 48,903.18
Reason for Change Order
6-1 to Construct new driveway opposite Single Speed Brewery Dock to accommodate truck movements.
6-19
CONTRACT PRICE
Original:
Previous C.O,s IADD/DEDUCT)
This C.O. (ADD/DEDUCT)
Contract Price with all approved
Change Orders:
CONTRACT TIME
To substantial To Flna'
Completion Completion
S 810,810.00 Original Completion Date: 10/30/20161 10/30/2016
S 58,424.46
$ 48,903.18 Revised Completion Date: 6/15/20171 6/15/20171
$ 918437.64
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s) ordered herein,
Incldding all impact, delays, and acceleration costs. Other than the dollar amount and time allowance listed above, there shall be no further
time or dollar compensation as a result of this Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND CONVENANTS OF THE CONTRACT SHALL APPLY (HERETO.
APPRO
BY:
Owwnner (Authorized Signature
ACCEPTED:
BY:
Contractor (Authorized Signature)
ACCEPTED:
BY: .A-2"4+ je(
Date
S/yfi7
Date
s I(
Date
AECOM
60509363 I 6
Project No, C.O. No.