HomeMy WebLinkAboutASPRO - CO#2 - FY16 Street Reconstruction-5/22/2017Item
Description
Unit
Unit$
Est. Q
Total
2001
STORM SEWER, 2000D, 30"
LF
$136.40
525.00
$71,610.00
2002
SW -401, 60" DIA.
EACH
$6,710.00
2.00
$13,420.00
2003
TYPE E -2-C INLET, USE EXISTING CASTING
EACH
$3,300.00
3.00
$9,900.00
2004
FILL EXISTING AND PLUG 12 STORM SEWER
EACH
$324.50
2.00
$649.00
2005
COLLAR PIPE, SW -211
EACH
$1,320.00
2.00
$2,640.00
2006
CORE DRILL MANHOLE FOR 30" DIA. PIPE
EACH
$3,420.00
2.00
$6,840.00-
2007
ADDITIONAL STARLITE BLVD. SURVEY
LS
$1,309.00
1.00
$1,309.00
2008
ADDITIONAL STARLITE BLVD. TRAFFIC CONTROL
LS
$3,520.00
1.00
$3,520.00
TOTAL
$109,888.00
CITY OF WATERLOO, IOWA
CHANGE or EXTRA WORK ORDER NO. 2
PROJECT: F.Y. 2016 STREET RECONSTRUCTION PROGRAM, CONTRACT NO. 898
Date Prepared: November 15, 2016 AMOUNT: $ 109,888.00 INCREASE
TO: ASPRO, INC.
, Contractor
You are hereby ordered to make the following changes from the plans and specifications or perform the following
extra work on your contract dated April 4, 2016
A. Description of change to be made or extra work to be done:
2001-2008 Add construction of 30" storm sewer to the 700 block of Starlite Blvd. which is being
reconstructed under this contract.
B. Reason for ordering change or extra work:
2001-2008 Starlite Blvd. contains an outlet for storm sewer from University Avenue. Preliminary design o
University Avenue storm sewer system indicates the need to increase the size of the storm sewer in this
block to 30". This extra work order is to increase the size of the storm sewer with the street reconstruction,
so this block of Starlite Blvd. will not be impacted with the University Ave. project.
C. Settlement for cost of work to be made as follows:
CITY OF WATERLOO
BY:
Mayor
Change Order No. 2
TOTAL INCREASE =
/111/1
Date
Date CONTRACTOR
BY: % J ✓ li'
ASPRO, INC.
$109,888.00
6/)dt
D to
PRINTED NAME: Milt Dakovich
5////7
Date
TITLE: President
APPROVED;
City Engineer Eate
Contract No. 898 Page 1/1
Item Coversheet Page 1 of 1
CITY OF WATERLOO
Council Communication
Motion approving Change Order No. 2 for a net increase of$109,888.00 for the F.Y. 2016 Street Reconstruction Program, Contract No. 898; and
authorize the Mayor and City Clerk to execute said document.
City Council Meeting: 5/22/2017
Prepared: 5/17/2017
ATTACHMENTS:
Description
❑ Cont 898 CO ff2
SUBJECT:
Submitted by:
Recommended Action:
Summary Statement:
Type
okk!r Morn,
Motion approving Change Order No. 2 for a net increase of $109,888.00 for the F.Y. 2016 Street
Reconstntction Program, Contract No. 898: and authorize the Mayor and City Clerk to execute said
document.
Submitted By: Dennis Gentz, PE, Assistant City Engineer
Approve change order.
Source of Funds: Local Option Sales Tax Funds
Background Information:
Starlite Blvd. contains an outlet for storm sewer from University Avenue. Preliminary design of
University Avenue storm sewer system indicates the need to increase the size of the storm sewer in
this block to 30". This extra work order is to increase the size of the storm sewer with the street
reconstruction, so this block of Starlite Blvd. will not be impacted with the University Ave. project.
»
https://waterloo.novusagenda.com/AgendaWeb/CoverSheet.aspx?ItemID=8491 5/17/2017