HomeMy WebLinkAboutLarson Construction Company, Inc.-7/13/2015CHANGE ORDER NO. 4
Owner. City of Waterloo Date: July 06, 2015
Project: F.Y. 2013 Blowers Creek Storm Water Lift Station and Dry Run Creek Improvements
Owner's Contract No.: 842 (EDA Award No. 05-79-05007) Contractor. Larson Construction Company, Inc.
Date of Contract Start: April 29, 2014 $ 3,570,000.00
You are directed to make the following changes in the Contract Documents. Description:
Item 107 — Stainless Steel Pull Box and Conduit for Generator Connector Box - (1.0 LS ® $2,300.00 = $2,300.00)
Item 108 — Modifications for Radar Unit - (1.0 LS ® $6,734.76 = $6,734.76)
Item 109 — Additional Riprap — (1.0 LS ® $8,422.40 = $8,422.40)
Item 110 — Fence Around Gate Well — (1.0 LS ® 87,935.00 = $7,935.00)
Item 111— Sump Pit in Valve Vault — (1.0 LS ® $506.00 = $506.00)
Reason for Change Order
Item 107 — The Generator Connector Box supplied has connections for the portable generator cables in the bottom of the box. As a result, there is no bottom access for the
conduit connections from the Generator Connector Box to the MCC utilizing the conduit stubbed out of the floor slab directly below the box. These connections
must be made into the side of the Generator Connection Box. In order to make these connections, additional conduit and a stainless steel pull box must be
installed. This change order covers the cost to supply, fabricate and install the conduit and pull box necessary to make these connections.
Item 108 — In order for the radar level detection unit to work properly, the hole in the floor needs to be enlarged. This is necessary to ensure the radar unit does not receive
false readings due to the signal bouncing off the edges of the opening.
Item 109 — Additional riprap is being installed on the north and east sides of the pump station to cover the 3:1 slopes. This will limit the maintenance required on these steep
slopes by eliminating the need for mowing.
Item 110 — Fence is being added around the gate well to limit the vandalism damage to the new gate actuators.
Item 111— A sump pit is being added to the floor of the valve vault so maintenance crews don't have to work in standing water. This pit will allow a temporary sump pump
to be dropped into the structure to pump out the water.
CONTRACT PRICE
CONTRACT TLMES (Calendar Days)
To fmal
completion
Original: $ 3,570,000.00 Original: March 31, 2015
Previous C.O.s (ADD/DEDUCT): $ 65,331.34 Previous C.O.s (ADD/DEDUCT): May 15, 2015
This C.O. (ADD/DEDUCT): $ 25,898.16 This C.O. (ADD/DEDUCT):
Contract Price With All Approved
Change Orders: $ 3,661,229.50 REVISED: May 15, 2015
Revised Completion Date: May 15, 2015
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s) ordered herein, including all impact, delays,
and acceleration costs. Other than the dollar amount and time allowance listed above, there shall be no further time or dollar compensation as a result of this Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO
By:
Owner (Authorized Signature)
ACCEPTED:
By:
Con for Authorized Signature) Date:
Date:
I - t5
AECOM
60188622.15 4
Project No. Change Order No.
CARSON
CONSTRUCTION CO. INC.
May 7, 2015
AECOM
500 SW 7th Street, Suite 301
Des Moines, Iowa 50309
P.O. Box 112
INDEPENDENCE, IA 50644
Phone (319) 334-7061 Fax (319) 334-4474
Web site: larsonconst.com
RE: Blowers Creek Storm Water Lift Station
ATTN: Todd Allyn
Change Proposal #7
Scope of work to be done:
RFI #34--, Electrical Work (I
Cost Summary:
K&W Electric
Respectfully,
Ann Schwartz
Larson Construction Co., Inc.
$ 2,000.00
Sub -Total $ 2,000.00
15% OH&P $ 300.00
TOTAL $ 2,300.00
COMMERCIAL AND INDUSTRIAL GENERAL CONTRACTORS
KW Electric Inc.
1127 Lincoln Street
P.O. Box 967
Cedar Falls, Iowa 50613
http:// www.k-welectic.com
E-mail ckrull@k-welectric.com
Phone (319) 277-0415
Fax (319) 277-1418
Date: 4/16/15
To: Larson Construction
Attention: Travis S
Regarding: Blowers Creek, Generator Pull Box
We propose to install the required electrical per plans for the sum of:
Material $ 978.00
Labor $1,022.00
Total $2,000.00
****This price does include:
1. Supply and install (1) Stainless steel pull box sized per NEC installed on top of
the (3) installed 4" conduits for the Portable Generator Connector Box.
2. Supplying and installing (6) additional Meyers threaded hubs and (3) additional
rigid conduit nipples between the added pull box and the connector box.
*****This price does not include:
1. Voice, data, t -stat, temp control, security, and other low voltage cabling by
others.
2. Cutting and patching.
*****This quote can be held for 30 business days. After this time the material will be
requoted.
If you have any questions feel free to call.
Thank you,
Christopher A Krull
Project Manager (Customer's Signature)
KW Electric, Inc.
****Please he advised that under Statue 572.13 Liability of Owner to Original Contractor:
"Persons or companies furnishing materials for improvement of real property may enforce a lien upon the improved
property if they are not paid for their contributions, even if the parties have no direct contractual relationship with the
owner"
An Equal Opportunity Employer
CARSON
CONSTRUCTION CO. INC.
PROJECT:
P.O. Box 112
INDEPENDENCE, IOWA 50644
Telephone (319) 334-7061 Fax (319) 334-4474
Web -site: larsonconst.com
REQUEST FOR INFORMATION
Blowers Creek, Waterloo Iowa
RFI #28
Date: 4/8/2015
Subject:
Generator Connector Box
Drawing
Detail
Specification
The Generator connector box Is shown on the plans to be fed from (3) 4° rigid conduits installed In the slab.
These conduits have been installed. The Generator Connector Box Is designed to have the generator cables
connect and leave the box from the bottom and run to the generator. There is no bottom access for the
conduits between the generator connector box and the MCC for the Installed conduits.
K&W Proposes: to install the required electrical per plans for the sum of:
Material : $ 978.00
Labor : $1,022.00
Total : $2,000.00
****This price does include:
1. Supply and Install (1) Stainless steel pull box sized per NEC installed on top of
the (3) installed 4" conduits for the Portable Generator Connector Box.
2. Supplying and installing (6) additional Meyers threaded hubs and (3) additional
rigid conduit nipples between the added pull box and the connector box.
*****This price does not include:
1. Voice, data, t -stat, temp control, security, and other low voltage cabling by
others.
2. Cutting and patching.
Submitted by: KW Electric/LCCI
Response:
Distribution:
Proposal Acceptable. Please Proceed.
Answered by: AECOM - Todd Allyn
Date: 4/27/2015
CARSON
CONSTRUCTION CO. INC.
June 1, 2015
AECOM
500 SW 7th Street, Suite 301
Des Moines, Iowa 50309
P.O. Box 112
INDEPENDENCE, IA 50644
Phone (319) 334-7061 Fax (319) 334-4474
Web site: larsonconst.com
RE: Blowers Creek Storm Water Lift Station
ATTN: Todd Allyn
Change Proposal #8
Scope of work to be done:
Modifications for radar unit, additional riprap
Cost Summary:
Iowa Wall Sawing $ 2,710.00
IEP $ 506.31
LCCI Labor (3 people - 2 days _ 48 mh @ $55ihr) $ 2,640.00
Additional stone at lift station bldg (357.26 ton @ $20.50) $ 7,323.83
Sub -Total $ 13,180.14
15% OH&P $ 1,977.02
TOTAL $ 15,157.16
Respectfully,
Ann Schwartz
Larson Construction Co., Inc.
COMMERCIAL AND INDUSTRIAL GENERAL CONTRACTORS
Quotation
1-110u-7�7-4
Quote: 0000005607
Quote Date: 04/24/2015
Quote Expires: 05/24/2015
Job Name: CORE DRILL
Fax 1-319-934-3279 * Email: info@ lowaWallSawing.com
2600 Quasqueton Diagonal Blvd, Independence, IA 50644
PREPARED FOR
LARSON CONSTRUCTION CO.
PO BOX 112
INDEPENDENCE, IA 50644
Phone: 319-334-7061
Attn: Travis Schwartz
Qty Description
Fax: 319-334-4784
JOB SITE ADDRESS
J l
3260 LAFAYETTE ROD
WATERLOO, IA 50707
Sales Rep: PETER MURRAY
Each
J
Total
1.00 SCANNING 850.00 850.00
SCANNING
1.00 CORE DRILLING 1,650.00
CORE DRILL @ 30" DEPTH, CUSTOMER TO HAVE MARKED, WATER ON SITE
1,650.00
(2) 10" CORE HOLES
2.00 TRAVEL CHARGE 105.00 210.00
TRAVEL CHARGES
2,710.00
STANDARD CONDITIOINS: The customer Is responsible for maintaining the Job site and their equipment per OSHA standards. Clear and open access must be provided.
Iowa Wall Sawing accepts no liability for any damages to anything hidden or concealed in or under concrete, or beneath the material to be cut, cored, broken, nor for water or dust damage.
Prices are Quoted tor standard overcuta for all work at ground level. Additional charges will be made for overtlmo and double-time.
STANDARD EXCLUSIONS: Layout, traffic control, barricades. patching anchor holes, power source, lighting, water source, water control, slurry control and removal, blocking storm drains/catch basins,
scaffoldinghnanli ts, ventilation, shoring, core catching, cutting or ddNng any steel or any obstacles unless specifically detailed above.
SIGNATURE: PRINT NAME: DATE:
"• THIS QUOTE IS GOOD FOR 45 DAYS UNLESS OTHERWISE SPECIFIED ABOVE."*
- WE ACCEPT ALL MAJOR CREDIT CARDS -
Printecl: 04/24/2015 09:41:42 AM Page 1 of 1
Iowa Engineered Processes 2
513 17th Street SE
Independence, Iowa 50644
UNITED STATES
Email: steve@iepc.com
Invoice (Not Paid)
Invoice No: 13629
Invoice date: 320/2015
Sales Order No: 1816
Due date: 3/20/2015
Reference: Blowers Creek
Customer ID: 25
BM to:
Larson Construction
600 17th Street
Independence, IA 50644
Ship to:
Larson Construction
600 17th Street SE
Independence, IA 50644
Radiator
General Repair
YES Or NLD)
Delivery Date
Job Name/Contract
Blowers Creek
Shipping Method
Extra To Contract
Or NO
1
# Blowers Creek -
Custom Plate
Blowers Creek. Custom Plate 140x14" x
318" With Hole Pattern Prlmed Grey Per
Travis S.
$506.31
Subtotal: $50631
Tax total: $0.00
Total: $506.31
Payments: $0.00
Balance due: $50631
Page 1 of 1
CARSON
CONSTRUCTION CO. INC.
June 17, 2015
AECOM
500 SW 7th Street, Suite 301
Des Moines, Iowa 50309
P.O. Box 112
INDEPENDENCE, IA 50644
Phone (319) 334-7061 Fax (319) 334-4474
Web site: larsonconst.com
RE: Blowers Creek Storm Water Lift Station
ATTN: Todd Allyn
Change Proposal #9revised
Scope of work to be done:
For Black Vinyl Coated
Cost Summary:
D&N Fence (verbal phone quote)
Respectfully,
Ann Schwartz
Larson Construction Co., Inc.
$ 6,900.00
Sub -Total $ 6,900.00
15% OH&P $ 1,035.00
TOTAL $ 7,935.00
COMMERCIAL AND INDUSTRIAL GENERAL CONTRACTORS
CARSON
CONSTRUCTION CO. INC.
July 1, 2015
AECOM
500 SW 7th Street, Suite 301
Des Moines, Iowa 50309
P.O. Box 112
INDEPENDENCE, IA 50644
Phone (319) 334-7061 Fax (319) 334-4474
Web site: larsonconst.com
RE: Blowers Creek Storm Water Lift Station
ATTN: Todd Allyn
Change Proposal #10
Scope of work to be done:
Sump Pump Work
Cost Summary:
2 people - 4 hrs each (8mh @ $55/hr) $ 440.00
Sub -Total $ 440.00
15% OH&P $ 66.00
TOTAL $ 506.00
Respectfully,
Ann Schwartz
Larson Construction Co., Inc.
COMMERCIAL AND INDUSTRIAL GENERAL CONTRACTORS
CITY OF WATERLOO
Council Communication
Motion approving Change Order No. 4 for a net increase of $25,898.16 for the F.Y. 2014
Blowers Creek Storm Water Lift Station and Dry Run Creek Improvements, Contract No. 842;
and authorize the Mayor and City Clerk to execute said document.
City Council Meeting: 7/13/2015
Prepared: 7/8/2015
ATTACHMENTS:
Description Type
o Cont 842_Change Order 4 Cover Memo
SUBJECT:
Submitted by:
Recommended Action:
Summary Statement:
Source of Funds:
Background Information:
Motion approving Change Order No. 4 for a net increase of
$25,898.16 for the F.Y. 2014 Blowers Creek Storm Water Lift
Station and Dry Run Creek Improvements, Contract No. 842; and
authorize the Mayor and City Clerk to execute said document.
Submitted By: Jamie Knutson, PE, Associate Engineer
Approve change order.
Approval of change order increases total contract price to
$3,661,229.50.
100% grant; no city funding
See attached Change Order for additional information.