CHANGE or EXTRA WORK ORDER NO. 4
PROJECT: F.Y. 2014 Street Reconstruction Program CONTRACT NO. 859
Date Prepared:August 19, 2015 AMOUNT: $34,149.00 INCREASE
TO: Aspro, Inc. , Contractor
You are hereby ordered to make the following changes from the plans and specifications or perform the
following extra work on your contract dated April 21, 2014.
A. Description of change to be made or extra work to be done:
4001 Installing new sanitary sewer along Fisher Drive
4002 Installing new sanitary manholes along Fisher Drive
4003 Traffic control during construction of new sanitary sewer on Fisher Drive
B. Reason for ordering change or extra work:
4001-4003 Installation of new sanitary sewer along Fisher Drive prior to the Green Acres Storage
building being completed. By installing the sanitary sewer prior to the Green Acres Storage
development there will not be any costs for replacement of landscaping, driveways or repair of the
detention basin.
C. Settlement for cost of work to be made as follows:
4001 398.00 L.F. x $60.50/L.F. = $24,079.00
4002 2 Each x $4,785.00/Each = $9,570.00
4003 1 L.S. x $500.00 = $500.00
CITY S WATE
BY:
Mayor
4/�
Date
ATTES
City Cler Date
NET INCREASE $34,149.00
Aspro, Inc.
BY:
PRINTED NAME:
TITLE:Vs•
20 1 -
Date
APP OVED:
ci:A.T6VA4,4"" e(25/ks---
City Engineer Date
CITY OF WATERLOO
Council Communication
Motion approving Change Order No. 4 for a net increase of $34,149.00 for the F.Y. 2014 Street
Reconstruction Program, Contract No. 859; and authorize the Mayor and City Clerk to execute said
document.
City Council Meeting: 8/24/2015
Prepared: 8/19/2015
REVIEWERS:
Department Reviewer Action Date
Engineering Thorson, Eric Approved 8/19/2015 - 11:01 AM
Clerk Office Felchle, Kelley Approved 8/19/2015 - 12:57 PM
ATTACHMENTS:
Description Type
Cont 842_Change Order 4 Cover Memo
Submitted by: Submitted By: Jamie Knutson, PE, Associate Engineer
Recommended Action: Approve change order.
Source of Funds: San Marnan TIF
Background Information:
Installation of new sanitary sewer along Fisher Drive prior to the
Green Acres Storage building being completed. By installing
the sanitary sewer prior to the Green Acres Storage development
there will not be any costs for replacement of landscaping,
driveways or repair of the detention basin.