HomeMy WebLinkAboutAecom Technical Services-10/5/2015 (3)A=COM
September 17, 2015
Mr. Keith Kaspari
Director of Aviation
Waterloo Regional Airport
2790 Livingston Lane
Waterloo, IA 50703
AECOM 515 323 7910 tel
500 SW 7th Street 515 244 4803 fax
Suite 301
Des Moines, Iowa 50309
www.aecom.com RECEIVED SEP 222015
SUBJECT: Remove and Replace Windows and Clean and Tuck Point Masonry
Waterloo Regional Airport
City of Waterloo, Iowa
Iowa DOT CSVI FY 2015 Grant # 91150AL0200
Contract No. 16609
AECOM ID No. 60338621
Dear Mr. Kaspari:
Transmitted herewith for review and approval, are four (4) copies of Change Order Nos. 1 & 2 for the
above mentioned project. Change Order No. 1 provides a deduct for a change from the 850 Series Pella
windows specified to a 450 Series Pella window. Currently there are 450 Series windows at other
locations on this building. In addition, the 850 Series and 450 Series windows are basically the same
except the 850 Series allows for more options. Since the existing windows are plain casement windows,
the 850 Series are not needed so the contractor is offering to use the 450 Series to match the existing
windows. This Change Order decreases the total contract amount by $1,350.00.
Change Order No. 2 covers the cost to remove and replace the drywall that is below the replacement
windows. This drywall was damaged by moisture from leaks in the existing windows. The existing
drywall will be removed, new drywall will be installed, the patches will be finished and sanded, and the
patched areas will be painted to match the existing interior walls. This Change Order increases the total
contract amount by $970.00.
Combined, these Change Orders decrease the total contract amount by $380.00. We have reviewed
these Change Orders, find them to be fair and reasonable, and recommend approval.
Please return three (3) fully -executed copies to our office for distribution to the IDOT and the
Contractor.
If you have any questions or comments, please contact our office at your convenience.
Yours sincerely,
David B. Hughes, P.E.
Enclosures: As noted
P:\60338621 ALO FY 2015 Vertical Infrastructure\600_Construction_Support\620_Correspondence\KK091715.00 Nos. 1 & 2.Itr.doc
CHANGE ORDER NO. 1
Owner Waterloo Regional Airport, City of Waterloo, Iowa Date 08/10/15
Project Remove and Replace Windows and Clean and Tuck Point Masonry
Owner's Contract No. IDOT CSVI FY 2015 Grant #91150AL0200, Contract #16609 Contractor Failor Hurley Constr
Date of Contract Start
You are directed to make the following changes in the Contract Documents. Description:
Item No.
Description
Unit
Unit Price
Quantity
Amount
101
Deduct for Change in Window Type
LS
$ 1,350.00
(1.0)
($ 1,350.00)
Total Change Order ($ 1,350.00)
Reason for Change Order:
Item Number 101, Deduct for Change in Window Type, covers the difference in cost between the 850
Series Pella windows specified and a 450 Series Pella window. Currently, there are 450 Series windows
at other locations on this building. In addition, the 850 and 450 series windows are basically the same
except the 850 allows for more options. Since the existing windows are plain casement windows the
850 Series are not needed so the contractor is offering to use the 450 Series to match the existing
windows.
Remove and Replace Windows CO -1 Project No — 60338621
And Clean and Tuck Point Masonry
1
CONTRACT PRICE
Original: $
Previous C.O.s (ADD): $
This C.O. (DEDUCT): $ 1,350.00
Contract Price with all
approved Change Orders: $ 28,223.54
29,573.54 Original:
CONTRACT TIMES (Calendar Days)
0.00 Previous C.O.s (ADD):
This C.O. (ADD):
REVISED:
To substantial
completion
08/28/15
0 Days
56 Days
10/23/15
To fmal
completion
0
0
0
0
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the
change(s) ordered herein, including all impact, delays, and acceleration costs. Other than the dollar amount and time
allowance listed above, there shall be no further time or dollar compensation as a result of this Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
S I PULATIONS AND COVENANTS OF THE CON TRACT SHALL APPLY HERETO.
RECOMMENDED:
By:
Engineer (Authorized Signature)
APPROVE
By:
Owner (Authorized Signature)
ACCEPTED:
By:
C i actor / uthorize i:u ature)
5Ji-i) 5—
Date
Lb /5/t 5'
Date
-7-&-1-0
Date
Remove and Replace Windows
And Clean and Tuck Point Masonry
CO -1 Project No - 60338621
2
CHANGE ORDER NO. 2
Owner Waterloo Regional Airport, City of Waterloo, Iowa Date 09/02/15
Project Remove and Replace Windows and Clean and Tuck Point Masonry
Owner's Contract No. IDOT CSVI FY 2015 Grant #9I150AL0200, Contract #16609 Contractor Failor Hurley Constr
Date of Contract Start
You are directed to make the following changes in the Contract Documents. Description:
Item No.
Description
Unit
Unit Price
Quantity
Amount
102
Remove and Replace Drywall Under Windows
LS
$ 970.00
1.0
$ 970.00
Total Change Order $ 970.00
Reason for Change Order:
Item Number 102, Remove and Replace Drywall Under Windows, covers the cost to remove and
replace the drywall that is under the replacement windows. This drywall has been damaged by moisture
from leaks in the existing windows. The existing drywall will be removed, new drywall will be
installed, the patches will be finished and sanded, and the patched areas will be painted to match the
existing interior walls.
Remove and Replace Windows
And Clean and Tuck Point Masonry
CO -2 Project No — 60338621
1
CONTRACT PRICE CONTRACT TIMES (Calendar Days)
To substantial To final
completion completion
Original: $ 29,573.54 Original: 08/28/15 0
Previous C.O.s (DEDUCT): $ 1,350.00 Previous C.O.s (ADD): 56 Days 0
This C.O. (ADD): $ 970.00 This C.O. (ADD): 0 Days 0
Contract Price with all REVISED: 10/23/15 0
approved Change Orders: $ 29,193.54
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the
change(s) ordered herein, including all impact, delays, and acceleration costs. Other than the dollar amount and time
allowance listed above, there shall be no further time or dollar compensation as a result of this Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO.
RECOMMENDED:
By: 4 A . \44"`
Engineer (Authorized Signature)
APPROVED
By:
Owner (Authorized Signature
ACCEPTED:
By:
11
Co actor (Authiiif ed Signature)
Ct / I
Date
Date
0/20Dta-i
Remove and Replace Windows CO -2 Project No — 60338621
And Clean and Tuck Point Masonry
2
CHANGE ORDER NO. 1
Owner Waterloo Regional Airport, City of Waterloo, Iowa Date 08/10/15
Project Remove and Replace Windows and Clean and Tuck Point Masonry
Owner's Contract No. IDOT CSVI FY 2015 Grant #9I150AL0200, Contract #16609 Contractor Failor Hurley Constr
Date of Contract Start
You are directed to make the following changes in the Contract Documents. Description:
Item No.
Description
Unit
Unit Price
Quantity
Amount
101
Deduct for Change in Window Type
LS
$ 1,350.00
(1.0)
($ 1,350.00)
Total Change Order ($ 1,350.00)
Reason for Change Order:
Item Number 101, Deduct for Change in Window Type, covers the difference in cost between the 850
Series Pella windows specified and a 450 Series Pella window. Currently, there are 450 Series windows
at other locations on this building. In addition, the 850 and 450 series windows are basically the same
except the 850 allows for more options. Since the existing windows are plain casement windows the
850 Series are not needed so the contractor is offering to use the 450 Series to match the existing
windows.
Remove and Replace Windows
And Clean and Tuck Point Masonry
CO -1 Project No — 60338621
1
CONTRACT PRICE
Original: $
Previous C.O.s (ADD): $
This C.O. (DEDUCT): $ 1,350.00
Contract Price with all
approved Change Orders: $ 28,223.54
29,573.54 Original:
CONTRACT TIMES (Calendar Days)
To substantial To fmal
completion completion
08/28/15 0
0.00 Previous C.O.s (ADD): 0 Days 0
This C.O. (ADD):
REVISED:
56 Days 0
10/23/15 0
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the
change(s) ordered herein, including all impact, delays, and acceleration costs. Other than the dollar amount and time
allowance listed above, there shall be no further time or dollar compensation as a result of this Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO.
RECOMMENDED:
By: 3. \,
Engineer (Authorized Signature)
Date
Owner (Authorized Signature) Date
ACCEPTED:
e-13-2o1S
Date
Remove and Replace Windows CO -1 Project No — 60338621
And Clean and Tuck Point Masonry
2
CHANGE ORDER NO. 2
Owner Waterloo Regional Airport, City of Waterloo, Iowa Date 09/02/15
Project Remove and Replace Windows and Clean and Tuck Point Masonry
Owner's Contract No. IDOT CSVI FY 2015 Grant #9I150AL0200, Contract #16609 Contractor Failor Hurley Constr
Date of Contract Start
You are directed to make the following changes in the Contract Documents. Description:
Item No.
Description
Unit
Unit Price
Quantity
Amount
102
Remove and Replace Drywall Under Windows
LS
$ 970.00
1.0
$ 970.00
Total Change Order $ 970.00
Reason for Change Order:
Item Number 102, Remove and Replace Drywall Under Windows, covers the cost to remove and
replace the drywall that is under the replacement windows. This drywall has been damaged by moisture
from leaks in the existing windows. The existing drywall will be removed, new drywall will be
installed, the patches will be finished and sanded, and the patched areas will be painted to match the
existing interior walls.
Remove and Replace Windows CO -2 Project No — 60338621
And Clean and Tuck Point Masonry
1
CONTRACT PRICE CONTRACT TIMES (Calendar Days)
To substantial To fmal
completion completion
Original: $ 29,573.54 Original: 08/28/15 0
Previous C.O.s (DEDUCT):$ 1,350.00 Previous C.O.s (ADD): 56 Days 0
This C.O. (ADD): $ 970.00 This C.O. (ADD): 0 Days 0
Contract Price with all REVISED: 10/23/15 0
approved Change Orders: $ 29,193.54
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the
change(s) ordered herein, including all impact, delays, and acceleration costs. Other than the dollar amount and time
allowance listed above, there shall be no further time or dollar compensation as a result of this Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO.
RECOMMENDED:
By:. --
Engineer (Authorized Signature)
cAft,Iis
Date
Owner (Authorized Signature) Date
ACCEPTED:
By:
C
actor (A orized Signature) Date
Remove and Replace Windows
And Clean and Tuck Point Masonry
CO -2 Project No — 60338621
2