Loading...
HomeMy WebLinkAboutMuniciple Pipe Tool Company, LLC-8/4/2014CHANGE ORDER NO. 1 Owner: City of Waterloo Date: 7/29/2014 Project Sanitary Sewer Improvements Service Area No. 15 and No. 16 Phase I Cl? Pipe Lining Owner's Contract No.: 866 Contractor: Municipal Pipe Tool Company, LLC Date of Contract Start: March 17, 2014 $ 641,171.36 You are directed to make the following changes in the Contract Documents. Description: See attached Change Order No. 1 spread sheet. Line Item 1. MH Inspection Results — Additions and deductions were made to the contract based on the data collected from contractor manhole inspections authorized by the City. From these inspections, the contact was adjusted to mirror revised quantities. 2. City of Waterloo Emergency Additions — The City added work on Fletcher and Lafayette due to pipe failures 3. Inaccessible Manhole Video Results — The Contractor could not access a few manholes due to obstructions or being buried. These lines were videotaped to see if pipe lining work was necessary. Work was added or deducted based on those video results 4. COP Pipe Size Changes — Additions and deductions where two pipe runs were discovered to have different sized pipe than was documented in the City record drawings 5. Additional Work — Work added on Upton Ave based the poor condition of the pipe Reason for Change Order. See above CONTRACT PRICE Original: $ 641,171.36 Original: Previous C.O.s (ADD/DEDUCT): $ 0.00 Previous C.O.s (ADD/DEDUCT): This C.O. (ADD/DEDUCT): $ 121,839.93 This C.O. (ADD/DEDUCT): Contract Price With All Approved Change Orders: $ 763,011.19 REVISED: Original Completion Date: Revised Completion Date: CONTRACT TIMES (Calendar Days) To Substantial To Final Completion Completion It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s) ordered herein, including all impact, delays, and acceleration costs. Other than the dollar amount and time allowance listed above, there shall be no further time or dollar compensation as a result of this Change Order. THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO APPROVED: (I2‘612 e ( Signature) By: / / Si ature) ACCEPTED: glJi: SliPro . WRsciF,&t Contractor (Authorized Signature) 7/2_9/14 Date: AECOM 60323440 Project No. Change Order No. P:\60323440\00000000\600 -Construction Support\670 Change Orders\20140729 CO #1\20140729 Change Order No 1-SIGNED.doc Original Contract 1 23221.0 1 405.01 57.0 1 51.0 1 25.01 20.0 1 0.0 1 O.b r 50.00 ay Estimate Change Order No. 1 00.11114 253E1.0 312.0 10 0 I I I I4utl;1 33.0 1 41.01 180.0 1 5.0 1 51260.00 02; 34.2 20 a Z 0 Original Construction Contract Quantity Totals CONTRACT PRICE WITH APPROVED CHANGE ORDERS` $783,011,10 CHANGE ORDER NO. 11 $121,838.83 CONTRACT ADJ MH INSP CHANGE ORDER ACTIONS n o n o1. m , n E iram D g m F m City or Waterloo Emergency AddISone Inecceseible Manhole Video Results Change Order NO. 1 Actions Contract Adjustment from the Manhole Inspection' 837,511.26 ¢ g 3 r g t m n val ..'-ii Original Construction Contract Contract Adjustment from the Manhole Inspection m ri 3 r u v m D 3 g.z o - o ? o i .. �m Original Contract 8.2 o 0 m 8= i3 0. s �.. m c a ......1581 . m '¢ ! 3 C3 + a $ C3 0, ow. b o m 28 C3 o i N N $ u o N 0 0 8T m C3 o ageg oo m C3 Oa 0o 131 g33 mm` . ,'a c S .00-W S 2 UDP $ (I .3¢ -a m m x'rno 0 06¢ mm3 Va Bid Item 04 External Chimney Seal 5.01 to 0 m a a r g w wS Bld Item 04 External Chimney Seal 0,0 EA e . S ' Bld Item 04 External Chimney Seal 51.0 EA ft! _m ..- P T o c o vmmee ' N o W c FR p¢ s3 e g o D m o m n ;ff s3 Ea ft m n� l'' 0 o m N 0 e w N o v o fU g _o. ' 3 .8 c -..8,72P,1," m m El as S Oem .2i c x_0+41 g u 7 1_ i s $ T F S s oo 0 .. 2 ,..;_z ai o, a A r m --00 ® m S_� v '"e m =.5.. 3ai I. .'I"0 o _ c Z 3m q`¢3 WI 388 F a '+'gP o 0 22882 8828 N: .Se N 0 m F�3 :mo Fmk �oP W V ...4+ M -` ->•. N A W N N by - m r m - N W TOTAL m A r �. 4 TOTAL 2 n C tow 0 Z 0 m p ..am aWn coz Z m O Z v 0 -71C