HomeMy WebLinkAboutK & W Electric Inc-12/8/2014CHANGE ORDER NO. 6 (FINAL)
Owner Waterloo Regional Airport, City of Waterloo, Iowa Date November 7, 2014
Project Rehabilitate Airfield Vault
Owner's Contract No. FAA AIP Project No. 3-19-0094-40 Contractor K&W Electric Inc.
Date of Contract Start August 13, 2012
You are directed to make the following changes in the Contract Documents. Description:
Item No.
Description
Unit
Unit Price
Quantity
Amount
109
Asbestos Removal Allowance Modification
LS
-$11,338.44
1
-$11,338.44
Change Order Subtotal
-$11,338.44
Total Amount of Change Order -$11,338.44
Reason for Change Order:
Item 4 — A $15,000 allowance was included in the bids for removal of asbestos materials in the existing Airport
Lighting Vault. The contractor only needed a total of $3,661.56 for the asbestos removal so the remaining $11,338.44
will be deleted from the contract.
Rehabilitate Airfield Vault
CO -6 (FINAL) Project No — 60275869
1
CONTRACT PRICE
Original: $ 865,905.00
Previous C.O.s (ADD): $ 34,986.75
This C.O. (ADD): $ -11,338.44
Contract Price with all
approved Change Orders: $ 889,553.31
CONTRACT TIMES (Calendar Days)
To substantial To final
completion completion
Original:
Previous C.O.s (ADD):
This C.O. (ADD):
REVISED:
270
0
45
315
Original Completion Date: 270
Revised Completion Date: 315
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the
change(s) ordered herein, including all impact, delays, and acceleration costs. Other than the dollar amount and time
allowance listed above, there shall be no further time or dollar compensation as a result of this Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO.
RECOMMENDED:
By: 044
Engine. (Authorized Signature)
APP' V.' D:
By:
wner (Authorized Signature
ACCEPTED:
By: 4j
Contractor (Authorized Signature)
1Z/
Date
bate
/1/21/1 /
Date
Rehabilitate Airfield Vault
CO -6 (FINAL) Project No — 60275869
2