HomeMy WebLinkAboutPeterson Contracting, Inc-5/6/2013CHANGE ORDER NO. 3 Owner: City of Waterloo, Iowa Date: April 30, 2013 Project: FY 2011 Anaerobic Lagoon Influent Pump Station Owner's Contract No.: 807 Contractor. Peterson Contractors, Inc. Date of Contract Start: August 17, 2011 $ 1,145,000.00 You are directed to make the following changes in the Contract Documents. Description: CO3-1. Additional Electrical Work $50,778.25 CO3-2. Additional Pipe and Materials 2,721.75 CO3-3. Additional Fence 2311.20 TOTAL $55,811.20 Reason for Change Order: CO3-1-3. Payment for additional work performed and resolution of all claims on the project. CONTRACT PRICE Original: 5 1,145,000.00 Original: Previous C.O.s (ADD/DED1JGT): S 15,683.09 Previous C.O.s (ADD/DEDUCT): This C.O. (ADDS): S 55,811.20 This C.O. (ADD/DEDUCT): Contract Price With All Approved Change Orders: $ 1,216,494.29 REVISED: CONTRACT TIMES (Calendar Days) To Completion December 30, 2011 December 7, 2012 Revised Completion Date: December 7, 2012 It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s) ordered herein, including all impact, delays, and acceleration costs. Other than the dollar amount and time allowance listed above, there shall be no further time or dollar compensation as a result of this Change Order. APPROVED: By: ACCEPTE B3 THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO Signature) Date: Contractor (Authorized Signature Date: L: work project 1 I3632'adnm•60184424 41 -Anaerobic Lagoon Specs•CO 3.doc AECOM 113632.41 3 Project No. Change Order No.