HomeMy WebLinkAboutMike Dolan Concrete & Masonry-8/19/2013CITY OF WATERLOO, IOWA CHANGE or EXTRA WORK ORDER NO. 1 PROJECT: FY 2012 CHAUTAUQUA PARK CURB REPAIR CONTRACT NO. 828 Date Prepared: Auqust2, 2013 AMOUNT: $2,745.50 INCREASE TO: MIKE DOLAN CONCRETE & MASONRY , Contractor You are hereby ordered to make the following changes from the plans and specifications or perform the following extra work on your contract dated November 5, 2012. A. Description of change to be made or extra work to be done: Adjust original construction quantities to actual construction quantities. B. Reason for ordering change or extra work: As -built quantities varied for some bid items C. Settlement for cost of work to be made as follows: Compensation already made to contractor through bid items. See attached summary. TOTAL I NCRERSE $2,745.50 q; MIKE DOLAN CONCRETE & MASONRY Mayor Da a CONTRACTOR BY: Mm -LV tkak A â– EST: City Cler Change Order No. 1 Date Date TITLE: Piesfle141- APP OVED: r_ City Engineer Date Contract No. 828 Sheet 1 of 1 F.Y. 2012 CHAUTAUQUA PARK CURB REPAIR CONTRACT NO. 828 FINAL QUANTITIES ADJUSTMENT BID ITEM ITEM DESCRIPTION MIKE DOLAN ORIGINAL FINAL QUANTITY INCREASE/ UNITS UNIT PRICE QUANTITY QUANTITY DIFFERENCE DECREASE 1 Curb Patch SF $ 75.00 45.0 47.0 2.0 $ 150.00 2 Remove/Replace Curb & Gutter, 24" Wide, 10.5" Depth SF $ 49.50 1,213.0 1,290.2 77.2 $ 3,821.40 3 Remove/Replace Curb & Gutter, 24" Wide, 6" Depth SF $ 48.50 541.0 561.0 20.0 $ 970.00 4 Remove/Replace PCC Sidewalk, 4" SF $ 6.00 193.0 211.6 18.6 $ 111.60 5 Remove/Replace PCC Sidewalk, 6" SF $ 6.50 125.0 0.0 (125.0) $ (812.50) 6 Detectable Waming Surface SF $ 40.00 16.0 0.0 (16.0) $ (640.00) 7 Cold Weather Protection EA $ 3.00 285.0 0.0 (285.0) $ (855.00) 8 Traffic Control LF $ 1,200.00 1.0 1.0 0.0 $ - TOTAL INCREASE IN CONSTRUCTION ITEMS $ 2,745.50 PAY ESTIMATE #1 $ 4,702.50 PAY ESTIMATE #2 $ 47,069.27 PAY ESTIMATE #3 $ 10,690.87 PAY ESTIMATE #4 $ 29,751.96 RETAINAGE $ 4,853.40 TOTAL PAYMENTS $ 97,068.00 ORIGINAL CONTRACT AMOUNT $ 94,322.50 NO CHANGE ORDERS ADDED NEW CONTRACT AMOUNT $ 94,322.50 FINAL NEW CONTRACT AMOUNT $ 94,322.50 FINAL QUANTITY SUMMARY - CHANGE ORDER #1 $ 2,746.50 FINAL CONTRACT AMOUNT $ 97,068.00