HomeMy WebLinkAboutAspro, Inc-9/23/2013CITY OF WATERLOO, IOWA CHANGE or EXTRA WORK ORDER NO. 3 PROJECT: F.Y. 2013 STREET RECONSTRUCTION PROGRAM, CONTRACT NO. 832 Date Prepared: September 25, 2013 AMOUNT: $ 5,179.74 INCREASE TO: ASPRO, INC. , Contractor You are hereby ordered to make the following changes from the plans and specifications or perform the following extra work on your contract dated May 13, 2013 A. Description of change to be made or extra work to be done: 3001 Lower 8" sanitary sewer main; remove existing and replace with ductile iron including incidentals involved Reason for ordering change or extra work: 3001 Existing 8" sanitary sewer mains north of Park Lane at Saratoga Drive and Edgemont Avenue are in conflict with the RCB and need to be lowered C. Settlement for cost of work to be made as follows: 3001 Lower existing 8" sanitary sewer main 2 Each @ $2,589.87 = $ 5,179.74 Per each TOTAL INCREASE TITLE: AR f5-/8T,v7' $ 5,179.74 APPROVED: arD cappitit 4, 9130113 City Engineer Date