HomeMy WebLinkAboutAspro Inc-10/14/2013CHANGE ORDER NO. 1
Owner Waterloo Regional Airport, City of Waterloo, Iowa Date October 3, 2013
Project Rehabilitation of Taxiway E
Owner's Contract No. FAA AIP Project No. 3-19-0094-41 Contractor Aspro, Inc.
Date of Contract Start June 3, 2013
You are directed to make the following changes in the Contract Documents. Description:
Reason for Change Order:
After completing the milling of the existing asphalt overlay on Taxiway E, the joints in the existing PCC
pavement were able to be visually inspected for the first time. This inspection revealed considerably
more damage at these joints than was previously anticipated. As a result, this change order is necessary
to pay for additional patching to fix the deterioration at these joints.
In addition, the visual inspection of the joints discussed above revealed significantly less joints and
cracks that required filling. As a result, this change order will delete the lineal feet of crack and joint
filling that was not required to help offset the cost of the additional patching.
Also, material testing during the first day of bituminous leveling course placement revealed that the
material that was placed was low on air voids and subject to rejection. The contractor chose to keep this
material in place and take a 50% reduction in payment for the material in lieu of removing the asphalt
and replacing it. As a result, the reduction in bituminous leveling course will be included in this change
order to help offset the cost of the additional patching.
Rehabilitation of Taxiway E CO -1 Project No — 60278510
1
Item No.
Description
Unit
Unit Price
Quantity
Amount
5
PCC Pavement Patching
SF
$22.60
3,422.0
$77,337.20
7
PCC Pavement Joint and Crack Filling
LF
$2.40
(10,000.0)
($24,000.00)
15
Bituminous Leveling Course
TON
$85.25
(400.0)
($34,100.00)
Change Order Subtotal
$19,237.20
Total Amount of Change Order $19,237.20
Reason for Change Order:
After completing the milling of the existing asphalt overlay on Taxiway E, the joints in the existing PCC
pavement were able to be visually inspected for the first time. This inspection revealed considerably
more damage at these joints than was previously anticipated. As a result, this change order is necessary
to pay for additional patching to fix the deterioration at these joints.
In addition, the visual inspection of the joints discussed above revealed significantly less joints and
cracks that required filling. As a result, this change order will delete the lineal feet of crack and joint
filling that was not required to help offset the cost of the additional patching.
Also, material testing during the first day of bituminous leveling course placement revealed that the
material that was placed was low on air voids and subject to rejection. The contractor chose to keep this
material in place and take a 50% reduction in payment for the material in lieu of removing the asphalt
and replacing it. As a result, the reduction in bituminous leveling course will be included in this change
order to help offset the cost of the additional patching.
Rehabilitation of Taxiway E CO -1 Project No — 60278510
1
CONTRACT PRICE CONTRACT TIMES (Calendar Days)
To substantial To final
completion completion
Original: $ 1,083,425.25 Original: 90
Previous C.O.s (ADD): $ 0.00 Previous C.O.s (ADD): 0
This C.O. (ADD): $ 19,237.20 This C.O. (ADD): 21
Contract Price with all REVISED: 111
approved Change Orders: $ 1,102,662.45
Original Completion Date: Aug. 31, 2013 90
Revised Completion Date: Sept. 21, 2013 111
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the
change(s) ordered herein, including all impact, delays, and acceleration costs. Other than the dollar amount and time
allowance listed above, there shall be no further time or dollar compensation as a result of this Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO.
Engineer
APPR
By
ACCEPTED
By:
Contr,
tor (Authorized Signature)
Date
/0i //
Date
Rehabilitation of Taxiway E CO -1 Project No — 60278510