HomeMy WebLinkAboutStickfort Construction-10/14/2013CITY OF WATERLOO Council Communication City Council Meeting: October 14, 2013 Prepared: October 7, 2013 Dept. Head Signature: Eric Thorson, PE., City Engineer # of Attachments: SUBJECT: CHANGE ORDER NO. - $168,124.56 INCREASE F.Y. 2013 BLOWERS CREEK CUNEI'1'h REPAIRS CONTRACT NO. 845 Submitted by: Jamie Knutson, PE, Associate Engineer Recommended City Council Action: Staff has reviewed this Change Order and recommends that the Mayor be authorized to sign it on behalf of the City. Please execute all three (3) copies and return two (2) to our office for further processing. Summary Statement Transmitted herewith is Change Order No. 2 in the increased amount of $168,124.56. This is the accumulated amount of adjustments from field changes on plan quantity bid items that were determined necessary during the construction of the project. Expenditure Required Source of Funds- GO Bond Funds Policy Issue N/A Alternative None Background Information: The large increase is due high waters that washed out half of the work that had begun, which then required repairs. The width of the channel paving was then increased to hopefully keep this type of washout from happening again. Cc: Rudy Jones, Community Development Director Pauline Closson, Engineering Depaitalent CITY OF WATERLOO, IOWA CHANGE or EXTRA WORK ORDER NO. 2 PROJECT: F.Y. 2013 Blowers Creek Cunette Repairs CONTRACT NO. 845 Date Prepared: October 2, 2013 AMOUNT: $168,124.56 INCREASE TO: Stickfort Construction , Contractor You are hereby ordered to make the following changes from the plans and specifications or perform the following extra work on your contract dated November 13, 2013. A. Description of change to be made or extra work to be done: Adjust original construction quantities to actual construction quantities. B. Reason for ordering change or extra work: As -built quantities varied for some bid items. C. Settlement for cost of work to be made as follows: Compensation already made to contractor through original bid items. See attached summary. CITY OF i ERLOO ^ i BY: Mayor ATTEST: Crty-.elerl� -- - Date NET INCREASE $168,124.56 1/l Stickfort Construction ate CONTRACTOR BY: )15A74\- 10 .2 I i 3 PRINTED NAME: Sa TITLE: 'P‘fisia.eA\- APPROVED: Date g2 City Engineer Date F.Y. 2013 BLOWERS CREEK CUNETTE REPLAIRS CONTRACT #845 FINAL QUANTITY SUMMARY BASE BID BID STICKFORT ITEM DESCRIPTION UNIT UNIT PRICE 1 PCC PAVEMENT REMOVAL SY $ 8.00 2 CLEARING AND GRUBBING LS $ 1,500.00 3 SALVAGE RIPRAP, STOCKPILE AND SPREAD LS $ 1,500.00 4 EXCAVATION, CLASS 10 CY $ 8.00 5 COMPACTION WITH M&D CY $ 3.00 6 COMPACTION TESTING LS $ 2,500.00 7 PCC PAVEMENT, 6" SY $ 44.00 8 ED JOINT LF $ 11.00 9 RT JOINT LF $ 11.00 10 COLD WEATHER PROTECTION SY $ 2.00 11 ENGINEERING FABRIC SY $ 10.00 12 TOPSOIL CY $ 10.00 13 INSTALL SILT FENCE LF $ 4.00 14 CLEAN SILT FENCE LF $ 1.00 15 REMOVE SILT FENCE LF $ 1.00 16 SEEDING ACRE $ 2,750.00 17 FERTILIZING ACRE $ 330.00 18 MULCHING ACRE $ 1,155.00 19 ROLLED EROSION CONTROL PRODUCT SY $ 1.35 20 SWPP MAINTENANCE, INSPECTION AND REPORTING LS $ 2,500.00 21 TRAFFIC CONTROL AND BARRICADING LS $ 2,500.00 1001 #4 BARS, 24" LONG @ 3' CENTERS EACH $ 3.30 1002 PUMPING CONRETE UNDER EXTISING SLAB CY $ 209.00 TOTAL BASE BID ALTERNATE #1 BID STICKFORT ITEM DESCRIPTION UNIT UNIT PRICE 1 PCC PAVEMENT REMOVAL SY $ 2 CLEARING AND GRUBBING LS $ 1,500.00 3 SALVAGE RIPRAP, STOCKPILE AND SPREAD LS $ 4 EXCAVATION, CLASS 10 CY $ 8.00 5 COMPACTION WITH M&D CY $ 3.00 • 6 COMPACTION TESTING LS $ 1,500.00 7 PCC PAVEMENT, 6" SY $ 8 ED JOINT LF $ 9 RT JOINT LF $ 10 COLD WEATHER PROTECTION SY $ 11 ENGINEERING FABRIC SY $ 10.00 12 TOPSOIL CY $ 10.00 13 INSTALL SILT FENCE LF $ 14 CLEAN SILT FENCE LF $ 15 REMOVE SILT FENCE LF $ 16 SEEDING ACRE $ 2,750.00 17 FERTILIZING ACRE $ 330.00 18 MULCHING ACRE $ 1,155.00 19 ROLLED EROSION CONTROL PRODUCT SY $ 1.35 20 SWPP MAINTENANCE, INSPECTION AND REPORTING LS $ 1,500.00 21 TRAFFIC CONTROL AND BARRICADING LS $ 2,000.00 TOTAL ALTERNATE #1 TOTAL BASE BID + ALTERNATE #1 PAY ESTIMATE #1 $ 196,015.97 PAY ESTIMATE #2 $ 38,674.98 PAY ESTIMATE #3 $ 44,797.11 PAY ESTIMATE #4 $ 44,681.35 PAY ESTIMATE #5 $ 57,456.62 RETAINAGE $ 20,085.58 TOTAL PAYMENT $ 401,711.60 ORIGINAL CONTRACT AMOUNT $ 217,747.04 CHANGE ORDER #1 APPROVED BY CITY ENGINEER $ 15,840.00 FINAL QUANTITY ADJUSTMENT $ 168,124.56 FINAL CONTRACT AMOUNT $ 401,711.60 ORIGINAL FINAL QUANTITY QUANTITY QUANTITY DIFFERENCE INCR/DECR 608.3 1,554.30 946.00 $ 7,568.00 1.0 1.00 0.00 $ 1.0 0.50 (0.50) $ (750.00) 6,656.5 8,798.50 2,142.00 $ 17,136.00 4,435.1 6,577.10 2,142.00 $ 6,426.00 1.0 1.00 0.00 $ 1,633.3 4,051.60 2,418.30 $ 106,405.20 360.0 72.00 (288.00) $ (3,168.00) 36.0 399.00 363.00 $ 3,993.00 1,633.3 1,767.60 134.30 $ 268.60 22.2 (22.20) $ (222.00) 521.2 1,193.20 672.00 $ 6,720.00 225.0 225.00 0.00 $ 225.0 (225.00) $ (225.00) 225.0 (225.00) $ (225.00) 0.98 3.56 2.58 $ 7,095.00 0.98 3.56 2.58 $ 851.40 0.23 2.91 2.68 $ 3,095.40 3,611.1 3,160.00 (451.10) $ (608.99) 1.0 1.00 0.00 $ 1.0 1.00 0.00 $ 1000.0 1,400.00 400.00 $ 1,320.00 60.0 146.75 86.75 $ 18,130.75 $ 173,810.37 ORIGINAL FINAL QUANTITY QUANTITY QUANTITY DIFFERENCE INCR/DECR 0.0 - $ 1.0 1.00 - $ 0.0 - $ 2,613.4 2,613.40 - $ 1,567.5 1,567.50 - $ 1.0 1.00 - $ 0.0 - $ 0.0 - $ 0.0 - $ 0.0 - $ 22.2 (22.20) $ (222.00) 359.7 359.70 $ 0.0 $ 0.0 $ 0.0 - $ 0.68 (0.68) $ (1,870.00) 0.68 (0.68) $ (224.40) 0.19 (0.19) $ (219.45) 2,333.3 (2,333.30) $ (3,149.96) 1.0 1.00 - $ 1.0 1.00 - $ $ (2,357.05) $ (5,685.81) $ (2,357.05) $ 168,124.56 ity of Waterloo