HomeMy WebLinkAboutKWS Inc-10/24/2013Contract No.:
CITY OF WATERLOO, IOWA
Traffic Operations Department
CONTRACT MODIFICATION
No.
6A<<5
Traffic Operations Project Number. TOF-219
Project No:
Kind of Work: Construction- Fiber Optics Date Prepared: October 15. 2013
Contractor. KWS
The above referenced contract between City of Waterloo and KWS Inc. is hereby modified as described in this Modification
document.
A - Description of change to be made or extra work to be done:
1- Install a conduit for Mediacom service to Sportsplex
B — Reason for change or extra work:
1- This is an addition to the original contract and is needed to provide Mediacom service to the Sporteplex building.
C-1 —Settlement for cost of work to be made as follows:
1- $3,500.
C-2 — Justification for cost(s)
1- Covers cost of the conduit and installation.
D — ITEMS INCLUDED IN CONTRACT
None.
E — ITEMS NOT INCLUDED IN CONTRACT
4" PVC Conduit (Sch 40 but Sch 80 under street pavement) from Sportsplex connection point to W 3rd Street by the alley
to Mediacom's PED in front of the peacock building on W 3rd. This conduit is to be used by Mediacom for providing service
to the Sportsplex building.
Approved: f \
{rq 7 B 'l` 1 I.
I11 C `iL ��l.'ryy17 1.
SSS -1� Project Engineer
0j14, 2_63
Date
Receipt is acknowledged of this modification and terms of settlement are hereby agreed to.
For City of Waterloo:
Name: e51l�•L���
Signatur Title:
Date:
/6 13/.3
For Contractor.
Name:
Signature:
Date:
Ai/
1C?/zip 3
Title: > P
ADDENDUM NO. 1
FY 2014
4TH STREET BRIDGE SLOPE PROTECTION AND RWERWALL REPAIRS
CITY CONTRACT NO. 855
AECOM #60287085
DATE: October 23, 2013
BIDS CLOSE: October 28, 2013; 4:00 p.m. Local Time
TO ALL BIDDERS BIDDING ON THE ABOVE PROJECT
All bidders submitting a bid on the above Contract shall carefully read this addendum and give it
consideration in the preparation of their Bid.
The following are revisions to the Specifications:
a) The Bid Form has been revised to include the addition of Bid Items 12, 13 and 14. A new
Bid Form, marked "Revised Per Addendum No. 1 - 10/23/13," is included with this
Addendum for use in submitting your bid.
b) Page M-6, MBE/WBE Business Enterprise Pre -Bid Contact Information Form, is included
in this Addendum and shall be included as part of the bid submittal for this project.
c) Special Provision Section 03 32 20, Removal and Replacement of PCC Sidewalk, has
been added and a copy is included in this Addendum.
II. The following are revisions to the Plans
a) Sheet 2 - Add the following general note. "Contractor may request temporary closure of
Cedar Street for access and staging needs for the project. Contractor will be responsible
for providing, maintaining, and removing traffic control associated with temporary closure
of Cedar Street as required by the City. All costs associated with the temporary closure
shall be considered incidental to the bid item for "Mobilization."
b) Sheet 2 - Add the following general note: "No Causeways or temporary fills may be
placed within the Cedar River."
c) Sheet 2 - Add the following general note: "All grass areas disturbed by project shall not
be measured or paid separately but shall be considered incidental to the project."
d) Sheet 3 - Add the following items to the table of Estimated Quantities:
ITEM NO.
DESCRIPTION
UNITS
ESTIMATED
QUANTITY
12
Handrail Removal
LF
110.0
13
Removal of Sidewalk
SY
135.0
14
Sidewalk, PC Concrete, 5 in.
SY
135.0
e) Sheet 3 - Add the following to the Estimate Reference Notes:
"12 Includes the removal and disposal of the existing handrail on top of the levee as
shown on Sheet 4. Work associated shall be in accordance with special
provision Section 03 24 00."
"13 Includes an undistributed quantity of removal of Cedar River Trail sidewalk on the
downstream side of the 4th Street Bridge. Actual quantity to be removed shall be
determined after bridge slope protection and riverwall repairs are substantially
complete."
"14 Includes an undistributed quantity of Cedar River Trail sidewalk to replace that
removed as part of item 13."
III. Attachments:
a) Bid Form for Submitting Bid (Marked "Revised Per Addendum No. 1 - 10/23/13")
b) Page M-6, MBE/WBE Business Enterprise Pre -Bid Contact Information Form, to be
included in bid submittal.
c) Specification Section 03 32 20 Removal and Replacement of PCC Sidewalk.
IV. Any revisions to any of the Contract Documents made by this Addendum shall be considered as
the same revision to any and all related areas of the Contract Documents not specifically called
out in this Addendum.
V. The Bidder shall acknowledge receipt of this addendum by inserting the date and number in the
spaces provided in the BID FORM marked "Revised Per Addendum No. 1 -10/23/13."
AECOM
WATERLOO, IOWA
Steven J. Eaton, P.E.
L:\work\project\60287085 FY 2014 4th St Bridge Repaire\400 Technica11420_Specs\ADDENDUM NO 1.docx
Revised Per Addendum No. 1 -10/23113
FORM OF BID OR PROPOSAL
4TH STREET BRIDGE SLOPE PROTECTION
AND RIVERWALL REPAIRS
CITY OF WATERLOO, IOWA
CITY CONTRACT NO. 855
Honorable Mayor and City Council
Waterloo, Iowa
Gentlemen:
1. The undersigned, being a Corporation existing under the laws of the State of , a Partnership
consisting of the following partners: , having familiarized
(himself) (themselves) (itself) with the existing conditions on the project area affecting the cost of the work,
and with all the contract documents listed in the Table of Contents and Addenda (if any), as prepared by
AECOM now on file in the office of the City Clerk, City Hall, Waterloo, Iowa, hereby proposes to furnish all
supervision, technical personnel, labor, materials, machinery, tools, appurtenances, equipment, and services,
including utility and transportation services required to construct and complete this 4111 STREET BRIDGE
SLOPE PROTECTION AND RIVERWALL REPAIRS, CONTRACT NO. 855, all in accordance with
the above -listed documents and for the unit prices for work in place for the following items and quantities:
4TH STREET BRIDGE SLOPE PROTECTION
AND RIVERWALL REPAIRS
CONTRACT NO. 855
BID
ITEM
DESCRIPTION
UNIT
EST. QTY.
UNIT BID
PRICE
TOTAL BID PRICE
1
Mobilization
LS
1.0
$
$
2
Pavement Removal
SY
271.0
$
$
3
Riverwall Removal and Replacement
LS
1.0
$
$
4
Riverwall Repairs
SF
140.0
$
$
5
Concrete Slope Protection
SY
271.0
$
$
6
Granular Subbase
SY
271.0
$
$
7
Subdrain, Longitudinal, 4 -Inch Diameter
LF
110.0
$
$
8
Subdrain, Longitudinal, 6 -Inch Diameter
LF
25.0
$
$
9
Flap -Gate, 4 -Inch Diameter
Each
1.0
$
$
10
Steel Handrail
LF
110.0.4$
$
11
Concrete Sealer
SF
3,450.0
$
$
12
Handrail Removal
LF
110.0
$
$
FORM OF BID
60287085
CONTRACT NO. 855
BF -1 of 3
Revised Per Addendum No. 1 -10123/13
BID
ITEM
DESCRIPTION
UNIT
EST. QTY.
UNIT BID
PRICE
TOTAL BID PRICE
13
Removal of Sidewalk
SY
135.0
$
$
14
Sidewalk, PC Concrete, 5 -Inch
SY
135.0
$
$
TOTAL BID
$
2. It is understood that the quantities set forth are approximate only and subject to variation and that the unit bid
price for the work done shall govern in the actual payment to Contractor.
3. In submitting this bid, the bidder understands that the right is reserved by the City of Waterloo, Iowa, to
reject any or all bids. If written notice of the acceptance of this bid is mailed, telegraphed, or delivered to the
undersigned within thirty (30) days after the opening thereof, or at any time thereafter before this bid is
withdrawn, the undersigned agrees to execute and deliver an agreement in the prescribed form and furnish the
required bond and certificate of the insurance within ten (10) days after the agreement is presented to him for
signature, and start work within ten (10) days after "Notice to Proceed" is issued.
4. Security in the sum of Dollars
($ ) in the form of , is submitted herewith in
accordance with the INSTRUCTIONS TO BIDDERS.
5. Attached hereto is a Non -Collusion Affidavit of Prime Contractor.
6. Attached hereto is a Resident Bidder Certification ( ), or Non -Resident Bidder Certification
( ). (Mark one.)
7. The bidder is prepared to submit a financial and experience statement upon request.
8. The Prime Contractor and Subcontractor(s), which have performed an aggregate of $10,000.00 in work for
the City in the current calendar year, are prepared to submit an AAP or Update and an EOC, within ten (10)
days of notification that the bid submitted is lowest and acceptable.
9. The bidder has received the following Addendum or Addenda:
Addendum No. Date
10. The bidder shall list the MBEIWBE subcontractor(s), amount of subcontracts and bid items on the City of
Waterloo Minority and/or Women Business Pre-bid Contact Information Form submitted with this Form of
Bid or Proposal. The apparent low Bidder shall submit a list of all other Subcontractor(s) to be used on this
Project to the City of Waterloo by 5:00 p.m. the business day following the day Bids on this Project are due
along with the Non -Collusion Affidavits of All Subcontractor(s).
The Contractor shall submit information on subcontractors on "SUBCONTRACTOR REQUEST AND
APPROVAL" Form to be provided by City prior to approval of contract.
The subcontractors listed on this proposal and/or submitted to the Contract Compliance Officer cannot be
changed except for the following reasons:
1) The City of Waterloo does not approve the subcontractors.
2) The subcontractors submit in writing that they cannot fulfill their subcontracts.
FORM OF BID
60287085
CONTRACT NO. 855 BF -2 of 3
Revised Per Addendum No. 1 -10/23/13
11. The bidder has filled in all blanks on this proposal. Those blanks not applicable are marked "none" or "NA".
12. The bidder has attached all applicable forms.
13. The Owner reserves the right to select alternates, delete line items, and/or to reduce quantities prior to the
award of a contract due to budgetary limitations.
(Name of Bidder)
(Date)
BY: Title
Official Address: (Including Zip Code):
I.R.S. No.
FORM OF BID
60287085
CONTRACT NO. 855 BF -3 of 3
MBE/WBE BUSINESS ENTERPRISE
PRE-BID CONTACT INFORMATION FORM
Prime Contractor Name: Project: Letting Date:
NO MBE/WBE SUBCONTRACTORS: If you are NOT using any MBE/WBE subcontractors to complete this project, sign below. Attach a brief explanation
as to why subcontracting was not feasible with this project. If any MBE/WBE subcontractors will be used, please use the bottom portion of this form.
Contractor Signature: Title: Date:
SUBCONTRACTORS APPLICABLE: You are required, in order for your bid to be considered responsive, to provide the information on this form showing
ALL of your MBE/WBE subcontractor contacts made for your bid submission. This information is subject to verification. Any questions should be directed to
Contract Compliance Office 319-291-4429.
You are required, in order for your bid to be considered responsive, to provide the information on this Form showing your MBE/WBE Business Enterprise
contacts made prior to your bid submission. This information is subject to verifications and confirmation.
If you are unable to identify MBE/WBE firms to perform portions of the work, please contact Louis Starks, Contract Compliance Officer, for assistance at (319)
291-4429.
In the event it is determined that the MBE/WBE Business Enterprise goals are not met, then before awarding the contract the City of Waterloo will make a
determination as to whether or not the apparent successful low bidder made good faith efforts to meet the goals.
TABLE OF INFORMATION SHOWING BIDDER'S PRE-BID
MBE/WBE BUSINESS ENTERPRISE CONTACTS
Quotes Received Quotation used in bid
MBE/WBE
Subcontractors
Dates
Contacted
Yes/No
Dates
Contacted
Yes/No
Dollar Amount Proposed to
be Subcontracted
(Form CCO-4) Rev. 06-20-02
MBE/WBE PARTICIPATION
60287085
CONTRACT NO. 855
M-6 of 6
SECTION 03 32 20
REMOVAL AND REPLACEMENT OF PCC SIDEWALK
PART 1 DESCRIPTION
1.01 GENERAL
A. Work under this section includes removal of PCC sidewalk and construction of new PCC sidewalk.
B. SPECIFICATIONS
1. IDOT Specifications - Term "IDOT Specifications" in this section refers to Standard
Specifications for Highway and Bridge Construction, Series of 2012, Iowa Department of
Transportation, including current revised and supplemental specifications.
PART 2 PRODUCTS
2.01 MATERIALS
1. PC concrete for new sidewalk shall meet the requirements of Section 2511 of the IDOT
Specifications.
PART 3 EXECUTION
3.01 EXECUTION
A. Sidewalk removal shall be in accordance with Section 2511 of the IDOT Specifications.
B. Sidewalk construction shall be in accordance with Section 2511 of the IDOT Specifications.
* * * END OF SECTION * * *
03 32 20-1 60287085 -4th St Bridge Slope