HomeMy WebLinkAboutAspro Inc-10/21/2013CITY OF WATERLOO, IOWA CHANGE or EXTRA WORK ORDER NO. 5 PROJECT: F.Y. 2013 STREET RECONSTRUCTION PROGRAM, CONTRACT NO. 832 Date Prepared: October 23, 2013 AMOUNT: $ 7,111.40 INCREASE TO: ASPRO, INC. , Contractor You are hereby ordered to make the following changes from the plans and specifications or perform the following extra work on your contract dated May 13, 2013 B. C. Description of change to be made or extra work to be done: 5001 Remove existing concrete paving on Washington St. south of the SportsPlex between W. 3rd and W. 2nd 5002 Remove existing sidewalk on Washington St. south of the SportsPlex between W. 3`d and W. 2nd 5003 Saw cut for removal at W. 3rd and Washington St. 5004 Remove two existing inlets Reason for ordering change or extra work: 5001-5004 the City is responsible for removal of the remaining paving, inlets and sidewalk in this area Settlement for cost of work to be made as follows: 5001 Concrete Paving Removal 5002 Sidewalk Removal 5003 Saw Cut 5004 Remove Existing Structure ASPRO, INC. 1,268.4 SY @ $4.25/ SY = $ 5,390.70 66.4 SY @ $4.25/SY = $ 282.20 90.0 LF @ $4.25/LF = $ 382.50 2 @ $528.00 Each = $ 1,056.00 TOTAL INCREASE _ $ 7,111.40 BY: TITLE: Date /19 TOR /7_143 APPROVED: eg/l/(ILJ`,��irnr `/// //3 City Engineer Date