HomeMy WebLinkAboutAllied Manatts Group LLC-11/5/2012CHANGE ORDER NO. 3 Owner Waterloo Regional Airport, City of Waterloo, Iowa Date September 28, 2012 Project Rehabilitate Apron Phase 3A Owner's Contract No. FAA AIP Project No. 3-19-0094-38 Contractor Allied Manaus Group LLC Date of Contract Start June 20, 2011 You are directed to make the following changes in the Contract Documents. Description: Item No. Description Unit Unit Price Quantity Amount 3 Pavement Removal SY $7.00 (151.3) ($1,059.10) 4 Storm Sewer Pipe Removal LF $25.00 (5.0) ($125.00) 6 Unclassified Excavation CY $12.00 27.8 $333.60 7 Crushed Aggregate Base Course CY $43.00 (58.6) ($2,519.80) 8 Portland Cement Concrete Pavement - 8" Thickness SY $42.00 (45.6) ($1,915.20) 9 Portland Cement Concrete Pavement - 12" Thickness SY $46.00 (133.5) ($6,141.00) 11 Apron Marking (Yellow-Reflective-Waterbome) SF $3.40 (78.5) ($266.90) 12 Apron Marking (Black -Non -Reflective -Waterborne) SF $2.60 146.0 $379.60 100 Additional Depth Pavement Removal SY $5.40 (4.1) ($22.14) 102 Special Backfill (Recycled PCC Material) CY $32.00 9.0 $288.00 Total Amount of Change Order ($11,047.94) Reason for Change Order: This change order is necessary to adjust all final field measured quantities to contract. They are all based on final in-place measurements of quantities. All are within five percent of the authorized quantities except Item 7, Item 11 and Item 12. Item No. 7 - Crushed Aggregate Base Course is below authorized quantity because the actual amount is a direct relationship with the amount of PCC pavement placed. The pavement area placed was less than original plan quantity. Item No. 11 - Apron Marking (Yellow -Reflective -Waterborne) is less than plan quantity because the length of the taxiway edge marking and the non -movement marking were shorter than the amount shown on the plans. Less existing paint marking were disturbed by construction than anticipated. Rehabilitate Apron Phase 3A CO -2 Project No — 60218987 1 Item No. 12 - Apron Marking (Black -non -Reflective -Waterborne) was increase to match the existing marking on either side of this project area. The outer black outline was painted at 12" wide instead of 6" wide as shown on the plans. CONTRACT PRICE CONTRACT TIMES (Calendar Days) To substantial To final completion completion Original: $ 296,934.00 Original: Previous C.O.s (ADD): $ 20,400.00 Previous C.O.s (ADD): This C.O. (ADD): $ (11,047.94) This C.O. (ADD): Contract Price with all REVISED: approved Change Orders: $ 306,286.06 60 0 0 60 Original Completion Date: 60 Revised Completion Date: 60 It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s) ordered herein, including all impact, delays, and acceleration costs. Other than the dollar amount and time allowance listed above, there shall be no further time or dollar compensation as a result of this Change Order. THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL STIPULATIONS AND COVENANTS OF THE CON TRACT SHALL APPLY HERETO. RECO 1 =ED.111.•••00* Engineer (A APPRO ,A4D :�G By: _.4.xril 61/zg /1--- d Signature) Date 5( (9-6 Owner (Authorized Signature) Date ACCEP 1'ED: By:IP � Contractor (Authorize ignature) Date Rehabilitate Apron Phase 3A CO -2 Project No — 60218987 2