HomeMy WebLinkAboutDon Gardner Construction-5/29/2012*AIAt Document G701 TM- 2001 Change Order PROJECT (Name and address): 11014 Waterloo Center for the Arts Window Replacement TO CONTRACTOR (Name and address): Don Gardner Construction Co. Inc 315 LaPorte Road Waterloo, IA 50702 CHANGE ORDER NUMBER: 005 DATE: May 17, 2012 ARCHITECT'S PROJECT NUMBER: 11014 CONTRACT DATE: August 12, 2011 CONTRACT FOR: General Construction OWNER: El ARCHITECT: 0 CONTRACTOR: 0 FIELD: 0 OTHER: 0 THE CONTRACT IS CHANGED AS FOLLOWS: (Include, where applicable, any undisputed amount attributable to previously executed Construction Change Directives) 1. To adjust the new Contract Sum to not reflect the amount not approved in CO #3 but carried forward by AIA software to CO #4. DEDUCT: 5,514.00 The original Contract Sum was The net change by previously authorized Change Orders The Contract Sum prior to this Change Order was The Contract Sum will be decreased by this Change Order in the amount of The new Contract Sum including this Change Order will be $ 178,974.00 $ 4,379.47 $ 183,353.47 $ 5,514.00 $ 177,839.47 The Contract Time will be increased by Zero (0) days. The date of Substantial Completion as of the date of this Change Order therefore is NOTE: This Change Order does not include changes in the Contract Sum, Contract Time or Guaranteed Maximum Price which have been authorized by Construction Change Directive until the cost and time have been agreed upon by both the Owner and Contractor, in which case a Change Order is executed to supersede the Construction Change Directive. NOT VALID UNTIL SIGNED BY THE INVISION Architecture ARCHITECT, CONTRACTOR AND OWNER. ARCHITECT (Firm name) PO Box 1800, Waterloo, IA 50704-1800 ADDRE S� Don Gardner Construction Co. Inc CONTRACTOR (Firm name) 315 LaPorte Road, Waterloo, IA 50702 City of Waterloo OWNER (Firm name) City Hall, 715 Mulberry Street, Waterloo, Iowa 4f 03 SS BY (Si ature) Jos .' . Demmer, AIA (Ted name) .5/.II/12. DATE BY (Signature Mark Gardner (Typedme) DATE (Signature) % 1 k r. (Typed name) 5llPTl9— DATE AIA Document G701 — 2001. Copyright © 1979, 1987, 2000 and 2001 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and Will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 11:34:43 on 05/17/2012 under Order No.5896542442_1 which expires on 07/19/2012, and is not for resale. User Notes: (1364551010) !'AIA. MINIIIIIE Change Order Document G701' - 2001 PROJECT (Name and address): 11014 Waterloo Center for the Arts Window Replacement TO CONTRACTOR (Name and address): Don Gardner Construction Co. Inc 315 LaPorte Road Waterloo, IA 50702 CHANGE ORDER NUMBER: 003 DATE: March 20, 2012 ARCHITECT'S PROJECT NUMBER: 11014 CONTRACT DATE: August 12, 2011 CONTRACT FOR: General Construction OWNER: ❑ ARCHITECT: ❑ CONTRACTOR: 0 FIELD: 0 OTHER: ❑ THE CONTRACT IS CHANGED AS FOLLOWS: (Include, where applicable, any undisputed amount attributable to previously executed Construction Change Directives) 1. Cost associated with adding the following construction to the south stair, as shown in PR #2: a. 9'-0" tall aluminum storefront framing with glazing b. 7'-0" tall aluminum medium style door with full glass c. Door hardware as indicated in PR #2 ADD: $5,514.00 The original Contract Sum was The net change by previously authorized Change Orders The Contract Sum prior to this Change Order was The Contract Sum will be increased by this Change Order in the amount of The new Contract Sum including this Change Order will be The Contract Time will be increased by Zero (0) days. The date of Substantial Completion as of the date of this Change Order therefore is $ 178,974.00 $ -6,308.53 $ 172,665.47 $ 5,514.00 $ 178,179.47 NOTE: This Change Order does not include changes in the Contract Sum, Contract Time or Guaranteed Maximum Price which have been authorized by Construction Change Directive until the cost and time have been agreed upon by both the Owner and Contractor, in which case a Change Order is executed to supersede the Construction Change Directive. NOT VALID UNTIL SIGNED BY THE ARCHITECT, CONTRACTOR AND OWNER. INVISION Architecture Don Gardner Construction Co. Inc ARCHITECT (Firm name) CONTRACTOR (Firm name) PO Box 1800, Waterloo, IA 50704-1800 315 LaPorte Road, Waterloo, IA 50702 ADDRESS ADDRESS BY (Signature) BY (Signature) Joshua Demmer, AIA Mark Gardner (Typed name) (Typed name) DATE DATE City of Waterloo OWNER (Firm name) City Hall, 715 Mulberry Street, Waterloo, Iowa 50703 ADDRESS BY (Signature) C e5 (t . C- amt--t- (Typed name) 1*(P-e4 DATE AIA Document G701 TM - 2001. Copyright © 1979, 1987, 2000 and 2001 by The American Institute of Architects. All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA' Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 14:54:58 on 03/20/2012 under Order No.5896542442_1 which expires on 07/19/2012, and is not for resale. User Notes: (726153558) AIA Document G7014' - 2001 Change Order PROJECT (Name and address): 11014 Waterloo Center for the Arts DATE: Window Replacement CHANGE ORDER NUMBER: 004 TO CONTRACTOR (Name and address): Don Gardner Construction Co. Inc 315 LaPorte Road Waterloo, IA 50702 ARCHITECTS PROJECT NUMBER: 11014 CONTRACT DATE: August 12, 2011 CONTRACT FOR: General Construction OWNER: ❑ ARCHITECT: D CONTRACTOR: ❑ FIELD: ❑ OTHER: ❑ THE CONTRACT IS CHANGED AS FOLLOWS: (Include, where applicable, any undisputed amount attributable to previously executed Construction Change Directives) 1. Cost associated to provide and install new HM frame and glass, re -use existing doors and hardware and relocate exit sign. Per Don Gardner Construction document dated April 11, 2012. ADD: $5,174.00 The original Contract Sum was The net change by previously authorized Change Orders The Contract Sum prior to this Change Order was Contract Sum will be increased- by this Change Order in the amo� of The new Contract Sum including this Change Order will be $ 178,974.00 $ -794.53 $ 178,179.47 $ 5,174.00 $ 183,353.47 The Contract Time will be increased by Zero (0) days. The date of Substantial Completion as of the date of this Change Order therefore is NOTE: This Change Order does not include changes in the Contract Sum, Contract Time or Guaranteed Maximum Price which have been authorized by Construction Change Directive until the cost and time have been agreed upon by both the Owner and Contractor, in which case a Change Order is executed to supersede the Construction Change Directive. NOT VALID UNTIL SIGNED BY THE ARCHITECT, CONTRACTOR AND OWNER. INVISION Architecture ARCHITECT (Firm name) Don Gardner Construction Co. Inc CONTRACTOR (Firm name) PO Box t00, Waterloo, IA 50704-1800 315 LaPorte Road, Waterloo. IA 50702 ADD B (; gnature) Jo„ ua Demmer, AIA yped n e)/ / %Z DATE Y (. ignaturef Mark Gardner (Type n ) DATE City of Waterloo OWNER (Firm name) City Hall, 715 Mulberry Street, Waterloo, Iowa 50703 ADDRESS BY (Signature) Buck Clark (Typed name) DATE AIA Document G701", — 2001. Copyright © 1979, 1987, 2000 and 2001 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of thls AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 14:47:26 on 05/01/2012 under Order No.5896542442 1 which expires on 07/19/2012, and is not for resale. User Notes: (879391313)