DONALD STREET IMPROVEMENTS
U.S. HIGHWAY 63 TO MILDRED STREET
WATERLOO, IOWA
SUPPLEMENTAL AGREEMENT NO. 1
WHEREAS, a Professional Services Agreement was entered into by the City of Waterloo, Iowa
(City), and AECOM Technical Services, Inc. (Consultant), of Waterloo, Iowa, dated October 6,
2010, for the preliminary design, final design and construction review for improvements on Donald
Street from U.S. Highway 63 to Mildred Street in Waterloo, Iowa; and
WHEREAS, the City and Consultant desire to amend the previous agreement to include
engineering services during the construction phase of the Donald Street Improvements.
NOW THEREFORE, it is mutually agreed to amend the original Professional Services Agreement
as follows:
I. SCOPE OF SERVICES
Services to be provided under this supplemental agreement include the construction
staking, review, material testing and contract administration for the construction of the
Donald Street Improvements from U.S. Highway 63 to Mildred Street. The scope of
services is further defined by the following tasks:
Task 1. Preconstruction Conference. Assist the City with conducting the preconstruction
conference and have appropriate representative staff attend. This task includes conducting
the meeting and preparing minutes.
Task 2. Construction Staking. Provide horizontal and vertical control, including the
following items:
a. Set Project Control
b. Mark Removals
c. Set Stakes for Erosion Control
d. Set Stakes at 50 -Foot Intervals for Grading
e. Set Stakes for Sanitary Sewer and Manhole Adjustments
f. Set Stakes for Water Services
g. Set Stakes for Storm Sewer
h. Set Stakes for Paving and Intersections
i. Set Stakes for Concrete Driveways
j. Set Stakes for Sidewalks
k. Set Stakes for Recreational Trail
I. Set Locations for Paint Markings
Task 3. Interpret Plans and Specifications. Interpret the intent of the plans and
specifications for general compliance with the construction contract. The Consultant will
not, however, guarantee the performance of any contractor.
Task 4. Shop Drawing Review. Review work drawings, samples and other submittals of the
contractor only for general conformance to the design concept of the project and for general
compliance with the construction contract. Article 1105.03, Iowa DOT Standard
Specifications for Highway and Bridge Construction, will apply.
A=COM
Task 5. Progress and Quality of Construction. Maintain direct contact with the City's
representative or his authorized representative to the extent necessary to inform the City's
representative of the progress and quality of construction work performed. Provide the
necessary qualified staff at the job site to act under the authority of the City's
representative, and observe and review the work in progress and determine whether the
work is in general conformity with the contract plans and specifications. It is understood
that responsibility for the correctness of every detail of construction is beyond the scope of
this agreement. The Consultant shall not assume management or direction of the
contractor's operations or any utility company's operations. For estimating purposes,
construction activity in the field is anticipated at 20 weeks, with average level of service 30
hours per week for 10 weeks and 20 hours per week for 9 weeks.
Nothing in this agreement shall be construed as giving the Consultant the responsibility or
authority to direct or supervise construction methods, means, techniques, procedures or
safety methods used by the contractor, subcontractors, or utility companies performing the
actual construction work. Neither observations by the Consultant nor inspections, tests or
approvals, shall relieve the contractor, subcontractors or utility companies from their
obligation to perform the work in accordance with the requirements of the contract
documents.
The contractor has ultimate responsibility to monitor all his work to ensure proper quality,
safety and completion within the contract time, as do the utility companies involved in this
project.
Task 6. Testing. Consultant will complete necessary earthwork, density and P.C.C.
verification testing for the project as required by Iowa DOT's Materials Department
Instruction Memorandums and Iowa DOT's Construction Manual. The contractor shall be
responsible for certified plant inspection in accordance with the standard specifications.
Task 7. Reports. Prepare and submit daily, weekly and monthly reports as required by
Iowa DOT's Materials Department Instruction Memorandums and Iowa DOT's Construction
Manual. Also includes preparation and submittal of change and extra work orders,
subcontract requests and other forms as are normally utilized by the Iowa DOT on
construction projects. Reports are to be submitted per Iowa DOT Standards for reporting,
and copies of reports are to be submitted to the City.
Task 8. Estimates. Make monthly or bi-monthly reports to the City's representative, or his
authorized representative, of the estimated amount of materials furnished and delivered
and the work performed. Review and approve estimates for progress and final payment.
Task 9. Pay Quantities. Measure and document construction pay quantities and perform
functions necessary to assist with funding reimbursement for the project.
Task 10. Claims. Consider and evaluate contractor's suggestions for modifications and
report them with recommendation to the City. Prepare and assist the City and contractor in
processing contract change orders.
Task 11. Final Construction Review. Conduct the final construction review with
representatives of the Iowa DOT and City at completion of the project. The Consultant shall
state his opinion as to whether the project was completed in substantial conformance with
the Plans and Specifications and recommend acceptance thereof.
Task 12. Record Drawings. Prepare record drawings conforming to the construction
records provided to the Consultant by the contractor during the construction process.
A=COM
Task 13. Project Close -Out. Complete quantities and materials audit in compliance with
Iowa DOT standards. Prepare final acceptance documents, as required by Iowa DOT.
Task 14. Proiect Administration. Attend periodic construction meetings and conduct
intraoffice administration and coordination of the project.
II. COMPENSATION
The Consultant shall be reimbursed for the actual costs incurred in accordance with
Article 3 of the original agreement.
The estimated actual costs, fixed fee, contingency and maximum amount payable for this
supplemental agreement, as stated below and as shown in Attachment A, are to be
segregated from those covered under the original agreement.
Estimated Actual Costs $164,160.00
Fixed Fee 20,980.00
Contingency 7,000.00
Maximum Amount Payable 192,140.00
III. In all other respects, the obligations of the City and Consultant shall remain as specified in
the Professional Services Agreement dated October 6, 2010.
IN WITNESS WHEREOF, the parties hereto have executed this Supplemental Agreement No. 1 as
of the dates shown below:
AECOM TECHNICAL SERVICES, INC.
CITY OF
By
Sub -District Manager
TERLOO, IOWA
61,
Ernest G. Clark, Mayor
IOWA DEPARTMENT OF TRANSPORTATION
ACCEPTED FOR AUTHORIZATION
By
Robert Welper, P.E.
Local Systems Engineer
District 2
L:\work\ADMIN\AGREE\SUPPLE\SA1 WatDonaldStrlmprUs63toMildred.docx
Date April 17, 2012
Date Auk 1, i P---
Date_
Attachment A
Donald Street Improvements
U.S. Highway 63 to Mildred Street
Waterloo, Iowa
Construction Related Services
Cost Analysis
L Direct Labor Cost (AECOM Technical Services)
Category Hours Rate/Hour Amount
Senior Professional 0 $83.50 $0.00
Project Professional 260 $59.60 $15,496.00
Staff Professional 40 $40.00 $1,600.00
Professional 0 $32.00 $0.00
CADD Operator 11 40 $30.00 $1,200.00
CADD Operator I 0 $21.00 $0.00
Senior Technician 1,190 $32.00 $38,080.00
Technician 160 $25.50 $4,080.00
Project Support 60 $27.00 $1,620.00 $62,076.00
1750
II. Payroll Burden and Overhead Provisional Costs 160.00% $99,321.60
III. Direct Project Expenses
Category Units Rate/Uni Amount
Mileage 3000 0.51 1,530.00
Per Diem 0 40.00 0.00
Lodging 0 80.00 0.00
B/W Copies 2000 0.06 120.00
Color Copies 500 0.12 60.00
EDM Equipment 40 12.50 500.00
GPS Equipment 10 25.00 250.00
Miscellaneous, Other 300.00 $2,760.00
IV. AECOM Estimated Actual Costs $164,157.60
Rounded $164,160.00
V. Subcontract Expense
$0.00
VI. Estimated Actual Costs $164,160.00
VII. Fixed Fee $20,980.00
VIII. Contingency $7,000.00
AECOM Technical Services $7,000.00
Craig Ritland Landscape Architects $0.00
Robinson Engineering Company $0.00
IX. Maximum Amount Payable $192,140.00
Page 1 of 1
JEFF BALES
From: JEFF BALES
Sent: Wednesday, May 30, 2012 10:13 AM
To: 'Durbahn, Mark'
Subject: STP -U-8155(714)-70-07 - Supplemental Agreement No. 1
Mark,
Please consider this e-mail your "Notice -To -Proceed" with work under this agreement effective
Wednesday, May 30th.
Jeff Bales
Associate Engineer
City of Waterloo
715 Mulberry Street
Waterloo, Iowa 50703
319-291-4312
5/30/2012
Attachment A
Donald Street Improvements
U.S. Highway 63 to Mildred Street
Waterloo, Iowa
Construction Related Services
Staff Hour Estimate
Description of Work
Senior
Prof.
Project
Prof.
Staff
Prof.
CADD
Op. 11
Senior
Tech
Tech
Project
Support
Total
1 Preconstruction Conference
12
6
18
2 Construction Staking
a. Set Pro ect Control,
4
4
b. Mark Removals8
,.,`
_-__,
c. Set Stakes for Erosion Control
, ,
2
2
4
d. Set Stakes at 50 -Foot Ir_ilsvAlii9Egading
16
16
32
e. Set Stakes for Sanita Sewer
4
4
8
f Set Stakes for Water Services4
4
8
Set Stakes for Storrn Sewer
40
40
. 80
h. Set Stakes for Paving & Intersections
48
48
96
i. Set Stakes for Concrete Driveways
j. Set Stakes for Sidewalks
24
24
48
6
4
6
4
12
8
k. Set Stakes for Recreational Trail
1. Set Locations for Paint Markin
_-___..
8
8
16
3 Interpret Plans & Specifications
32
8
40
Drawing Review16
4 Shy_
8
24
5 Progress & Quality of Construction
40
_
12
780
60
12
40
820
60
64
6 Testi__ ui
__.
7 Reports
8 Estimates
16
12
28
9 Pay Quantities
8
4
40
52
10 Claims
32
4
44
20
80
52
11 Final Construction Review
32
12 Record Drawings
8
12
40
8
40
56
52
13 Project Closeout
14 Pr ect Administration40
20
20
80
TOTAL HOURS
0
260
40
40
1,190
160
60
1,750