HomeMy WebLinkAboutWaterloo Water Works-4/23/2012CITY OF WATERLOO and WATERLOO WATER WORKS
WEST SHAULIS ROAD EXTENSION AND ANSBOROUGH AVENUE
RECONSTRUCTION, CITY CONTRACT No. 784
AGREEMENT
NOW on this 7-1/ day of i , 2012,
Works Waterloo Water ("Water Works") and th City of Waterloo, Iowa, (the "City")
enter into this Agreement for and in consideration of the mutual covenants and
promises contained herein and for other good and valuable consideration, the receipt
and sufficiency of which are hereby acknowledged.
I. RECITALS
WHEREAS, the roadway reconstruction and water main replacements and
extensions are to be constructed in the same corridors (refer below to E. AREA
COVERED) in which the parties have some interest, and are proposed to be
constructed in calendar year 2012; and
WHEREAS, the parties presently have varying degrees of responsibilities for the
roadway extension of West Shaulis Road and the reconstruction of Ansborough
Avenue, and the replacement and extension of the existing water main in the corridors
listed below in E. AREA COVERED; and
WHEREAS, the parties believe that the payments to be made to the contractor
would best be handled by the City.
NOW, THEREFORE, the parties agree as follows:
II. TERMS OF AGREEMENT
A. PURPOSE. Refer to Recitals.
B. JURISDICTION. The jurisdiction for responsibility for design, inspection
and funding shall be: Division 1 — City of Waterloo
Division 2 — Waterloo Water Works
Said responsibilities with respect to each division of the Project shall include
review and approval of any design changes or change orders and general
supervision of the work of that division.
C. FINANCING. The Water Works and the City shall share the costs for the
Project according to the following:
1. The Water Works shall pay for the entire cost of reconstruction or
extension of the water mains along the proposed corridors.
(Division 2). The Water Works shall also pay additional costs for a
portion of two Division 1 lump sum items, Mobilization, Construction
Survey, and Silt Fence. The Water Works share of Mobilization
shall be the sum of $3,500.00; the Water Works share of
Construction Survey shall be the sum of $1,400.00; and the Water
Works share of Silt Fence shall be the sum of $200.00.
2. The City shall pay for its appropriate share of the cost of the
roadway reconstruction along the proposed corridors. (Division 1).
3. The City shall be responsible for administering the payments to the
contractor and to bill the Water Works. The Water Works shall
make payment to the City within fifteen (15) days of said billing.
4. Financing for this Project, including changes to a division of the
Project that are later deemed to be necessary or advisable, shall
be the responsibility of each of the parties hereto as reflected in
this Agreement. Each party agrees to exercise diligence and good
faith to arrange all funding necessary to complete the Project on
the scheduled timeline.
D. ADMINISTRATION OF AGREEMENT. The Water Works shall prepare
plans, specifications, estimate of quantities, estimate of cost, etc., and submit
them to the City, to be included in the contract as Division 2. A licensed
professional engineer in the State of Iowa, who is a representative of the Water
Works, shall sign the Division 2 Plans and Specifications.
The City shall follow the current City bidding procedures for the Project and
administer the letting phase of this Project. The construction phase of this
Project shall be administered by the City for Division 1 and Water Works for
Division 2. The Water Works shall be notified of all meetings involving said
Project and shall have the right of review and acceptance for each of the
following phases for Division 2:
1. Bid Award Approval.
2. Final Construction Approval.
In all matters relating to administration of the Project, the parties agree to
cooperate in good faith and in a timely manner, to maintain open lines of
communications, and to have at least one person designated as the primary
contact for all issues concerning the Project.
E. AREA COVERED. The area covered by this Agreement shall be:
1. West Shaulis Road from Ansborough Avenue to Hawkeye Road.
2. Ansborough Avenue from West Shaulis Road to south of U.S.
Highway 20.
F. DURATION. This Agreement shall be in effect until completion of the
construction or termination by written agreement of all parties.
DATED this /r' day of 1 , 2012.
WATERLOO WATE' ORKS
By:
ATTEST:
Terry M. K
Board of r
Dennis Clark, General Manager and Board Secretary
STATE OF IOWA, BLACK HAWK COUNTY, ss:
On this IS TSF day of Ap arc 1 2012, before me, the
undersigned, a Notary Public in and for the State of Iowa, personally appeared Terry M.
Kuntz and Dennis Clark, to me personally known, and who, being by me duly sworn, did
say that they are the Board of Trustees Chairman and the Board Secretary,
respectively, of the Waterloo Water Works; and that the instrument was signed and
sealed on behalf of the utility by authority of its Board of Trustees as contained in the
Resolution adopted by the Board of Trustees, on the day of
, 2012, and that Terry M. Kuntz and Dennis Clark
acknowledged the execution of the instrument to be their voluntary act and deed and
the voluntary act and deed of the utility, by it voluntarily executed.
otary9ublic in and for the State of Iowa
Cnv�`earArno'ss;0,... Expires YYIe41 Iy �o�y
ATTEST:
Suzy Sch4es, City Clerk
CITY OF WATERLOO, IOWA
By:
STATE OF IOWA, BLACK HAWK COUNTY, ss:
rnest G. Clark, Mayor
On this day of( L , 2012, before me,
the undersigned, a Notary Public in a d for the State of Iowa, personally appeared
Ernest G. Clark and Suzy Schares, to me personally known, and who, being by me duly
sworn, did say that they are the Mayor and City Clerk, respectively, of the City of
Waterloo, Iowa; that the seal affixed to the foregoing instrument is the corporate seal of
the corporation, and that the instrument was signed and sealed on behalf of the
corporation by authority of its City Council as contained in the Resolution adopted by
the City Council, and r Council Action No. I �Jir6'7 ' of the City Council on the
day of-�, ,`Z_ , 2012, and that Ernest G. Clark
and Suzy Schares acknowledged the execution of the instrument to be their voluntary
act and deed and the voluntary act and deed of the corporation, by it voluntarily
executed.
ry P blic in and for the State of to
3 wl/tm