HomeMy WebLinkAboutB & B Builders and Supply-1/30/2012Cc7.o1e� 7i�1 ,70 CI CITY OF WATERLOO, IOWA CHANGE or EXTRA WORK ORDER NO. 1 (Revised) PROJECT: FY 2012 SIDEWALK REPAIR ASSESSMENT PROGRAM - ZONE 1 CONTRACT NO. 811 Date Prepared: January19, 2012 AMOUNT: $175,219.38 DECREASE TO: B & B BUILDERS AND SUPPLY , Contractor You are hereby ordered to make the following changes from the plans and specifications or perform the following extra work on your contract dated Auqust 15, 2011. A. Description of change to be made or extra work to be done: Adjust original construction quantities to actual construction quantities. B. Reason for ordering change or extra work: As -built quantities varied for some bid items C. Settlement for cost of work to be made as follows: Compensation already made to contractor through bid items. See attached summary. TOTAL DECREASE 02/7 Da CONTRACTOR B & B BUILDERS AND SUPPLY ce-N-9,,,o a/1/1'A Date APPROVED: $175,219.38 BY: /-e!o c Z O / Date TITLE: Dt )i2er Change Order No. 1 -Revised City Engineer 1/30/1a Date Contract No. 811 Sheet 1 of 1