HomeMy WebLinkAboutPeterson Contractors, Inc-11/7/2011CHANGE ORDER NO. 1
Owner: City of Waterloo, Iowa Date: October 18, 2011
Project: FY 2011 Anaerobic Lagoon Influent Pump Station
Owner's Contract No.: 807 Contractor: Peterson Contractors, Inc.
Date of Contract Start: August 17, 2011 $ 1,145,000.00
You are directed to make the following changes in the Contract Documents. Description:
8001: Provide Xypex Integral Waterproofing Additive toCast in -Place Concrete Per Project Specifications - ADD - LUMP SUM $4,275.00
Reason for Change Order:
8001: Contractor's concrete supplier inadvertently did not include material cost of waterproofing in bid price
CONTRACT PRICE
CONTRACT TIMES (Calendar Days)
To
Completion
Original: $ 1,145,000.00 Original: December30, 2011
Previous C.O.s (ADD/DEDUCT): $ Previous C.O.s (ADD/DEDUCT):
This C.O. (ADD/DEDUCT): $ 4,275.00 This C.O. (ADD/DEDUCT):
Contract Price With All Approved
Change Orders: $ 1,149,275.00 REVISED: December 30, 2011
Revised Completion Date: December 30, 2011
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s) ordered herein, including all impact, delays, and
acceleration costs. Other than the dollar amount and time allowance listed above, there shall be no further time or dollar compensation as a result of this Change Order.
APPROVED:
By:
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO
wrier (Authoriz-4Ignatu
ACCEPTED:
By:
Date:
on �, : d Signature) Date
L:\work\project\113632\admn\60184424.41-Anaerobic Lagoon Specs\CO 1.doc
72/7
AECOM
113632.41 1
Project No. Change Order No.