HomeMy WebLinkAboutPeterson Construction-9/26/2011Owner City of Waterloo
Project FY 2010 River Renaissance Lower Plaza
Owner's Contract No. 763
CHANGE ORDER NO. 12
Date September 20, 2011
3 - CJ
Contractor Peterson Contractors Inc.
Date of Contract Start April 15, 2010 $ 3,189,424.95
You are directed to make the following changes in the Contract Documents. Description:
12-1 Provide Scofield Chromix Coloring Agent and Lithochrome ColorWax
(12,465 SF @ $2.86/SF) $35,649.90
TOTAL ADDITIONS $35,649.90
Reason for Change Order:
12-1 Based on the results obtained on other downtown Waterloo Vision Iowa projects. it was decided to use the Scofield products in lieu of
the originally bid coloring agents..
CONTRACT PRICE CONTRACT TIMES
To Substantial To Final
Completion Completion
Original: $ 3,189,424.95 Original Completion Date: 11/30/2010 12/31/2010
Previous C.O.s (ADD/DEDUCT): $ 167,505.85 Revised Completion Date: No Change No Change
This C.O. (ADD/DEBUUCT): $ 35,649.90
Contract Price with all
approved Change Orders:
$ 3,393,580.70
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s) ordered herein,
including all impact, delays, and acceleration costs. Other than the dollar amount and time allowance listed above, there shall be no further time
or dollar compensation as a result of this Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO.
APPR S ED:
By.
Owner (Authorized Signature)
W -1:/t1-?- ).\
By,�
Qt1(a "Poll
Date
Contractor (Authorized Signature) Date
Date
AECOM
60155128 / 12
Project No. Change Order No.
L:\work\project\60155128\eng\Change Orders\Lower Plaza CO# 12.docx