HomeMy WebLinkAboutAllied Manatts Group LLC-8/8/2011CHANGE ORDER NO. 1
Owner Waterloo Regional Airport, City of Waterloo, Iowa Date July 22, 2011
Project Rehabilitate Apron Phase 3A
Owner's Contract No. FAA AIP Project No. 3-19-0094-38 Contractor Allied Manatts Group LLC
Date of Contract Start June 20, 2011
You are directed to make the following changes in the Contract Documents. Description:
Reason for Change Order:
During the removal of existing pavement it was determined that there is an underlying concrete slab
below the apron surface area. This buried and un -bonded slab had been encountered on the previous
apron reconstruction project. There was no buried slab under the Taxiway A project which is directly
north of this project. Based on the previous apron project it was believed that this buried slab had been
removed as part of the previous apron project. The joint lines indicated a change in pavement section
and/or base section.
The area of this buried slab extends under most of the area for Phase 3A. As a result of the additional
pavement depth the unclassified excavation quantity will be deleted from the project. Special Backfill
(recycled concrete pavement) shall be provided to fill the depth between the pavement removal limits
and the P-208 base course.
Rehabilitate Apron Phase 3A CO -1 Project No — 60218987
1
Item No.
Description
Unit
Unit Price
Quantity
Amount
6
Unclassified Excavation
CY
$12.00
(430.0)
($5,160.00)
100
Additional Depth Pavement Removal
SY
$5.40
3,325.0
$17,955.00
101
Special Backfill (Recycled PCC Material)
CY
$32.00
560.0
$17,920.00
Change Order Subtotal
$30,715.00
Total Amount of Change Order $30,715.00
Reason for Change Order:
During the removal of existing pavement it was determined that there is an underlying concrete slab
below the apron surface area. This buried and un -bonded slab had been encountered on the previous
apron reconstruction project. There was no buried slab under the Taxiway A project which is directly
north of this project. Based on the previous apron project it was believed that this buried slab had been
removed as part of the previous apron project. The joint lines indicated a change in pavement section
and/or base section.
The area of this buried slab extends under most of the area for Phase 3A. As a result of the additional
pavement depth the unclassified excavation quantity will be deleted from the project. Special Backfill
(recycled concrete pavement) shall be provided to fill the depth between the pavement removal limits
and the P-208 base course.
Rehabilitate Apron Phase 3A CO -1 Project No — 60218987
1
CONTRACT PRICE
Original: $ 296,934.00
Previous C.O.s (ADD): $ 0.00
This C.O. (ADD): $ 30,715.00
Contract Price with all
approved Change Orders: $ 327,649.00
CONTRACT TIMES (Calendar Days)
To substantial To final
completion completion
Original:
Previous C.O.s (ADD):
This C.O. (ADD):
REVISED:
60
0
0
60
Original Completion Date: 60
Revised Completion Date: 60
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the
change(s) ordered herein, including all impact, delays, and acceleration costs. Other than the dollar amount and time
allowance listed above, there shall be no further time or dollar compensation as a result of this Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO.
RECOMMENDE
By:
Engineer (Aut
APPRO
By:
67 2S— 26J/
ed Signature) 1 Dat
7(//14/
Date
Owner (Authorized Signature)
ACCEPTED:
By:
Cgntracto (� j orized Signature)
o-7/Zz/z011
Date
Rehabilitate Apron Phase 3A CO -1 Project No — 60218987