HomeMy WebLinkAboutAllied Manatts Group LLC-8/8/2011CHANGE ORDER NO. 1 Owner Waterloo Regional Airport, City of Waterloo, Iowa Date July 22, 2011 Project Rehabilitate Apron Phase 3A Owner's Contract No. FAA AIP Project No. 3-19-0094-38 Contractor Allied Manatts Group LLC Date of Contract Start June 20, 2011 You are directed to make the following changes in the Contract Documents. Description: Reason for Change Order: During the removal of existing pavement it was determined that there is an underlying concrete slab below the apron surface area. This buried and un -bonded slab had been encountered on the previous apron reconstruction project. There was no buried slab under the Taxiway A project which is directly north of this project. Based on the previous apron project it was believed that this buried slab had been removed as part of the previous apron project. The joint lines indicated a change in pavement section and/or base section. The area of this buried slab extends under most of the area for Phase 3A. As a result of the additional pavement depth the unclassified excavation quantity will be deleted from the project. Special Backfill (recycled concrete pavement) shall be provided to fill the depth between the pavement removal limits and the P-208 base course. Rehabilitate Apron Phase 3A CO -1 Project No — 60218987 1 Item No. Description Unit Unit Price Quantity Amount 6 Unclassified Excavation CY $12.00 (430.0) ($5,160.00) 100 Additional Depth Pavement Removal SY $5.40 3,325.0 $17,955.00 101 Special Backfill (Recycled PCC Material) CY $32.00 560.0 $17,920.00 Change Order Subtotal $30,715.00 Total Amount of Change Order $30,715.00 Reason for Change Order: During the removal of existing pavement it was determined that there is an underlying concrete slab below the apron surface area. This buried and un -bonded slab had been encountered on the previous apron reconstruction project. There was no buried slab under the Taxiway A project which is directly north of this project. Based on the previous apron project it was believed that this buried slab had been removed as part of the previous apron project. The joint lines indicated a change in pavement section and/or base section. The area of this buried slab extends under most of the area for Phase 3A. As a result of the additional pavement depth the unclassified excavation quantity will be deleted from the project. Special Backfill (recycled concrete pavement) shall be provided to fill the depth between the pavement removal limits and the P-208 base course. Rehabilitate Apron Phase 3A CO -1 Project No — 60218987 1 CONTRACT PRICE Original: $ 296,934.00 Previous C.O.s (ADD): $ 0.00 This C.O. (ADD): $ 30,715.00 Contract Price with all approved Change Orders: $ 327,649.00 CONTRACT TIMES (Calendar Days) To substantial To final completion completion Original: Previous C.O.s (ADD): This C.O. (ADD): REVISED: 60 0 0 60 Original Completion Date: 60 Revised Completion Date: 60 It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s) ordered herein, including all impact, delays, and acceleration costs. Other than the dollar amount and time allowance listed above, there shall be no further time or dollar compensation as a result of this Change Order. THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO. RECOMMENDE By: Engineer (Aut APPRO By: 67 2S— 26J/ ed Signature) 1 Dat 7(//14/ Date Owner (Authorized Signature) ACCEPTED: By: Cgntracto (� j orized Signature) o-7/Zz/z011 Date Rehabilitate Apron Phase 3A CO -1 Project No — 60218987 2