Loading...
HomeMy WebLinkAboutIowa Department of Transportation-8/1/2011 (3)Iowa Department of Transportation District 2, 1420 4th Street SE, Mason City, IA 50401-4438 641-423-7584 or 800-477-4368, Fax 641-423-0246 August 15, 2011 Mr. Jeff Bales City of Waterloo 715 Mulberry Street Waterloo, IA 50703 Dear Jeff: Ref. No.: STP -U-8155(719)-70-07 Black Hawk County Attached for your records on the above referenced project are two fully -executed copies of Iowa DOT Supplemental Agreements #1 for the 2011 installation of wayfinding signage within downtown Waterloo. If you have any questions, please feel free to contact this office. Sincerely, illi- C. Mohorne, Engineering Techni an Senior District 2 Office WCM/Im Attachment cc: Kevin Galloway Records Center (319464-7913 July 26, 2011 500 Alain St., La Porte City, IA 50651 jdeeng@netins.net F.Y. 2011 INSTALLATION OF WAYFINDING SIGNAGE WITHIN DOWNTOWN WATERLOO IOWA DOT PROJECT NO. STP -U-8155(719)-70-07 CITY OF WATERLOO PROJECT NO. 783 SUPPLEMENTAL AGREEMENT #1 WHEREAS, a Professional Services Agreement is currently in place between the City of Waterloo, Iowa ("City") and JDE Engineering, PLC ("Consultant") dated March 21, 2011, and WHEREAS, additional material testing and certification procedures were determined to be necessary to document quality of materials to be incorporated into the finished work product, NOW THEREFORE, it is mutually agreed that this Supplemental Agreement #1 shall consist of the following: I. SCOPE OF SERVICES The scope of services shall consist of obtaining the following: • Certified Plant Inspection • Concrete Plant Monitoring • Gradation of the sand to be used under the brick pavers • Proctor of the modified subbase proposed for use under sidewalk areas • Compaction testing for modified subbase at each sidewalk installation location II. TIME OF BEGINNING AND COMPLETION Work under this supplemental agreement shall begin following approval of the City Council and execution of this agreement by the Mayor of the City of Waterloo. Work shall end when concrete base construction and sidewalk installation is completed by the Contractor. 1 I11. COMPENSATION The fee for the work detailed under "Section I. Scope of Services" is based on cost -plus -fixed -fee. The total cost of Supplemental Agreement #1 is $2,750. This fee is considered a maximum not -to -exceed cost. A revised fee schedule, and a copy of the Supplemental Services Agreement with Terracon, Inc. is attached to this agreement for review. IN WITNESS WHEREOF, the parties hereto have executed this Supplemental Agreement #1 as of the dates shown below: JDE ENGINEERING, PLC —7/2—(:/// Jirfi D. Ellis, P.E. Date Owner/Project Manager CITY OF WATE0, IOWA Ernest G. Clark Mayor IOWA DEPARTMENT OF TRANSPORTATION Accepted for FHWA Authorization* Robert Welper, P.E. Local Systems Engineer District 2 Date g//;s e,o// Date * The Iowa DOT is not a party to this agreement. However, by signing this agreement, the Iowa DOT is indicating the work proposed under this Agreement is acceptable for FHWA authorization of Federal funds. 2 JDE Engineering, PLC 500 Main Street La Porte City, Iowa 50651 Wayfinding Signage Project Fee Schedule Revised to Include Supplemental Agreement #1 1. Direct Labor Cost Employee Classification Hours Billing Rate Amount Project Manager 100.5 $95.00 $9,547.50 Design Engineer 0.0 $85.00 $0.00 Construction Observation Technician 171.0 $75.00 $12,825.00 Administrative Assistant 0.0 $40.00 $0.00 11. Direct Prosect Expenses 01. Subconsultant Costs IV. Estimate Actual Costs (I +11+1111 V. Contingency - Prime Only VI. Total Estimated Cost (IV + V + Vii Quantity Direct Labor Total = $22,372.50 Rate Amount Copies (each) = 1,100 $0.25 $275.00 Mileage = 165 $0.60 $99.00 Rental Car (days) = 0 $100.00 $0.00 Meals (each) = 0 $12.00 $0.00 Lodging (nights) = 0 $85.00 $0.00 Total Direct Expenses= $374.00 Craig Ritland Landscape Architects (specific rate of compensation) = Terracon Consultants, Inc. (cost plus fixed -fee) = $6,000.00 $4,540.00 Total Subconsultants = $10,540.00 $33,286.50 $6,402.40 $39,688.90 lierracon July 11, 2011 JDE Engineering 500 Main La Porte City, IA 50654 Attn: Mr. Jim Ellis P: (319) 464-7913 jdeeng@netins.net Re: Supplement to Agreement for Services Construction Materials Observation and Testing Services Waterloo Way Findings Waterloo, Iowa Terracon Project No. 13111037 Dear Mr. Ellis: Terracon would be pleased to provide construction materials observation and testing services for the above referenced project. Attached to this letter is our Supplement to Agreement for Services including Exhibits B and C. This supplement reflects the change to our scope of services as well as the related fee schedule. The invoices for our services will be submitted to your attention at the above referenced address. To accept this change, please sign and return one copy of this supplement to agreement to our office at the below address. We appreciate the opportunity to be of continued service to you on this project. Should you have any questions concerning the details of this Supplement to Agreement for Services, please contact this office. Sincerely, Terracon Consultants, Inc. Project Manager Cc: (2) - Client (1) - File Attachments: Exhibit C Supplement To Agreement For Services Rick Lockhart Office Manager Principal Terracon Consultants, Inc. 6612 Chancellor Drive, Ste. 102 Cedar Falls, Iowa 50613 P 319 277 4016 F 319 277 4320 terracon.com Geotechnical EnvironrnentaI Construction Materials • Facilities Proposed Way Findings (Plant Monitor and Inspection) Waterloo, Iowa Job and Proposal No. 13111037/ CF11061 R July 11, 2011 SCHEDULE A I. Direct Labor Costs: CATEGORY HOURS RATE/HR. AMOUNT Technician 1 11.92 Technician II 10 15.01 150 Technician IV 9 22.99 207 Driller 20.21 CAD Drafter 16.55 Administration / Secretary 3 16.63 50 Field Engineer 21.67 Project Engineer 25.97 Senior Project Manager 9 34.84 314 Senior Principal Engineer 0 50.00 0 Subtotal (Rounded) $720 II. Payroll Burden & Overhead Costs @ 198.87% (3 -year average - Rounded) $1,430 Ills. Direct Project Expense CATEGORY UNITS UNIT RATE AMOUNT Cylinder Molds 0 0.75 0 Mileage 200 0.50 100 Subtotal (Rounded) $100 IIIb. Direct Third -Party Expense Crop Damage Meals and Accommodations (per diem) Consumable & Misc. Supplies Other Third -Party Expenses IV. Estimated Costs (I+II+IIIa+IIIb) V. Fixed Fee (12% of I+II+IIIa, Rounded) VI. Total Cost plus Fee (IV+V) VII. Contingency (10% of IV, Rounded) VIII. Total with Contingency 100.00 Subtotal (Rounded) $0 $2,250 $270 $2,520 $230 $2,750 LO -9 'Ae9 211.90L LAO / L£OL 1 L£L:(JegwnN loa(oJd Jo lesodoJd leluewelddns uooeJJel) JequmN eouaJe;eH luewelddns :xed £I6L'19b'6I£ :eUO4d P9909 en '43 emmod el :e3ea 03CP LLZ'6I£ :xed 910P LLZ'66£ :euoyd £ 1909 two' 'sated .iepo3 Well 009 :ssaJPPv ZOI eilnS'OAl4asii eaueg3 2699 :ssaiPPH :epfJraweN JefeueW ioe(oid / Aelsi . ell 0 , : , .�:� weN 110Z/11/L :e3ea 7 • 1,41fj :A9 6upeeul6u3 ea(r :3uep0 vim suns • 0 uooc.uoj sUo3 s! eue31nsuo0 pue pa3daaoe s! 3uawalddn9 MILL 'peso pue anisuompuooou pazuo43ne Gam; Ilei ul anupuoo pays seolJueg �o; �ewae�6d 843;a pue suJJa3 IM 1343 qui pe)e.odIooul aJe llq!yxa Jo uogoos yolyM) euawelddnS slgl o3 0 liglyx3 u! Jo Mo lun ieso d ld leg Pelsls as!Mie43o ale sea/ sselun lesodwd leluewalddn9 1343 u! pa3els see; e43 3e pewaoped seo ues paBueyo Jo leuoplppe a43 Jo; uopesuedwoo iced Heys luep0 'uoliesuedwo0 'Z (luewa!ddnS oy3 qui peieiod.00ul ale llglgxa Jo uogoas goltM) 3uawalddn9 s!43 03 9 31glgx3 u! JO Moleq paq!Josep es!Mia43o aJe seoliues sselun gesodoid leluewaiddnS s,3ue31nsuo9 Gig ;o uopoas saoliues ;o edoos a43 u! pequosep aJe seol ues pa6uego Jo leuoplppe a43 ;o edoos ayl •seo;JueS ;o odooS • 6 •sool,ues Jo; 3uowooJ6y 843;0 lied pue owl pe)eJodJoou! s! 3uewelddn9 s141 '(3uawelddnS e43 qul pe)eJodioou! s! 3!glgxe Jo uopoas yolgM) 3uawalddns qui o v ilq!gx3 Jo '(,lesodwd le3uawelddnS.) L L0Z/L L/L Pelee lesodwd le3uowolddns s,lue31nsuo0;o uogoas uogeuuo/u! 1aa(oJc oyl ul ! aq!Josep es!Mie43o sse!un 'slues Jo; pJewooi6y eq; u! pegposep se 'lae(oJc eta uo 3uelp Jo; 3uellnsuo0 etq pepp oJd eq 03 sealAJOS paBueyo Jo leuoplpps Jo; (juellnsuo0.) *out 'slus31nsuo0 uooeJJel pue (Juan.) buueaulou3 lar uee*3eq s! (L90L Ld0 Jegwnu eouaJa;aI 3ueweai6y 140Z/Lie palep 3uawea'By leul6uo) saalAJes J0; 3uaweaJBy leu,Buo 1343 03 S301A113S VOA 1N3W33210V of 1N311113lddfS elgl S33d ONV S33IA213S AO 3dOOS 01 3ONVH3 S301A213S 21Od 1N3W33NOV 01 1N31N31dd11S uocauajL ATTACHMENT A Scope of Services (Original Contract - Dated 3-21-2011) 1. Assist in development of tax exemption certificates. These certificates would be delivered to the contractor. Certificates would be developed by the Waterloo City Clerk's Office, with assistance from JDE Engineering, and delivered to the contractor prior to the beginning of construction. 2. Develop a construction notebook for organization of construction documents. 3. Maintain bid tabulation and bid summary information following bid opening. 4. Develop a preconstruction conference agenda and sign -in sheet. 5. Conduct the Preconstruction Conference. 6. Produce minutes of the Preconstruction Conference meeting and provide a copy of the minutes to all parties in attendance. 7. Conduct progress meetings every 2 weeks during the construction phase of the project. These meetings could be conducted on-site during construction, or at a mutually agreed upon location (City Hall or contractors office, etc.). 8 Produce minutes of Progress Meetings and provide a copy of the minutes to all parties in attendance. 9. Obtain contracts, bonds, and certificates of insurance from the contractor prior to the beginning of construction and submit these to the owner. 10. Obtain the contractors work schedule prior to the beginning of construction. 11. Obtain signed Work in Right -of -Way Permitting from the Iowa DOT, prior to the start of construction, related to Exhibit 14 and Exhibit 15 of the final plans. 12. Issue a Notice -to -Proceed to the contractor. 13. Contact property owners directly adjacent to the project areas prior to the start of construction to inform them of the proposed work. 14. Observe the proper installation of traffic control. 15. Conduct daily review of traffic control condition and inform the contractor of needed maintenance. 16. Document traffic control condition on a daily basis. 17. Document the completion of utility locates in the area of construction prior to the beginning of work. 18. Mark with paint the proposed installation locations for each sign. 19. Meet with the contractor, Owner, and Craig Ritland Landscape Architect to obtain final approval for sign installation locations. 20. Conduct storm water related site inspections (the work area is less than 1 acre, however, any erosion from construction areas should be documented and the contractor notified to correct issues that may arise). 21. Obtain photos of work areas prior to the start of construction to document existing conditions, existing damage to sidewalks, and existing damage to street pavement. 22. Complete a daily working day log related to construction activity, and mail to all parties on a weekly basis. 23. Complete weekly working day reports during construction and mail to all parties on a weekly basis. 24. Print all e-mail and letter correspondence related to the contract and keep this information in the construction notebook. 25. Obtain concrete plant certifications for the plant(s) used to provide concrete for sign bases. 26. Obtain material certifications for concrete, steel, signs, sign posts, and materials used to manufacture the signs and sign posts. 27. Receive and obtain approvals for shop drawings for signs and sign posts. 28. Collect delivery tickets for materials (Le. sand, concrete, brick, steel). 29. Obtain material test results from Terracon Consultants, Inc. 30. Obtain photos during and after construction to document construction methods and the finished product. 31. Measure quantities in the field. 32. Develop pay estimates for review and approval by the contractor and the Owner. 33. Process change / extra work orders (if necessary). 34. Develop a Punch List of incomplete items and deliver to the contractor. 35. Prepare record drawings for submittal to the Owner. 36. Obtained lien waivers from material suppliers prior to the acceptance of work. 37. Develop a letter of acceptance for submittal to the City Council and the Iowa DOT upon project completion. 38. Submit the final project construction notebook to the Owner for their records. 39. Provide project related documentation to the Iowa DOT for final project audit to obtain final reimbursement of funds to the Owner. ATTACHMENT B Specifications for Project Deliverables (Original Contract - Dated 3-21-2011) 1. Develop a construction notebook for organization of construction documents. 2. Produce minutes of the preconstruction conference meeting. 3. Produce minutes of progress meetings. 4. Obtain signed Work in Right -of -Way Permitting from the Iowa DOT. 5. Conduct storm water related site inspections and document inspection results. 6. Complete a daily working day log related to construction activity. 7. Complete weekly working day reports during construction. 8. Obtain concrete plant certification. 9. Obtain material certifications for concrete, steel, signs, sign posts, and materials used to manufacture the signs and sign posts. 10. Receive and obtain approvals for shop drawings for signs and sign posts. 11. Collect delivery tickets for materials. 12. Obtain material test results. 13. Develop pay estimates for review and approval by the contractor and the City. 14. Process change/extra work orders if necessary. 15. Develop a Punch List of incomplete items. 16. Prepare record drawings for submittal to the City. 17. Develop a letter of acceptance for submittal to the City Council and the Iowa DOT upon project completion. 18. Submit the final project construction notebook to the City.