HomeMy WebLinkAboutPeterson Contractors Inc-1/24/2011CHANGE ORDER NO. 7
Owner City of Waterloo Date January 7, 2011
Project FY 2010 River Renaissance Lower Plaza
Owner's Contract No. 763 Contractor Peterson Contractors Inc.
Date of Contract Start April 15, 2010 $ 3.189.424.95
You are directed to make the following changes in the Contract Documents. Description:
7-1 Standpipe Connections
TOTAL ADDITIONS
$29,500.00
$29,500.00
Reason for Change Order.
6-1 The Waterloo Fire Department requested the additional standpipe hydrant connections after completion of design and bidding for the
project. The proposed connection will include 2 connections at the lower level of the large retaining wall with pipe connections to the
upper level where two 2 -way brass fire outlets will be constructed in the planter beds.
CONTRACT PRICE CONTRACT TIMES
To Substantial To Final
Completion Completion
Original: $ 3,189.424.95 Original Completion Date: 11/30/2010 12/31/2010
Previous C.O.s (ADD/B€944€T): $ 99.069.35 Revised Completion Date: No Chang No Change
This C.O. (ADDIDE914(4-): $ 2 500.00
Contract Price with all
approved Change Orders: $ 3.317.994.30
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s) ordered herein,
including all impact, delays, and acceleration costs. Other than the dollar amount and time allowance listed above, there shall be no fluffier time
or dollar compensation as a result of this Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO.
APPRO
By:
Owner (Authorized Signature)
1-A4--,9011
Date
P-1 -/t
Contractor (Authorized Signature) Date
vA
1
- -►
Date
L:\work\project1601551281eng\Change Orders\Lower Plaza CO#7.docx
AECOM
60155128 / 7
Project No. Change Order No.
CITY OF WATERLOO
Council Communication
City Council Meeting: January 24, 2011
Prepared: January 19, 2011
Dept. Head Signature: Eric Thorson, PE, City Engineer
# of Attachments:
SUBJECT: CHANGE ORDER NO. 7 - $29,500.00 INCREASE
F.Y. 2.010 RIVER RENA[SSANCE LOWER PIAZA.
Contract No. 763
PETERSON CONTRACTORS, INC.
Submitted by: Jamie Knutson, P.E., Associate Engineer
Recommended City Council Action:
Staff has reviewed this Change Order and recommends that the Mayor be authorized to sign it on
behalf of the City.
Summary Statement
Change Order No. 7 is for the increased amount of $29,500.00. This change order is for
additional standpipe connections.
Expenditure Required
Source of Funds Solid Waste Distributions
Policy Issue N/A
Alternative N/A
Background Information
The Waterloo Fire Depaituient requested the additional standpipe hydrant connections after
completion of design and bidding for the project. The proposed connection will include two
connections at the lower level of the large retaining wall with pipe connections to the upper level
where two, 2 -way brass fire outlets will be constructed in the planter beds. The City looked at
several different options to provide these connections and this is the best solution at the lowest
cost.
Cc: Michelle Weidner, CFO
Pauline Closson, Engineering