CHANGE or EXTRA WORK ORDER NO. 2
PROJECT: F.Y. 2010 SIDEWALK REPAIR PROGRAM — ZONE 10 AND TRAIL REPAIRS
CONTRACT. NO. 779 Date Prepared: Deoember3, 2010 AMOUNT: $26,775.00 INCREASE
TO: B & B BUILDERS AND SUPPLY , Contractor
You are hereby ordered to make the following changes from the plans and specifications or perform
the following extra work on your contract dated April 12, 2010.
A. Description of change to be made or extra work to be done:
2001 Additional removal of existing asphalt trail and replacement with 5 -inch PCC
B. Reason for ordering change or extra work:
2001 Review of funds showed additional older General Obligation bond monies available to make trail
repairs beyond the amount originally put out for bid and amount added in Change Order #1.
Settlement for cost of work to be made as follows:
2001 Remove existing asphalt trail, replace 5950 SF @ $4.50 per SF $26,775
with 5" PCC
TOTAL INCREASE $26,775.00
BY: I40 016 B & B BUILDERS AND SUPPLY
Mayor Date
Change Order No. 2
CONTRACTOR
BY:
/A `if zo/°
bate
171131410
71I3 4(0 TITLE: ae
Date APP OVED:
/2/q/0/0City Engineer Date