HomeMy WebLinkAboutKWS Inc-11/22/2010Contract & Final Acceptance Amount Modification
Date: November 15, 2010
Project: US 218 & 18th/Williston Traffic Safety Improvements
Traffic Operations Project Number: TRF -150
Iowa DOT Project Number: CS -TSF -8155(706)--85-07
Contractor: KWS of Cedar Falls, Iowa
The construction contract KWS and the final acceptance amount with for
the above mentioned project is here by modified as described in this
Modification Document the effective date of which is the date it signed
by the Mayor of Waterloo.
Reason For Modification: No loops were shown on the plans but the
contractor was asked to provide the loop detectors. Contractor provided
them. The vendor recently invoiced the contractor because the plans did
not mention existence of the loops. The original price was quoted based
on having no loop detectors.
Items & Cost
Number
Item
Unit
price
Unit
Total Item
Price
1
Rack Mount 2 -Channel Loop
Detector Amplifier
$235.00
EA
$1645.00
2
Shipping
$21.14
LS
$21.14
Total:
$1666.14
Contract Modification: Contract is hereby modified to include 7 loop
detectors.
Final construction cost: The final construction cost as presented to
Council on September 20, 2010 is now increased to $99,648.14 to reflect
the cost of 7 loop detectors.