HomeMy WebLinkAboutHR Green Company-10/11/2010Howard R. Green Company
8710 Earhart Lane SW P. O. Box 9009
Cedar Rapids, IA 52409-9009
(319) 841-4000 FAX (319) 841-4012
CHANGE ORDER
Distribution:
Owner X
Engineer
Contractor X
Field
Other HRG
PROJECT:
Phase 2 Demolition
Former Chamberlain Manufacturing Property
Contract No. 762
Waterloo, Iowa
Change Order No.
1 E
Date
September 28, 2010
To Contractor:
Active Thermal Concepts, Inc.
2805 Stonegate Court
Hiawatha, Iowa 52233
Contract No.
762
Original Contract Date
May 17, 2010
The contract is changed as follows:
1.Complete additional work of asbestos abatement in accordance with the procedures required in the Specifications dated
April 12, 2010, including Attachment A requirements, as follows:
Abate the asbestos not in Attachment A in Building No. 1, 2 & 3.
Total Cost Change Order No. 2 is $8,832.00.
The original Contract Sum was
$547,427.00
Net change by previously authorized Change Orders
$47,720.00
The Contract Sum prior to this Change Order was
$595,147.00
The Contract Sum will be increased by this Change Order in the amount of
$8,832.00
The new Contract Sum including this Change order will be
$603,979.00
The Contract Time will be increased by
zero (0) days
The date of Substantial Completion as of the date of this Change Order therefore is
October 30, 2010
NOT VALID UNTIL. SIGNED BY THE CONTRACTOR, OWNER'S REPRESENTATIVE, if applicable, AND OWNER
Contractor
Active Thermal Concepts, Inc.
Owner's Representative
Howard R. Green Company
Owner
City o, = aterloo, low
By
Cory Albers, Vice President
By
Gene H. Fritch, P. E.
B �" <
' est G. Clark, Mayor
Date: `
Date:
Date: 10 Li J?o( 6
F:iChamberlain Phase 2 demo\Pay EstimateslChange Order No. 2-092810.doc