Loading...
HomeMy WebLinkAboutIowa Bridge & Culvert, Inc-10/4/2010CITY OF WATERLOO, IOWA CHANGE or EXTRA WORK ORDER NO. 3 PROJECT: F.Y. 2010 CEDAR PRAIRIE TRAIL BRIDGE REPAIRS CONTRACT NO. 764 Date Prepared: September 8, 2010 AMOUNT: $4,284.00 DECREASE TO: Iowa Bridge & Culvert, Inc. , Contractor You are hereby ordered to make the following changes from the plans and specifications or perform the following extra work on your contract dated April 5, 2010. A. Description of change to be made or extra work to be done: Adjust original construction quantities to actual construction quantities. B. Reason for ordering change or extra work: As -built quantities varied for some bid items. C. Settlement for cost of work to be made as follows: Compensation already made to contractor through original bid items. See attached summary. $4,284.00 CITY OF RLOO NET DECREASE BY: % .! .' Iowa Bridge & Culvert. Inc. ATTEST: City C erk 16I',f (o Date CONTRACT BY: (Date 7-1?—/o Date PRINTED NAME: TITLE: APPROVED: OVioCity Engineer ineer Gate F.Y. 2010 CEDAR PRAIRIE TRAIL BRIDGE REPAIRS CONTRACT #764 FINAL QUANTITY SUMMARY BID ITEM DESCRIPTION IOWA BRIDGE UNIT UNIT PRICE ORIGINAL FINAL QUANTITY OUANTITY QUANTITY DIFFERENCE INCR/DECR 1 CLEARING AND GRUBBING ACRE $ 4,000.00 1.00 1.00 - $ - 2 DEBRIS REMOVAL TON $ 35.00 250.00 63.60 (186.4) $ (6,524.00) 3 REMOVE DAMAGED TIMBER PILES EACH $ 250.00 4.00 4.00 - $ - 4 REMOVAL OF EXISTING STRUCTURE EACH $ 1,500.00 6.00 6.00 - $ - 5 6 PILES, STEEL PIPE, 12" (PIOA TYPE 1) STEEL W 14X90 SUPPORT BEAMS LF $ 65.00 LB $ 2.50 180.00 180.00 720.00 720.00 - - $ - $ - 7 8 STEEL W 18X50 CAP BEAMS REPLACE TIMBER BEAMS LB $ 2.50 LS $ 12,000.00 1,600.00 1,600.00 1.00 1.00 - - $ - $ - 9 REVETMENT, CLASS E TON $ 50.00 90.00 92.80 2.8 $ 140.00 10 11 TEMPORARY CAUSEWAY TYPE A SIGNS, SHEET ALUMINUM LS $ 34,000.00 EACH $ 400.00 1.00 1.00 2.00 2.00 - - $ - $ - 12 13 SITE RESTORATION MOBILIZATION ACRE $ 6,000.00 LS $ 17,000.00 1.00 1.00 1.00 1.00 - - $ - $ - 1001 2001 DETOUR ROUTE FOR TRAIL ADDITIONAL REMOVAL OF EXISTING STRUCTURE LS $ 2,475.00 EACH $ 1,500.00 1.00 1.00 1.00 1.00 - - $ - $ - 2002 ADDITIONAL PILES, STEEL PIPE, 12" (P10a, Type 1) LF $ 65.00 140.00 140.00 - $ - 2003 2004 ADDITIONAL STEEL, W14X90 SUPPORT BEAMS ADDITIONAL STEEL, W18X50 CAP BEAMS LBS $ 2.50 LBS $ 2.50 720.00 720.00 1,600.00 1,600.00 - - $ - $ - 2005 2006 BEAM SPLICE CONNECTIONS ADDITIONAL PILING AND FREIGHT CHARGE EACH $ 2,100.00 LS $ 863.80 20.00 21.00 1.00 1.00 1.0 - $ 2,100.00 $ - 2007 TREE REMOVAL EACH $ 950.00 2.00 2.00 - $ - PAY ESTIMATE #1 $ 53,499.72 PAY ESTIMATE #2 PAY ESTIMATE #3 $ 96,942.56 $ 14,767.28 (`Je""v V� \ ,, INCR/DECR $ (4,284.00) p �p / �p e �b RETAINAGE TOTAL PAYMENT $ 8,695.24 $ 173,904.80 Iowa Bridge Date ORIGINAL CONTRACT AMOUNT $ 114,550.00 CHANGE ORDER #1 APPROVED BY CITY ENGINEER $ 2,475.00 CHANGE ORDER #2 APPROVED BY CITY COUNCIL FINAL QUANTITY ADJUSTMENT $ 61,163.80 $ (4,284.00'° l i /(J ty of Waterlo. Da FINAL CONTRACT AMOUNT $ 173,904.:'4