HomeMy WebLinkAboutStickfort Construction-9/27/2010CHANGE ORDER NO. 2
Owner City of Waterloo Date August 30, 2010
Project FY 2010 ADA Accessibility Plan, University Avenue and Greenhill Road
Owner's Contract No. Contractor Stickfort Construction
Date of Contract Start October 12, 2009 $ 135,522.65
You are directed to make the following changes in the Contract Documents. Description:
2-1 Adjust original construction quantities to actual construction quantities. $3,400.70
TOTAL ADDITIONS $3,400.70
Reason for Change Order:
2-1 As -Built quantities varied for some bid items.
Compensation already made to contractor through original bid items.
See Attached Summary
CONTRACT PRICE CONTRACT TIMES
Original:
Previous C.O.s (ADD/DEDUCT):
$ 135,522.65
$ 20,200.00
This C.O. (ADD/DEDUCT): $ 3,400.70
Contract Price with all
approved Change Orders:
$ 159,123.35
To Substantial To Final
Completion Completion
Original Completion Date: 11/30/2009 12/31/2009
Revised Completion Date: No Change No Change
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s) ordered herein, including
all impact, delays, and acceleration costs. Other than the dollar amount and time allowance listed above, there shall be no further time or dollar
compensation as a result of this Change Order.
APPROV
By:
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS,• ND COVENANTS OF THE CONTRACT SHALL APPLY HERETO.
0
er (Authorized Signa Date
ACCEPTED:
By:
(A orized Signature) Date
L:\work\project\111142\eng\ADA CO#2.doc
Date
0 \
Co
AECOM
100112 / 2
Project No. Change Order No.