HomeMy WebLinkAboutKW Electric Inc-6/28/2010CHANGE ORDER NO.1
Owner Waterloo Reotonal Aliroo, Citv of Waterloo, Iowa Date November 16.2009
- Project 400 Hz Ground Power Unit �+
Owner's Contract No. FAA AIP Project No. 3-19-0094-36 Contractor KW Electric Inc. Vit'
Date of Contract Start July 13 2009
You are directed to make the following changes in the Contract Documents Description:
Rein
Unit
,
No.
Desafption
Unit
Price
Quantity
Amount
2
Control Wring Modification
LS
$389.00
1.0
$389.00
Change Order Total
5389.00
Reason for Change Order.
Provide control wiring to prevatt the Passenger Boarding Bridge from moving when the Ground Power Unit is attached
to an aircraft. This is an optional function when both the boarding bridge and the Ground Power Unit are installed at
the same time, The Ground Power Unit was added to an existing boarding bridge and this limit switch with control
wiring was not provided by the boarding bridge supplier.
400 Hz Ground Power Unit
CO- 1 Project No - 112230
1
CONTRACT PRICE
Original: $ 92.550 00
Previous C s (ADD): $ 0.00
This C (ADD): $ 3S9.00
Contract Price with all
approved Change Orders: $ _72.939.00.
CONTRACT TIMES (Calendar Days)
Io substantial To fatal
completion completion
Original: 210
Previous C 0.s (ADD):
This C,.O. (ADD):
REVLSED:
0
0
210
Original Completion Date: 210
Revised Completion Date: 210
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the
changc(s) ordered herein, including all impact, delays, and acceleration costs. Other than the dollar amount and time
allowance listed above, there shall be no further time or dollar compensation as a result of this Change Order.
IBIS DOCUMENT SHALL BECOME AN AMENDMENI TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO
ACCEPTED:
13q fr-
Contractor (Authorized Signature)
6/z1,0
Date
(1(216'6(6
Date
Date
400 Hz Ground Power Unit
CO -1 Project No —112230
2
134808 - Hart/Welper
that Change Order No. 1 for a net increase of $389.00 for work performed by K&W
Electric of Cedar Falls, Iowa in conjunction with Ground Power Unit project at
the Waterloo Regional Airport, be received, placed on file and approved and
Mayor authorized to execute same. Ayes: Six. Absent: Greenwood. Motion
carried.
134809 - Hart/Welper
that "Resolution approving Final Acceptance and Completion of Project performed
by K&W Electric of Cedar Falls, Iowa at a total cost of $72,939.00 in
conjunction with Ground Power Unit project at the Waterloo Regional Airport", be
adopted. Ayes: Six. Absent: Greenwood.
Resolution adopted and upon approval by Mayor assigned No. 2010-577.
.i ..
A \i) rte.`) ..��1 .
Pay Estimate No. 2 (Final)
400 Hz Ground Power Unit
Waterloo Municipal Airport
Waterloo, Iowa
FAA AIP 3-19-0094-36
AECOM Project No. 112230
PERIOD ENDING: June 17, 2010
item
No.
Spec.
No.
Description
Unit
Unit Bid
Price
Contract
Quantity
Contract
Amount
Authorized
Quantity
Authorized
Amount
Quantity
To Date
Amount
To Date
1
26 35 43
40D Hz Ground Power Unit Installed
L.S.
$ 72.550.00
1
$ 72.550.00
1
$ 72,550.00
1
$ 72,550.00
2
26 35 43
Control Wiring Modification (CO Al)
L.S.
$ 389.00
0
$ -
1
$ 389.00
1
$ 389.00
Total Amount
$ 72,550.00
$ 72.939.00
$ 72,939.00
Prepared by: AECOM
Waterloo Regional Airport Repre entative
rt Director
mg
Total Earned to Date
Stored Materials
Subtotal
Less Retainage (5%)
Subtotal
Less Previous Payments
Total Amount Per Division
$ 72,939.00
$ -
$ 72,939.00
$ -
$ 72,939.00
$ 68,922.50
$ 4,016.50
Total Amount Due This Estimate $ 4,016.60
Percent Complete
100.0%