Loading...
HomeMy WebLinkAboutFailor-Hurley Construction-6/28/2010CHANGE ORDER NO. 6 Owner. City of Waterloo, Iowa Date: May 24, 2010 Project: Commercial Street Parking Garage Repairs, Phase I - Stairwells Owner's Contract No.: — Contractor. Failor-Hurley Construction Date of Contract Start: May 18, 2009 $ 621,100.00 You are directed to make the following changes in the Contract Documents. Description: 8021: Add 5 Wall Stops and 13 Floor Stops to Doors $470.00 Reason for Change Order: 8021: Not included in original plans. CONTRACT PRICE CONTRACT TIMES (Calendar Days) To Completion Original: $ 621,100.00 Original: Sept. 30, 2009 Previous C.O.s (ADD/DEDUCT): $ 36,583.31 Previous C.O.s (ADD/DEDUCT): 30 Days This C.O. (ADD/DEDUCT): $ 470.00 This C.O. (ADD/DEDUCT): 15 Days Contract Price With All Approved Change Orders: $ 658,153.31 REVISED: Nov. 15, 2009 Revised Completion Date: Nov. 15, 2009 It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s) ordered herein, including all impact, delays, and acceleration costs. Other than the dollar amount and time allowance listed above, there shall be no further time or dollar compensation as a result of this Change Order. APPROVED By: ACCEPTED: By: THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO er (Authorized Signature) Date: 'luta Conntr or (Authorized yfnattuufe) Date: W,«,AA/ W. (GOZ, /44.5/4E.r S/ G6o 113100/C06-CommStParking-Ph l.doc AECOM 113100 -Ph1 6 Project No. Change Order No.