HomeMy WebLinkAboutAllied Construction Company Inc-6/28/2010CHANGE ORDER NO. 2
Owner Waterloo Regional Airport, City of Waterloo, Iowa Date June 22, 2010
Project Rehabilitation of GA Apron and Taxilanes (Phase I)
Owner's Contract No. FAA AIP Project No. 3-19-0094-30 Contractor Allied Constr. Company, Inc.
Date of Contract Start April 15, 2008
You are directed to make the following changes in the Contract Documents. Description:
ITEM
NO.
DESCRIPTION
UNIT
QUANTITY
UNIT
PRICE
TOTAL
AMOUNT
3
Storm Sewer Pipe Removal
LFT
-7.2
$ 17.75
$ (127.80)
5
Storm Sewer Structure Removal
EA
1.0
$ 285.00
$ 285.00
6
Removal of Paint
SFT
-777.5
$ 1.50
$ (1,166.25)
9
Silt Fence Installation & Removal
LFT
-175.0
$ 4.25
$ (743.75)
13
Taxiway Painting (Yellow -Epoxy)
SFT
-404.7
$ 3.82
$ (1,545.95)
14
15" RCP Storm Sewer Pipe
LFT
21.0
$ 43.00
$ 903.00
15
18" Slotted Drain
LFT
-6.5
$ 220.00
$ (1,430.00)
17
Storm Sewer Intake Adjustment
EA
-2.0
$ 750.00
$ (1,500.00)
Total Amount of Change Order
(5,325.75)
Reason for Change Order:
All quantities have been adjusted to final field measured quantities. The following quantities are substantial
changes and are further defined.
• Item 6. Majority of paint removal was completed under another project.
• Item 7. Construction Phasing required less silt fence installation.
• Items 13. Majority of paint was completed under another project.
Rehabilitation of GA Apron & Taxilanes (Phase I) CO -2 Project No — 103753
1
CONTRACT PRICE
Original: $ 671,317.25
Previous C.O.s (ADD): $ 13,126.70
This C.O. (ADD): $ (5,325.75)
Contract Price with all
approved Change Orders: $ 679,118.20
CONTRACT TIMES (Calendar Days)
To substantial
completion
To final
completion
Original: 105
Previous C.O.s (ADD): 0
This C.O. (ADD): 0
REVISED: 105
Original Completion Date: 105
Revised Completion Date: _ 105
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting
from the change(s) ordered herein, including all impact, delays, and acceleration costs. Other than the dollar
amount and time allowance listed above, there shall be no further time or dollar compensation as a result of this
Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO.
Owner (Authorized Signature)
ACCEP
By:
1Z3//)
Date
(0(2)812p0
Date
a/ -9 -e -e -e --L. 14'2 64/147
Contractor (Authorized Signature) Date
Rehabilitation of GA Apron & Taxilanes (Phase I) CO -2 Project No - 103753
2