HomeMy WebLinkAboutAspro Inc-6/28/2010 (2)CHANGE ORDER NO. 2 Owner Waterloo Regional Airport, City of Waterloo, Iowa Date June 22, 2010 Project Runway 12-30 Rehabilitation Owner's Contract No. FAA AIP Project No. 3-19-0094-29 Contractor ASPRO Inc. Date of Contract Start August 7, 2006 You are directed to make the following changes in the Contract Documents. Description: Item No. Description Unit Quantity Unit Price Total Amount 6 Pavement Removal SY 207.0 $ 36.00 $ 7,452.00 7 Runway Edge Light Removal Including Base EA 3.0 $ 325.00 $ 975.00 8 MALS Threshold Light Bar Removal LS (1.0) $ 11,895.00 $ (11,895.00) 9 Embankment in Place CY (200.0) $ 48.00 $ (9,600.00) 10 Crushed Aggregate Base Course CY (143.0) $ 60.00 $ (8,580.00) 11 Bituminous Surface Course TON (657.8) $ 57.65 $ (37,922.17) 12 Grooving SY 16.0 $ 0.85 $ 13.60 13 Bituminous Tack Coat GAL (5,525.0) $ 1.25 $ (6,906.25) 14 Polyurea Pavement Marking, White, with Ceramic Elements SF (122,500.0) $ 3.24 $ (396,900.00) 15 Polyurea Pavement Marking, Yellow, with Ceramic Elements SF (5,250.0) $ 3.24 $ (17,010.00) 16 Seeding and Mulching ACRE (1.0) $ 3,000.00 $ (3,000.00) 17 Topsoiling (Obtained Offsite) CY (800.0) $ 47.00 $ (37,600.00) 18 Trenching for Direct -Buried Counterpoise Wire LF (1,189.0) $ 0.40 $ (475.60) 19 No. 6 AWG, L -824C Cable, Installed in Duct Bank or Conduit LF 467.0 $ 1.50 $ 700.50 20 Bare Counterpoise Wire, Installed in Trench, Including Ground Rods and Ground Conductors LF (869.0) $ 1.00 $ (869.00) 21 Insulated Equipment Ground, Installed in Duct Bank or Conduit, Including Ground Rods and Ground Conductors LF 167.0 $ 1.50 $ 250.50 22 Electrical Conduit, 2" Schedule 40 PVC LF (875.0) $ 2.60 $ (2,275.00) 26 L-868 Electrical Handhole EA (1.0) $ 650.00 $ (650.00) 27 MALS Threshold Light Bar LS (1.0) $ 52,750.00 $ (52,750.00) 29 Storm Sewer Pipe Repair EA 5.0 $ 1,250.00 $ 6,250.00 14a White Waterborne Paint with Beads - Temporary SF 117,865.2 $ 0.56 $ 66,004.51 Runway 12-30 Rehabilitation CO -2 1 Project No - 91933 Item No. Description Unit Quantity Unit Price Total Amount 15a Yellow Waterbome Paint with Beads - Temporary SF 2,231.2 $ 0.56 $ 1,249.47 15b Polyurea Restocking Charge LS 1.0 $ 916.33 $ 916.33 15c Paint Removal SF 4,367.2 $ 1.00 $ 4,367.20 15d White Waterbome Paint with Beads SF 124,119.5 $ 0.56 $ 69,506.92 15e Yellow Waterbome Paint with Beads SF 7,524.3 $ 0.56 $ 4,213.61 102 Replace Damaged Conduit LF (20.0) $ 8.80 $ (176.00) 103 Remove and Replace #6 Wire from FAA Building LF 1,200.0 $ 1.50 $ 1,800.00 Total Amount of Change Order (422,909.38) Reason for Change Order: 6. This quantity has been adjusted to fmal field measured quantity. 7. This quantity has been adjusted to final field measured quantity. 8. This quantity was deleted in its entirety. 9. This quantity is a fmal field measured quantity. It was reduced as a result of the deletion of the MALS threshold bar. 10. This quantity is a final field measured quantity. It was reduced as a result of the deletion of the MALS threshold bar. 11. This quantity has been adjusted to fmal field measured quantity. 12. This quantity has been adjusted to fmal field measured quantity. 13. This quantity has been adjusted to fmal field measured quantity. 14. This quantity was deleted in its entirety and replaced with Waterborne Paint. See Item 14a and 15d. 15. This quantity was deleted in its entirety and replaced with Waterborne Paint. See Item 15a and 15e. 16. This quantity was deleted as a result of the reduction in embankment in place and the seeding and mulching completed as part of the runway lighting. 17. This quantity was deleted as a result of the reduction in embankment in place. 18. This quantity has been adjusted to final field measured quantity. 19. This quantity has been adjusted to final field measured quantity. 20. This quantity has been adjusted to final field measured quantity. 21. This quantity has been adjusted to fmal field measured quantity. 22. This quantity has been adjusted to final field measured quantity. 26. This quantity has been adjusted to final field measured quantity. 27. This quantity was deleted in its entirety. 29. This quantity has been adjusted to final field measured quantity. Additional pipe repairs were located during construction phase of the project. 14a. This quantity is for field measured quantity for all temporary white paint associated with the project. 15a. This quantity is for field measured quantity for all temporary yellow paint associated with the project. 15b. This item is for the restocking of the Polyurea Pavement Marking Materials. 15c. This quantity is for field measured quantity for all paint removal required for the project. 15d. his quantity is for field measured quantity for all permanent waterborne white paint associated with the project. Runway 12-30 Rehabilitation CO -2 Project No - 91933 2 15e. 'This quantity is for field measured quantity for all permanent waterborne yellow paint associated with the project. 102. This quantity has been adjusted to fmal field measured quantity. Increase was to replace additional conduit that was found to be damaged between the radar site and the beacon site. 103. This quantity has been adjusted to final field measured quantity. Increase was to replace additional #6 wire that was found to be damaged between the radar site and the beacon site. CONTRACT PRICE Original: Previous C.O.s (ADD): This C.O. (ADD): Contract Price with all approved Change Orders: $ 2,527,598.75 S 43,930.00 $ (422,909.38) $ 2,148,619.37 CONTRACT TIMES (Calendar Days) To final completion Original: Previous C.O.s (ADD): This C.O. (ADD): REVISED: To substantial completion 90 0 0 90 Original Completion Date: 90 Revised Completion Date: 90 It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s) ordered herein, including all impact, delays, and acceleration costs. Other than the dollar amount and time allowance listed above, there shall be no further time or dollar compensation as a result of this Change Order. THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO. RECOMME I ED: Bye Engineer APPRO By: rized Signature) Date wner (Authorized Signature ACCEPTED: 1 �� n By: 'i v``' �. L`��'� , chi Contractor (Authorized Signature) (Q /2lo Date Date Runway 12-30 Rehabilitation CO -2 Project No — 91933 3