HomeMy WebLinkAboutAment-3/15/2010Agreement Addendum Number 1
Project:
US 63/ Ridgeway Engineering Design for Traffic Safety
Improvements
Agreement Date:
Signed By Mayor on February 23, 2009
Engineering Firm:
Ament
The undersigned parties hereby agree to modify the above referenced agreement
according to the terms and conditions described below:
1. Work & Items
The following items required extra work that was not anticipated at the time of signing
the agreement:
• Design changes based on Iowa DOT's review of preliminary plans. Mast arm
pole configuration was changed to keep the existing truss.
• Additional surveying and design effort was also necessary when it was
determined that the existing roadway culvert to drain the median adjacent to the
lengthened northeast -bound US 63 left -turn lane could not be utilized and that
two new pipe culverts would need to be jacked under the southwest -bound lanes
ofUS63.
• Changes to plans and specifications format to accommodate a DOT letting.
2. Costs:
The Agreement amount is increased by $6,500. The original agreement amount was
$32,900. The new "not to exceed" amount is $39,400.
Engineering Firm: Ament
By:
Title: pJ, -i),(< f' 4'0` 6/13 /
Date:
City of Waterloo'
By: .,e •%a-tY 6e/df
Title:
Date: 3
olQ
Agreement Addendum Number 1
Project:
US 63/ Ridgeway Engineering Design for Traffic Safety
Improvements
Agreement Date:
Signed By Mayor on February 23, 2009
Engineering Firm:
Ament
The undersigned parties hereby agree to modify the above referenced agreement
according to the terms and conditions described below:
1. Work & Items
The following items required extra work that was not anticipated at the time of signing
the agreement:
• Design changes based on Iowa DOT's review of preliminary plans. Mast arm
pole configuration was changed to keep the existing truss.
• Additional surveying and design effort was also necessary when it was
determined that the existing roadway culvert to drain the median adjacent to the
lengthened northeast -bound US 63 left -turn lane could not be utilized and that
two new pipe culverts would need to be jacked under the southwest -bound lanes
of US 63.
• Changes to plans and specifications format to accommodate a DOT letting.
2. Costs:
The Agreement amount is increased by $6,500. The original agreement amount was
$32,900. The new "not to exceed" amount is $39,400.
Engineering Firm: Ament
By:
Title:
Date:
City of Waterlo
By:
Title:
Date: