HomeMy WebLinkAboutPeterson Contractors Inc-5/24/2010CITY OF WATERLOO, IOWA
CHANGE or EXTRA WORK ORDER NO. 1
PROJECT: F.Y. 2010 SALVAGED ASPHALT .CRU_SHING CONTRACT NO. 785
Date Prepared:
May 19, 2010 AMOUNT: $16,787.68 INCREASE
TO: PETERSON CONTRACTORS, INC. , Contractor
You are hereby ordered to make the following changes from the plans and specifications or perform
the following extra work on your contract dated March 15, 2010.
A. Description of change to be made or extra work to be done:
Adjust original construction quantities to actual construction quantities.
B. Reason for ordering change or extra work:
As -built quantities varied for some bid items.
C. Settlement for cost of work to be made as follows:
Compensation already made to contractor through original bid items.
See attached summary.
CITY OFt ATERLOO ,\
BY:S%LF (U PET
Date C
ayor
ATTEST:
Change Order No. 1
5-&14/g0(6
Date
TITLE:
NET INCREASE $16,787.68
CONTRACTORS, INC.
1 dalfiate
:- D
PRINTED NAMEIr10 1 t C„
Z
APPROVED:
City Engineer Date
Contract No. 785
Page 1 of 1
F.Y. 2010 SALVAGED ASPHALT CRUSHING
CONTRACT NO. 785
QUANTITY ADJUSTMENTS CHANGE ORDER NO. 1
BID FINAL EST. INCR/DECR PETERSON TOTAL
ITEM DESCRIPTION UNIT QTY QTY QTY UNIT PRICE INCR/DECR
1 ASPHALT CRUSHING TON 45,724.00 36,500.00 9,224.00 1.82 16,787.68
2 MOBILIZATION LS 1.00 1.00 0.00 1,800.00 0.00
ORIGINAL CONTRACT AMOUNT $68,230.00
CHANGE ORDER NO. 1
FINAL CONTRACT AMOUNT
$16,787.68
$85,017.681
PAY ESTIMATES 1-2 $80,766.80
RETAINAGE $4,250.88
TOTAL PAID CONTRACTOR $85,017.68
/ t1SCU#1-1MUK-IJELK. X19
TOTAL INCREASE $16,787.68
wage 1