HomeMy WebLinkAboutFailor Hurley Construction-5/24/2010CHANGE ORDER NO. 5
Owner. City of Waterloo, Iowa Date: April 13, 2010
Project Commercial Street Parking Garage Repairs, Phase I - Stairwells
Owner's Contract No.: — Contractor. Failor-Hurley Construction
Date of Contract Start: May 18, 2009 $ 621,100.00
You are directed to make the following changes in the Contract Documents. Description:
8020: Add Stair No. 1 Gate $1,127.00
Reason for Change Order:
8020: Required by Building Inspector.
CONTRACT PRICE CONTRACT TIMES
(Calendar Days)
To
Completion
Original: $ 621,100.00 Original: Sept. 30, 2009
Previous C.O.s (ADD/9€ GT): $ 35,456.31 Previous C.O.s (ADDJDEDUGT): 30 Days
This C.O. (ADD/IDE-DUG-Ty $ 1,127.00 This C.O. (ADD/DEDUGT): 15 Days
Contract Price With All Approved
Change Orders: $ 657,683.31 REVISED: Nov. 15, 2009
Revised Completion Date: Nov. 15, 2009
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s) ordered herein, including all
impact, delays, and acceleration costs. Other than the dollar amount and time allowance listed above, there shall be no further time or dollar compensation
as a result of this Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO
APPROVED:
By:
Owr r (Authorized Signature) Date:
ACCEPTED:
By:
Contractor (Authorized Signature)
/
Date:
5)9114[9-6o
113100/C05-CommStParking-Ph l .doc
AECOM
113100 -Ph 1
Project No.
5
Change Order No.
CHANGE ORDER NO. 5
Owner. City of Waterloo, Iowa Date: April 13, 2010
Project: Commercial Street Parking Garage Repairs, Phase I - Stairwells
Owner's Contract No.: — Contractor. Failor-Hurley Construction
Date of Contract Start May 18, 2009 $ 621,100.00
You are directed to make the following changes in the Contract Documents. Description:
8020: Add Stair No. 1 Gate $1,127.00
Reason for Change Order:
8020: Required by Building Inspector.
CONTRACT PRICE CONTRACT TIMES
(Calendar Days)
To
Completion
Original: $ 621,100.00 Original: Sept. 30, 2009
Previous C.O.s (ADD/DEDUCT): $ 35,456.31 Previous C.O.s (ADD/DEDUGT): 30 Days
This C.O. (ADD/DEDUCT): $ 1,127.00 This C.O. (ADD/DE-DUCT): 15 Days
Contract Price With All Approved
Change Orders: $ 657,683.31 REVISED: Nov. 15, 2009
Revised Completion Date: Nov. 15, 2009
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s) ordered herein, including all
impact, delays, and acceleration costs. Other than the dollar amount and time allowance listed above, there shall be no further time or dollar compensation
as a result of this Change Order.
APPROVED:
By:
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO
d%;
Owner (Authorized Signature) Date:
ACCEPTED:
By:
I/
Contractor (Authoriz Signa,urre)
WI/ (..L./4All 1,1/ i /alio de, ifle6S aE4Ji
113100/C05-CommStParking-Ph l .doc
501, I- I t
Date:
l/A o
AECOM
113100 -Ph 1
Project No.
5
Change Order No.