HomeMy WebLinkAboutAspro Inc-10/24/2016CITY OF WATERLOO, IOWA CHANGE or EXTRA WORK ORDER NO. 4 PROJECT: F.Y. 2016 ASPHALT OVERLAY PROGRAM , CONTRACT NO. 897 Date Prepared: April 4, 2016 AMOUNT: $ 22,128.60 Decrease TO: Aspro, Inc. , Contractor You are hereby ordered to make the following changes from the plans and specifications or perform the following extra work on your contract dated February 17, 2014. A. Description of change to be made or extra work to be done: Adjust original construction quantities to actual construction. B. Reason for ordering change or extra work: As -built quantities varied for some bid items. C. Settlement for cost of work to be made as follows: Compensation already made to contractor through original bid items. See attached summary. Total Net Decrease $ 22,128.60 CITY OF WATERLOO Iaj BY:(14-Ceel. Mayor Date CONTRACTOR BY/7 Aspro, Inc. ATTEST: L'IrLare /0/y//7 Date PRINTED NAME:/IT 0 /oI/i �Ll TITLE: /'/ ES/4 fi APPROVED: gr„.0,0 City Engineer /C'%% 9//� Date F.Y. 2016 ASPHALT OVERLAY PROGRAM CONTRACT #897 FINAL QUANTITY SUMMARY BID ASPRO ORIGINAL FINAL QUANTITY IT DESCRIPTION UNIT UNIT PRICE OUANTITY OUANTITY DIFFERENCE JNCR/DECR 1 REMOVE C AND REPLACE WITH E-1 INLET EACH $ 3,595.00 2.00 2.00 - $ - 2 REMOVE AND REPLACE E -I -C (USE EXISTING CASTING) EACH $ 3,145.00 6.00 8.00 2.00 $ 6,290.00 3 REMOVE AND REPLACE E -2-C (USE EXISTING CASTING) EACH $ 4,500.00 2.00 2.00 - $ - 4 REMOVE AND REPLACE INTAKE BOXOUT/E-1-C EACH $ 1,595.00 11.00 9.00 (2.00) $ (3,190.00) 5 FURNISH E -1-C INLET CASTING EACH $ 900.00 1.00 2.00 1.00 $ 900.00 6 FURNISH E -1-C DRIVE OVER INLET CASTING EACH $ 2,150.00 2.00 2.00 - $ - 7 REMOVE AND REPLACE MH BOXOUT EACH EACH $ 1,525.00 $ 125.00 9.00 8.00 4.00 3.00 (5.00) (5.00) $ (7,625.00) $ (625.00) 8 SUBDRAINOUTLET 9 STORM SEWER, 10" TRUSS LF $ 98.00 28.00 32.00 4.00 $ 392.00 10 REMOVE SIDEWALK SY $ 10.00 253.40 264.20 10.80 $ 108.00 11 SIDEWALK, 4" PCC SY $ 34.00 134.60 149.80 15.20 $ 516.80 12 SIDEWALK, 6" PCC SY $ 53.00 112.10 116.00 3.90 $ 206.70 13 PEDESTRIAN RAMP DETECTABLE WARNING SURFACE SF $ 31.25 266.00 206.00 (60.00) $ (1,875.00) 14 TOPSOIL REMOVAL FROM PARKING SY $ 14.00 28.00 1030 (17.70) $ (247.80) 15 REMOVE AND REPLACE 24" C & G/6" PCC LF $ 24.25 57.00 59.60 2.60 $ 63.05 16 REMOVE AND REPLACE 24" C&G/8" PCC LF $ 26.00 276.50 295.80 19.30 $ 501.80 17 FULL DEPTH PATCH, REM/REP 6" PCC SY $ 65.00 48.80 4630 (2.50) $ (162.50) 18 RECYCLED ASPHALT TON $ 62.50 510.40 1533 (495.07) $ (30,941.88) 19 PAVEMENT SCARIFICATION SY $ 6.65 27,490.50 27,761.20 270.70 $ 1,800.16 20 MILL WEDGE EACH $ 2,200.00 24.00 25.00 1.00 $ 2,200.00 21 CRACK AND SEAT SY $ 3.40 4,645.00 2,570.00 (2,075.00) $ (7,055.00) 22 SURFACE PATCH TON $ 237.00 12.00 12.70 0.70 $ 165.90 23 PARTIAL DEPTH PATCH SF $ 7.00 2,700.00 2,932.00 232.00 $ 1,624.00 24 HMA (1,000,000 ESAL) INTERMEDIATE, 3/4" MIX, 60% CE. TON $ 108.80 1,211.20 1,135.93 (75.27) $ (8,18938) 25 HMA (1,000,000 ESAL) SURFACE, 1/2" MIX , NO FRICTION REQD., 60% CR. TON $ 10930 3,386.40 3,561.44 175.04 $ 19,131.87 26 HMA (3,000,000 ESAL) INTERMEDIATE, 3/4" MDC, 75% CR TON $ 109.70 2,583.20 2,063.53 (519.67) $ (57,007.80) 27 BMA (3,000,000 ESAL) SURFACE, 1/2" MIX, NO FRICTION REQD., 75% CR TON $ 114.40 1,994.60 2,024.78 30.18 $ 3,452.59 28 HMA INTERLAYER TON $ 147.45 989.80 1,12631 136.51 $ 20,128.40 29 HMA PAVEMENT SAMPLES AND TESTING LS $ 4,500.00 1.00 1.0000 - $ - 30 CASTING EXTENSION RING (INLET) EACH $ 200.00 17.00 13.00 (4.00) $ (800.00) 31 CASTING EXTENSION RING (MANHOLE) EACH $ 615.00 54.00 54.00 - $ - 32 FURNISH AND INSTALL MANHOLE CASTING EACH $ 890.00 1.00 - (1.00) $ (890.00) 33 PAVEMENT SYMBOLS EACH $ 400.00 4.00 7.00 3.00 $ 1,200.00 34 PAINTED PAVEMENT MARKINGS STA $ 47.00 250.03 164.73 (8530) $ (4,009.10) 35 RAILROAD PERMIT AND INSURANCE IS $ 5,539.00 1.00 1.00 - $ - 36 TRAFFIC CONTROL IS $ 77,585.00 1.00 1.0000 - $ - 1001 GRIND TREE STUMP LS $ 165.00 1.00 1.00 - $ - 2001 REMOVE SIDEWALK SY $ 10.00 35.60 23.40 (12.20) $ (122.00) 2002 SIDEWALK, 6" PCC SY $ 53.00 35.60 17.40 (18.20) $ (964.60) 2003 PEDESTRIAN RAMP DETECTABLE WARNING SURFACE SF $ 31.25 40.00 40.00 - $ - 2004 MODIFIED SUBBASE TON $ 27.40 9.00 - (9.00) $ (246.60) 2005 HMA (1,000,000 ESAL) SURFACE, 112" MIX , NO FRICTION REQD., 60% CR TON $ 10930 40.00 89.51 49.51 $ 5,411.44 2006 HMA (1,000,000 ESAL) INTERMEDIATE, 3/4" MIX, 60% CR. TON $ 108.80 - 165.04 165.04 $ 17,95635 3001 HMA (1,000,000 ESAL) INTERMEDIATE, 3/4" MIX, 60% CR. TON $ 108.80 50.00 71.09 21.09 $ 2,294.59 4001 MODIFIED SUBBASE TON $ 27.40 2424 24.24 $ 664.18 4002 HMA (1,000,000 ESAL) SURFACE, 1/2" MIX , NO FRICTION REQD., 60% CR. TON $ 10930 - 150.74 150.74 $ 16,475.88 4003 PAINTED PAVEMENT MARKINGS STA $ 47.00 - 7.22 7.22 $ 339.34 INCREASE/DECREASE $ (22,128.60) PAY ESTIMATE #1 April 14, 2016 $ 18,57725 .`` ' / /��// PAY ESTIMATE #2 April 28, 2016 $ 31,281.70 ' / /P , - 1 -e57 -1X /v ` PAY ESTIMATE #3 May 14, 2016 $ 276,228.43 Aspro Date PAY ESTIMATE #4 June 2, 2016 $ 319,167.08 PAY ESTIMATE #5 June 11, 2015 $ 49,563.97 PAY ESTIMATE #6 July 15, 2016 $ 69 334.98 , (ry✓-a > �`� /��(� PAY ESTIMATE #7 July 29, 2016 $ 579,307.75 �//�� City of Water 35 ate / PAY ESTIMATE #8 August 29, 2016 $ 236,543.80 PAY ESTIMATE #9 September 30, 2016 $ 23,42136 PAY ESTIMATE #10 October 13, 2016 $ 17,479.40 RETAINAGE $ 82,397.14 TOTAL PAYMENT $ 1,703,302.86 ORIGINAL CONTRACT AMOUNT $ 1,711,715.06 . CHANGE ORDER #1 SIGNED BY CITY ENGINEER $ 165.00 CHANGE ORDER #2 SIGNED BY CITY ENGINEER $ 8,111.40 CHANGE ORDER #3 SIGNED BY CITY ENGINEER $ 5,440.00 FINAL QUANTITY ADJUSTMENT $ (22,128.60) FINAL CONTRACT AMOUNT $ 1,703,302.86 - Item Coversheet Page 1 of 1 CITY OF WATERLOO Council Communication Motion approving Change Order No. 4 for a net decrease of $22,128.60 for the F.Y. 2016 Asphalt Overlay Program, Contract No. 897 and authorize the Mayor and City Clerk to execute said document. City Council Meeting: 10/24/2016 Prepared: 10/19/2016 SUBJECT: Submitted by: Summary Statement: Source of Funds: Motion approving Change Order No. 4 for a net decrease of $22,128.60 for the F.Y. 2016 Asphalt Overlay Program, Contract No. 897 and authorize the Mayor and City Clerk to execute said document. Submitted By: Jamie Knutson, PE, Associate Engineer This is the accumulated amount of adjustments from original to final quantities that were determined necessary during the construction of the project, which results in a decrease to the total project cost. Local Option Sales Tax http://waterloo.novusagenda.com/AgendaWeb/CoverSheet.aspx?ItemID=6655 10/19/2016