HomeMy WebLinkAboutAspro Inc-10/24/2016 (2)CITY OF WATERLOO, IOWA CHANGE or EXTRA WORK ORDER NO. 4 PROJECT: F.Y. 2016 ASPHALT OVERLAY PROGRAM , CONTRACT NO. 897 Date Prepared: April 4, 2016 AMOUNT: $ 22,128.60 Decrease TO: Aspro, Inc. , Contractor You are hereby ordered to make the following changes from the plans and specifications or perform the following extra work on your contract dated February 17, 2014. A. Description of change to be made or extra work to be done: Adjust original construction quantities to actual construction. B. Reason for ordering change or extra work: As -built quantities varied for some bid items. C. Settlement for cost of work to be made as follows: Compensation already made to contractor through original bid items. See attached summary. CITY OF WATERLOO BY: Mayor ATTEST: Total Net Decrease $ 22,128.60 Aspro, Inc. Date CONTRACTOR BY/07 /®/(W/74 Date PRINTED NAME: /1--7 0%/S'Glvi c/-/ TITLE: ,/ei--S/42fa,>%= APPROVED: j /C//9// City Engineer Date -.; F.Y. 2016 ASPHALT OVERLAY PROGRAM CONTRACT #897 "" FINAL QUANTITY SUMMARY BID ASPRO ORIGINAL FINAL QUANTITY ITEM DESCRIPTION UNIT PRICE QUANTITY OUANTITY DIFFERENCE JNCR/DECR 1 REMOVE C AND REPLACE WITH E-1 INLET EACH $ 3,595.00 2.00 2.00 - $ - 2 REMOVE AND REPLACE E-1-C (USE EXISTING CASTING) EACH $ 3,145.00 6.00 8.00 2.00 $ 6,290.00 3 REMOVE AND REPLACE E-2-C (USE EXISTING CASTING) EACH $ 4,500.00 2.00 2.00 - $ - 4 REMOVE AND REPLACE INTAKE BOXOUT/E-1-C EACH $ 1,595.00 11.00 9.00 (2.00) $ (3,190.00) 5 FURNISH E-1-C INLET CASTING EACH $ 900.00 1.00 2.00 1.00 $ 900.00 6 FURNISH E-1-C DRIVE OVER INLET CASTING EACH $ 2,150.00 2.00 2.00 - $ - 7 REMOVE AND REPLACE MH BOXOUT EACH $ 1,525.00 9.00 4.00 (5.00) $ (7,625.00) 8 SUBDRAINOUTLET EACH $ 125.00 8.00 3.00 (5.00) $ (625.00) 9 STORM SEWER, 10" TRUSS LF $ 98.00 28.00 32.00 4.00 $ 392.00 10 REMOVE SIDEWALK SY $ 10.00 253.40 26420 10.80 $ 108.00 11 SIDEWALK, 4" PCC SY $ 34.00 134.60 149.80 15.20 $ 516.80 12 SIDEWALK, 6" PCC SY $ 53.00 112.10 116.00 3.90 $ 206.70 13 PEDESTRIAN RAMP Dh1'hCTABLE WARNING SURFACE SF $ 31.25 266.00 206.00 (60.00) $ (1,875.00) 14 TOPSOIL REMOVALFROMPARKNG SY $ 14.00 28.00 10.30 (17.70) $ (247.80) 15 REMOVE AND REPLACE 24" C & G/6" PCC LF $ 24.25 57.00 59.60 2.60 $ 63.05 16 REMOVE AND REPLACE 24" C&G/8" PCC LF $ 26.00 276.50 295.80 1930 $ 501.80 17 FULL DEPTH PATCH, REM/REP 6" PCC SY $ 65.00 48.80 4630 (2.50) $ (162.50) 18 RECYCLED ASPHALT TON $ 62.50 510.40 15.33 (495.07) $ (30,941.88) 19 PAVEMENT SCARIFICATION SY $ 6.65 27,490.50 27,761.20 270.70 $ 1,800.16 20 MIL WEDGE EACH $ 2,200.00 24.00 25.00 1.00 $ 2,200.00 21 CRACK AND SEAT SY $ 3.40 4,645.00 2,570.00 (2,075.00) $ (7,055.00) 22 SURFACE PATCH TON $ 237.00 12.00 12.70 0.70 $ 165.90 23 PARTIAL DEPTH PATCH SF $ 7.00 2,700.00 2,932.00 232.00 $ 1,624.00 24 HMA (1,000,000 ESAL) INTERMEDIATE, 3/4" MDC, 60% CR. TON $ 108.80 1,21120 1,135.93 (75.27) $ (8,189.38) 25 HMA (1,000,000 ESAL) SURFACE, 1/2" MIX , NO FRICTION REQD., 60% CR. TON $ 10930 3,386.40 3,561.44 175.04 $ 19,131.87 26 HMA (3,000,000 ESAL) INTERMEDIATE, 3/4" MDC, 75% CR TON $ 109.70 2,583.20 2,063.53 (519.67) $ (57,007.80) 27 HMA (3,000,000 ESAL) SURFACE, 1/2" MIX, NO FRICTION REQD., 75% CR TON $ 114.40 1,994.60 2,024.78 30.18 $ 3,452.59 28 HMA INTERLAYER TON $ 147.45 989.80 1,12631 136.51 $ 20,128.40 29 HMA PAVEMENT SAMPLES AND TESTING LS $ 4,500.00 1.00 1.0000 - $ - 30 CASTING EXTENSION RING (INLET) EACH $ 200.00 17.00 13.00 (4.00) $ (800.00) 31 CASTING EXTENSION RING (MANHOLE) EACH $ 615.00 54.00 54.00 - $ - 32 FURNISH AND INSTALL MANHOLE CASTING EACH $ 890.00 1.00 (1.00) $ (890.00) 33 PAVEMENT SYMBOLS EACH $ 400.00 4.00 7.00 3.00 $ 1,200.00 34 PAINTED PAVEMENT MARKINGS STA $ 47.00 250.03 164.73 (8530) $ (4,009.10) 35 RAILROAD PERMIT AND INSURANCE LS $ 5,539.00 1.00 1.00 - $ - 36 TRAFFIC CONTROL LS $ 77,585.00 1.00 1.0000 - $ - 1001 GRIND TREE STUMP LS $ 165.00 1.00 1.00 - $ - 2001 REMOVE SIDEWALK SY $ 10.00 35.60 23.40 (1220) $ (122.00) 2002 SIDEWALK, 6" PCC SY $ 53.00 35.60 17.40 (18.20) $ (964.60) 2003 PEDESTRIAN RAMP DETECTABLE WARNING SURFACE SF $ 31.25 40.00 40.00 - $ - 2004 MODIFIED SUBBASE TON $ 27.40 9.00 (9.00) $ (246.60) 2005 HMA (1,000,000 ESAL) SURFACE, 1/2" MIX , NO FRICTION REQD., 60% CR. TON $ 10930 40.00 89.51 49.51 $ 5,411.44 2006 HMA (1,000,000 ESAL) INTERMEDIATE, 3/4" MIX, 60% CR. TON $ 108.80 - 165.04 165.04 $ 17,956.35 3001 HMA (1,000,000 ESAL) INTERMEDIATE, 3/4" MIX, 60% CR. TON $ 108.80 50.00 71.09 21.09 $ 2,294.59 4001 MODIFIED SUBBASE TON $ 27.40 2424 2424 $ 664.18 4002 HMA (1,000,000 ESAL) SURFACE, 1/2" MIX , NO FRICTION REQD., 60% CR. TON $ 10930 - 150.74 150.74 $ 16,475.88 4003 PAINTED PAVEMENT MARKINGS STA $ 47.00 - 722 722 $ 33934 INCREASFJDECREASE $ (22,128.60) PAY ESTIMATE #1 April 14, 2016 $ 18,57725 ; ' ' .. 4;,1J2,' PAY ESTIMATE #2 April 28, 2016 $ 31,281.70 ' / /®�J'//j� PAY ESTIMATE #3 May 14, 2016 $ 276,228.43 Aspro Date PAY ESTIMATE #4 June 2, 2016 $ 319,167.08 PAY ESTIMATE #5 June 11, 2015 $ 49,563.97 PAY ESTIMATE #6 July 15, 2016 $ 69 334.98/16 Jo �' / �T5ate � PAY ESTIMATE #7 July 29, 2016 $ 579,307.75 Cityof Water PAY ESTIMATE #8 August 29, 2016 $ 236,543.80 PAY ESTIMATE #9 September 30, 2016 $ 23,42136 PAY ESTIMATE #10 October 13, 2016 $ 17,479.40 RETAINAGE $ 82 97.14 TOTAL PAYMENT $ 1,703,302.86 ORIGINAL CONTRACT AMOUNT $ 1,711,715.06 CHANGE ORDER #1 SIGNED BY CITY ENGINEER $ 165.00 CHANGE ORDER #2 SIGNED BY CITY ENGINEER $ 8,111.40 CHANGE ORDER #3 SIGNED BY CITY ENGINEER $ 5,440.00 FINAL QUANTITY ADJUSTMENT $ (22,128.60) FINAL CONTRACT AMOUNT $ 1,703,302.86