HomeMy WebLinkAboutModern Builders Inc-11/7/2016CHANGE ORDER NO. 1
Owner Waterloo Regional Airport, City of Waterloo, Iowa Date November 1, 2016
Project Hangar No. 4 Wall Repairs
Owner's Contract No. State Contract No. 17448 Contractor Modern Builders, Inc.
Date of Contract Start September 19, 2016
You are directed to make the following changes in the Contract Documents. Description:
NO.M
DESCRIPTION
UNIT
PRICE
QUANTITY
AMOUNT
101
Tuck Point and Seal West Office Wall
LS
$ 4,500.00
1
$ 4,500.00
TOTALS
$ 4,500.00
Reason for Change Order:
Item 101— During construction activities at Hangar #4, it was determined that infiltration was also occurring along
the west wall of the office area. This change order will provide tuck pointing of the west office wall, power
washing of the wall, subgrade foundation coating of the wall below grade and painting of the wall.
Hangar #4 Wall Repairs
CO -1 (REVISED)
1
Project No — 60482850
CONTRACT PRICE
Original: $ 72,168.00
Previous C.O.s (ADD): $ 0.00
This C.O. (ADD): $ 4,500.00
Contract Price with all
approved Change Orders: $ 76,668.00
CONTRACT TIMES (Calendar Date)
Substantial Final
completion completion
Original:
Previous C.O.s (ADD):
This C.O. (ADD):
REVISED:
11/18/2016
0
0
11/18/2016
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the
change(s) ordered herein, including all impact, delays, and acceleration costs. Other than the dollar amount and time
allowance listed above, there shall be no further time or dollar compensation as a result of this Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO.
RECOMMENDED:
By
Engineer (Authorized Siature)
APPROVED:
By: 615_—
Owner (Authorized Signature)
ACCEPTED:
X/1
By
Contractor (Authorized Signature)
November 29, 2016
Date
2-1
1
Date Cz w�c i� , ,�,�i ccL l� /, t,
Date
Hangar #4 Wall Repairs
CO -1 (REVISED)
2
Project No — 60482850