HomeMy WebLinkAboutVieth Construction Co-12/5/2016CITY OF WATERLOO, IOWA CHANGE or EXTRA WORK ORDER NO. 1 PROJECT: F.Y. 2016 STORM SEWER IMPROVEMENTS Date Prepared: October 13, 2016 TO: Vieth Construction Company , CONTRACT NO. 906 AMOUNT: $ 1,369.50 Decrease , Contractor You are hereby ordered to make the following changes from the plans and specifications the following extra work on your contract dated May 23, 2016. A. Description of change to be made or extra work to be done: Adjust original construction quantities to actual construction quantities. B. Reason for ordering change or extra work: As -built quantities varied for some bid items. C. Settlement for cost of work to be made as follows: Compensation already made to contractor through original bid items. See attached summary. CITY OF WATERLOO BY: Mayor Date U..,,ur () cam_ ; )2.-10 I 6 Total Net Decrease $ 1,369.50 ATTEST: i City Clerk Vieth Construction Company or perform CONTRACTOR BY: PRINTED NAME: Date TITLE: Pre'S Date APPROVED: t 7� jr kA City Engineer /:',//;:- Date 1//4sDate BID ITEM F.Y. 2016 STORM SEWER IMPROVEMENTS CONTRACT #906 FINAL QUANTITY SUMMARY 900 BLOCK CARTER STREET DESCRIPTION DIVISION I 1 RECYLED ASPHALT PAVING 2 CLASS A CRUSHED STONE 3 CONVENTIONAL SEEDING AND FERTILIZING, TYPE 1 SEED MIX 4 IRECP TYPE 2 5 TOPSOIL, 4" 6 DROP-IN INLET PROTECTION 7 I TRAFFIC CONTROL 8 ,_STORM SEWER, 200013, 15" 9 SW -511 MODIFIED RECTANGULAR AREA INLET 10 SW -401 CIRCULAR STORM SEWER MANHOLE 1 I MANHOLE, MINOR ADJUSTMENT 12 CLASS 10 EXCAVATION 13 REM/REP 7.5" I -TMA DRIVEWAY 14 REM/REP 7"PCC/4.5"HMA COMPOSITE PATCH TOTAL DIVISION I BID CENTER STREET ALLEY ITEM DESCRIPTION DIVISION If 1 RECYLED ASPHALT PAVING 2 CONVENTIONAL SEEDING AND FERTILIZING, TYPE 1 SEED MIN 3 TOPSOIL, 4" 4 RECP, TYPE 2 5 TRAFFIC CONTROL 6 STORM SEWER, 2000D, 12" 7 CONCRETE COLLAR 3 SW -512 CIRCULAR AREA INLET 9 SW -401 CIRCULAR STORM SEWER MANHOLE 10 CLASS 10 EXCAVATION *II REM/REP 4" SIDEWALK 12 REM/REP 6"PCCI4.0"HMA COMPOSITE PATCH 13 RAILROAD TIE REMOVALS 14 PLUG STORM SEWER TOTAL DIVISION If BID COTTONWOOD CUNETTE ITEM DESCRIPTION DIVISION 1[1 1 PAVEMENT REMOVAL 2 SAW CUT UNIT TON TON SY.. SY 5Y EACH LS LF EACH EACl-1 EACH CY SY SY VIETII ORIGINAL FINAL INCR/DECR UNIT. PRICE OUANTITy QUANTITY QUANTITY $ 25.00 263.5 307,66 44..16 $ 26,00 153.2 97.95 ._. (55.25) $ 2.00 349.3, 182.70 (166.60) $ 2.00 349.3 182.70 ` (166.60) $ 8.00 349.3 182.70 (166.60) $ 250.00s 1.0 2.00 1.00 $450.00._ 1.0 1.00' $ 42.50. 143.0 143.00 5 5,700.001.0 1.00 $ 3,225.00 - 1.0 1.00.' - 5'900.00 LO 4,00 3.00. 529.00 451.5 472.00 20.50 $ 96.00 258.3 255.00' (3.30) 5.155.00 35.8 26:00' (9.80) VIETEI TOTAL FINAL INCR/DECR UNIT UNIT PRICE QUANTITY QUANTITY OUANTITY TON 5 27.00 1653 127.58 (37.92) SY $ 2.00 _ 6025.7525.00:' (77.70) SY S'5.00' 602.7 525.00 (77.70) SY $ 2.00 602,7 525.00 (77,70) LS $ 450.00 1.0 1.00 - LF 5 28.00 151.0 151.00 EACH $ 450.00 2.0 2.00 EACH $ 2,150.00 2.0 3.00 EACH 5 3,175.00 1.0 1.00 CY 5 37.00 162.8 162.80 - SY $ 95.00 9.1 18.30 9:70 SY $ 120.00 33.3 15.60 (17.70) LS 5 1,000.00 1.0 1.00 LS $ 825.00 1.0' 1.00 1.00 VIETEI TOTAL UNIT UNIT PRICE OUANTITY QUA TITS' OUANTITY FINAL INCR/DECR IV SY LF $.30.00 $5.00 20.6 12.44 178,0 170.00 (8.16) (8.00) INCR/DECR AMOUNT $1,104.00 $:(1,436.50: $;(333,20; (333:20; $ (1,332.80,. 250.00 $.- $ $- $- $ 2,70000: $ 594.50 $(316.80; $ (],519.00] $,(623.00; INCR/DECR AMOUNT $ (1,023.84' $.(155.40; 5' (388.50; $ (155.40; 5 5 - 5- 5 2,150.00 5- 5_ 5,874.00 $ (2,124.00 5- $- $,(823.14; INCR/DECR AMOUNT $ (244.80; $(40,00) 3 REMOVE. SALVAGE AND RE -INSTALL STORM SEWER, 2000D, 18" 4 STORM SEWER, 2000D, 18" 5 SW -512 CIRCULAR AREA INTAKE 6 5" PCC PAVEMENT, C-4 7 6" PCC PAVEMENT, C-4 8 CLASS 10_EXCAVATION 9 REMOVE, SALVAGE AND RE -INSTALL EROSION STONE 10 REMOVE AND RE -INSTALL OBJECT MARKERS 11 TRAFFIC CONTROL 12 _ TOPSOIL, 4" 13 RECP, TYPE 2 14 CONVENTIONAL SEEDING AND FERTILIZING, TYPE 1 SEED MIX TOTAL DIVISION III BID 800 BLOCK FAIRVIEW AVENUE ITEM DESCRIPTION DIVISION IV 1 RECYLED ASPHALT PAVING 2 CLASS A CRUSHED STONE 3 CONVENTIONAL SEEDING, TYPE I SEED MIX 4 RECP,TYPE2 5 TOPSOIL, 4" 6 DROP-IN INLET PROTECTION 7 TRAFFIC CONTROL 8 STORM SEWER, 2000D, 12" 9 SW -501. TYPE Q CASTING 10 COLLAR STRUCTURE OR PIPE 11 CLASS 10 EXCAVATION TOTAL DIVISION IV INCREASE/DECREASE PAY ESTIMATE #1 PAY ESTIMATE #2 PAY ESTIMATE #3 PAY ESTIMATE 44 PAY ESTIMATE #5 PAY ESTIMATE #6 RETAINAGE TOTAL PAYMENT July 11,2016 March 8. 2016 August 5, 2016 August 29, 2016 September 12, 2016 September 16, 2016 ORIGINAL CONTRACT AMOUNT CHANGE ORDER #1 SIGNED BY CITY ENGINEER ' FINAL QUANTITY ADJUSTMENT FINAL CONTRACT AMOUNT LF LF EACII SY SY CY SY EACH LS SY SY SY $. 80.00: $ 60.00 $ 2_,150.00 $ 66.00 3'50.00( $ 62.501 $ 57.001 $ 110,001 $ 330.00 $ 6.00 $ 2.00 $ 2.00 VIETH UNIT UNIT PRICE TON TON SY SY SY EACH LS LF EACH EACH CY $26.00 $ 26.00 $ 2.00 $ 2.00 $ 6.00 3250.00 $ 450.00 $ 45.00 $ 4,600.00 $ 1,200.00 $ 42.00 16.0 8.0 1.0 12.3 136.7 65.1 41.2 2.0 1.0 0.0 0.0 0.0 TOTAL QUANTITY $ 34,208.70 e••". $ 53,397.26 $ 24,173.33 VIETFI $ 41,890.35 $ 4,627.67 $ 1.096 $8 $I 225.60 3230 528.20 528.20 528.20 2.00 1.00 134.00 2.00 1.00 22130 16.00 8.00 1.00 1/ 44 141.10 65.10 41.20 2.00 1.00 31.89 31.89 31.89 0.14, 4.40'. 31.89' 31.89 31.89 FINAL INCR/DECR QUANTITY QUANTITY 245.17 19.58 478.22 478.22 478.22 2.00 1.00 137.00 2.00 1.00 221.30 19.57 (12.72) (49.98) (49.98) (49.98) 3.00 Date /// �� $924 $ 220.00 $- $- $- 3- $ 191.34. $ 63.78 $ 63.78 $ 263.34 INCR/DECR AMOUNT $ 508.82 $ (330.72; $ (99.96) $ (99.96) $ (299.881 $- $- $ 135.00 8- $- $- $ (186.70; $ (1,369.50; ,152.95 $- $ (1,369.50) $ 167,783.44 I•iem Coversheet Page 1 of 1 CITY OF WATERLOO Council Communication ciA*Q Wsk Motion approving Change Order No. 1 for a net decrease of $1,369.50 for the F.Y. 2016 Storm Sewer Improvements, Contract No. 906; and authorize the Mayor and City Clerk to execute said document. City Council Meeting: 12/5/2016 Prepared: 11/30/2016 REVIEWERS: Department Reviewer Action Date Engineering Thorson, Eric Rejected 11/30/2016 - 10:12 AM SUBJECT: Submitted by: Summary Statement: Source of Funds: Motion approving Change Order No. 1 for a net decrease of $1,369.50 for the F.Y. 2016 Storm Sewer Improvements, Contract No. 906: and authorize the Mayor and City Clerk to execute said document. Submitted By: Jamie Knutson, PE, Associate Engineer This is the accumulated amount of adjustments from original to Final quantities that were determined necessary during the construction of the project, which results in a decrease to the total project Bost. Storm Water Fees http://waterloo.novusagenda.com/AgendaWeb/CoverSheet.aspx?ItemID=6975 11/30/2016