HomeMy WebLinkAboutCedar Valley Corporation-12/12/2016CITY OF WATERLOO, IOWA CHANGE or EXTRA WORK ORDER NO. 2 PROJECT: Midport Boulevard Phase III, City Contract # 894 Date Prepared: November 22, 2016 AMOUNT: $ 11,717.94 Decrease TO: Cedar Valley Corporation , Contractor You are hereby ordered to make the following changes from the plans and specifications or perform the following extra work on your contract dated April 5, 2016. A. Description of change to be made or extra work to be done: Adjust original construction quantifies to actual construction quantities. B. Reason for ordering change or extra work: As -built quantities varied for some bid items. C. Settlement for cost of work to be made as follows: Compensation already made to contractor through original bid items. See attached summary. CITY OF WATERLOO BY: au.9.11, Mayor ATTEST: )LQ 1r Total Net Decrease $ 11,717.94 Z/I Date City Clerk h-- h -I cc Date Cedar Valley Corporation CONTRA//r BY: �G Z OR 'Date PRINTED NAME: / , PC QVE TITLE:c�.z,.l' APPROVED: City Engineer Date Final Quantity Summary Midport Boulevard Phase III City Contact No. 894 RM -8155(748)--9D-07 AECOM PROJECT NO. 60491666 Item No. Item Unit Unit Cost Original Quantity Final Quantity Quanity Difference Increase/ Decrease Final Amount 1 SPECIAL BACKFILL CY $ 32.50 1114.9 1,114.90 - $ - $ 36,234.25 2 EXCAVATION, CLASS 10, ROADWAY AND BORROW CY $ 5.77 6828.0 6,828.00 - $ - $ 39,397.56 3 EXCAVATION, CLASS 12, BOULDERS OR ROCK FRAGMENTS CY $ 75.00 50.0 (50.00) $ (3,750.00) $ - 4 TOPSOIL, STRIP, SALVAGE AND SPREAD CY $ 2.75 3,046.0 3,046.00 - $ - $ 8,376.50 5 SPECIAL COMPACTION OF SUBGRADE STA $ 120.00 17.3 17.30 - $ - $ 2,076.00 6 REMOVAL OF PAVEMENT SY $ 6.00 31.1 77.80 46.70 $ 280.20 $ 466.80 7 SUBGRADE STABILIZATION MATERIAL, POLYMER GRID SY $ 1.80 6,689.1 6,689.10 - $ - $ 12,040.38 8 MODIFIED SUBBASE CY $ 32.75 1,114.9 1,121.30 6.40 $ 209.60 $ 36,722.58 9 PCC PAVEMENT, CLASS C, CLASS 3 DURABILITY, 10 IN. SY $ 38.03 5,542.4 5,581.00 38.60 $ 1,467.96 $ 212,245.43 10 GRANULAR SURFACING ON ROAD, CLASS A CRUSHED STONE TON $ 18.00 100.0 (100.00) $ (1,800.00) $ - 11 APRONS, CONCRETE, 18 IN. DIA. EACH $ 1,025.00 2.0 2.00 - $ - $ 2,050.00 12 SUBDRAIN, LONGITUDINAL, (SHOULDER) 4 IN. DIA. LF $ 6.50 1,945.0 1,945.00 - $ - $ 12,642.50 13 SUBDRAIN OUTLET (RF -19C) EACH $ 75.00 13.0 10.00 (3.00) $ (225.00) $ 750.00 14 INTAKE, SW -508 EACH $ 3,200.00 3.0 3.00 - $ - $ 9,600.00 15 INTAKE, SW -510 EACH $ 3,500.00 4.0 4.00 - $ - $ 14,000.00 16 STORM SEWER GRAVITY MAIN, TRENCHED, RCP, 2000D, 15 IN. LF $ 33.00 100.0 100.00 - $ - $ 3,300.00 17 STORM SEWER GRAVITY MAIN, TRENCHED, RCP, 2000D, 18 IN. LF $ 35.00 653.0 655.00 2.00 $ 70.00 $ 22,925.00 18 STORM SEWER GRAVITY MAIN, TRENCHED, RCP, 2000D, 24 IN. LF $ 55.00 221.0 225.50 4.50 $ 247.50 $ 12,402.50 19 STORM SEWER GRAVITY MAIN, TRENCHED, RCP, 2000D, 30 IN. LF $ 67.00 760.6 749.90 (10.70) $ (716.90) $ 50,243.30 20 STORM SEWER GRAVITY MAIN, TRENCHED, RCP, 2000D, 36 IN. LF $ 77.00 137.2 137.20 - $ - $ 10,564.40 21 ENGINEERING FABRIC SY $ 2.00 22.0 (22.00) $ (44.00) $ - 22 EROSION STONE TON $ 35.00 12.0 (12.00) $ (420.00) $ - 23 SAFETY CLOSURE EACH $ 100.00 2.0 2.00 - $ - $ 200.00 24 REMOVAL OF TYPE A SIGN EACH $ 125.00 8.0 8.00 - $ - $ 1,000.00 25 DELINEATOR, RIGID -TYPE I EACH $ 50.00 18.0 18.00 - $ - $ 900.00 26 WOOD POSTS FOR TYPE A OR B SIGNS, 4 IN. X 4 IN. LF $ 14.00 42.0 42.00 - $ - $ 588.00 27 TYPE A SIGNS, SHEET ALUMINUM SF $ 13.00 19.5 19.50 - $ - $ 253.50 28 PAINTED PAVEMENT MARKING, WATERBORNE OR SOLVENT -BASED STA $ 40.00 34.6 35.20 0.60 $ 24.00 $ 1,408.00 29 TRAFFIC CONTROL LS $ 1,400.00 1.0 1.00 - $ - $ 1,400.00 30 MOBILIZATION LS $ 19,285.00 1.0 1.00 - $ - $ 19,285.00 31 MOWING ACRE $ 175.00 10.3 (10.32) $ (1,806.00) $ - 32 MULCHING ACRE $ 2,925.00 5.2 5.20 0.04 $ 117.00 $ 15,210.00 33 SEEDING AND FERTILIZING (URBAN) ACRE $ 980.00 5.2 5.20 0.04 $ 39.20 $ 5,096.00 34 STABILIZING CROP - SEEDING AND FERTILIZING ACRE $ 400.00 5.2 (5.16) $ (2,064.00) $ - 35 SWPPP - MANAGEMENT LS $ 4,000.00 1.0 1.00 - $ - $ 4,000.00 Final Quantity Summary Midport Boulevard Phase III City Contact No. 894 RM -8155(748)--9D-07 AECOM PROJECT NO. 60491666 Item No. Item Unit Unit Cost Original Quantity Final Quantity Quanity Difference Increase/ Decrease Final Amount 36 SWPPP - QUALIFYING RAINFALL INSPECTION EACH $ 50.00 10.0 (10.00) $ (500.00) $ - 37 WATTLES - INSTALLATION LF $ 2.00 420.0 120.00 (300.00) $ (600.00) $ 240.00 38 WATTLES - REMOVAL LF $ 0.50 420.0 100.00 (320.00) $ (160.00) $ 50.00 39 SILT FENCE - INSTALLATION LF $ 2.00 1,600.0 1,150.00 (450.00) $ (900.00) $ 2,300.00 40 SILT FENCE - REMOVAL OF SEDIMENT LF $ 0.10 1,600.0 (1,600.00) $ (160.00) $ - 41 SILT FENCE - REMOVAL OF DEVICE LF $ 0.50 1,600.0 1,637.00 37.00 $ 18.50 $ 818.50 42 SPECIAL DITCH CONTROL RECP TYPE 3 SQ $ 19.00 343.0 309.00 (34.00) $ (646.00) $ 5,871.00 43 INLET PROTECTION DEVICE EACH $ 150.00 10.0 8.00 (2.00) $ (300.00) $ 1,200.00 44 INLET PROTECTION DEVICE MAINTENANCE EACH $ 50.00 10.0 8.00 (2.00) $ (100.00) $ 400.00 45 TWO-YEAR MAINTENANCE BOND LS $ 2,000.00 1.0 1.00 - $ - $ 2,000.00 1-1 REMOVE EXISTING HEADER, DRILL/GROUT BARS LS $ 1,046.36 1.0 1.00 - $ - $ 1,046.36 Increase/Decrease $ (11,717.94) Pay Est #1 $ 54,150.76 Original Contract Amount $ 559,975.14 Pay Est #2 $ 73,762.89 Change Order #1 $ 1,046.36 Pay Est #3 $ 132,453.76 Increase/Decrease Change Order $ (11,717.94) Pay Est #4 $ 213,990.76 Final Contract Amount $ 549,303.56 Pay Est #5 $ 6,870.40 Pay Est #6 $ 21,997.07 Pay Est #7 $ 18,612.74 Pay Est #8 $ 27,465.18 Total All Payments $ 549,303.56 Coversheet CITY OF WATERLOO Council Communication Page 1 of 1 Motion approving Change Order No. 2 for a net decrease of $11,717.94 for the F.Y. 2016 Midport Boulevard Extension - Phase III, Contract No. 894, and authorize the Mayo City Clerk to execute said document. City Council Meetin Prepared: 12/7/2016 12/12/2016 ATTACHMENTS: Description Type Cont 894 final CO Cover Memo a Cont 894 final qty summary Cover Memo SUBJECT: Submitted by: Summary Statement: Source of Funds: Motion approving Change Order No. 2 for a net decrease of $11,717.94 for the F.Y. 2016 Midport Boulevard Extension - Phase III, Contract No. 894, and authorize the Mayor and City Clerk to execute said document. Submitted By: Jeff Bales, Associate Engineer This is the accumulated amount of adjustments from original to final quantities that were determined necessary during the construction of the project, which results in a decrease to the total project cost. Midport TIF & RISE http://waterloo.novusagenda.com/AgendaWeb/CoverSheet.aspx?ItemID=7039 12/7/2016