HomeMy WebLinkAboutIowa Department of Natural Resources-2/6/2017Iowa Department of Natural Resources
Wastewater Section
Construction Permit Application
Sewage Treatment Agreement
INSTRUCTIONS
This agreement must be executed for all projects where construction and sewage treatment will be provided by different parties;
i.e., a private subdivision connecting to a municipal system. This agreement must be executed by the parties who are owners at the
time the permit is issued, regardless of whether title to the proposed construction project will be transferred after completion of the
project.
This agreement is not necessary when a contract for sewage treatment already exists; i.e., service contracts between municipalities.
However, the Department of Natural Resources must be informed in writing that the contractual agreement does exist.
APPLICANT
Owner: Midwest Development Co.
ENGINEER
Firm: Wayne Claassen Engineering and Surveying, Inc.
Address: 411 1st Ave., SE,Suite 410, Cedar rapids, is 52401
P.O. Box 898, 2705 University Ave., Waterloo, la
Address: 50704
Representative: Kevin M. Fittro
Project Officer: Thomas J. Noonan
Phone Number: 319-277-7862
Phone Number: 319-235-6294
Project Identification: Audubon Heights 6th Addition
Owner and System Receiving Wastes: City of Waterloo, la
CERTIFICATION
I am the authorized representative of the owner identified above and state that the proposed sanitary sewage facilities shall be
constructed in accordance with the plans and specifications and all wastes contributed by this project shall be discharged to the
treatment system identified above.
Signature ___-, Title: 1/, A Date /-0--/1
AGREEMENT TO PROVIDE SEWAGE TREATMENT
I am the authorized representative of the owner of the system identified above and state that the connection of the proposed
sanitary sewage facilities identified above is approved by the owner, and that the owner accepts responsibility for providing
adequate treatment of all wastes contributed by this project, in accordance with the provisions of Chapter 455B, Code of Iowa, and
the rules of the Department of Natural Resources. This agreement shall be construed in any way to affect any local ordinances,
sewer service agreements, or fee systems entered into between the parties.
Name: Title:
Signature(k*/Date �/6 /i1 Phone:
11 lona r .........
r Mo C.....-, CAo 4110.10
IOWA DEPARTMENT OF NATURAL RESOURCES
Wastewater Disposal System Construction Permit
Application Fee Form
CASHIER'S USE ONLY
0945-542-N PDE -CP -0570
32-3202
Owner
Owner Name: City of waterloo, la
Address: 715 mulberry St.
City, State, Zip: Waterloo, la 50703
Project Identification: Audubon heights 6th Addition
® $100 Fee enclosed
Please sign and return this form with a check or money order payable to "Iowa Department of Natural Resources".
Place it and the check or money order on top of other Construction Permit Application documents.
Effective beginning July 1, 2006, Applications for Construction Permits for wastewater disposal systems required by
Iowa Code 455B.173 and rules in Iowa Administrative Code 567 IAC 64, must be accompanied by the fee required by
Iowa Code 4556.197 and Iowa Administrative Code 567 IAC 64.16(3)"c".
The fee is $100 for each application, regardless of project size and project type including sanitary sewers, pump
stations, treatment units or a combination thereof. The fee shall be submitted with the certified engineering documents
necessary to apply for a construction permit (plans, specifications and related application schedules A, F, and G as well
as the appropriate schedules indentified on page 2 of Schedule A). The construction permitting process is initiated as
planning for construction begins. Planning coordination and submittal of preliminary engineering reports or facility plans
precedes submittal of technical documents necessary to constitute a construction permit application. The application
fee is not necessary when submitting a planning document but must accompany construction permit application
documents. A fee should accompany each permit application received on or after July 1, 2006.
Failure to submit a fee with the application may delay the processing of a construction permit. If you have any questions
regarding the application fee, please contact Donna Gomm at 515-725-8427 or Donna.Gomm@dnr.iowa.gov
Signature of Owner or Representative:
Printed Name:
Telephone or email contact:
Mail to:
Iowa Department of Natural Resources
Wastewater Engineering Section
502 East 9th Street
Des Moines, IA 50319-0034
/64'44 a 1(.5 AA
11/2014 cmc DNR Form 542-1245
Exhibit 11A
Iowa Department of Natural Resources
Wastewater Section
Construction Permit Application
SCHEDULE A, Construction Permit Application
APPLICANT
Owner: Midwest Development Co.
411 Ist Ave., SE, Suite 410,
Address: 52401
Cedar Rapids, la
Representative: Kevin M. Fittro
Phone Number: 319-277-7862
Email: kfittro@skogman.com
ENGINEER
Firm: Wayne Claassen Engineering and Surveying, Inc.
P.O. Box 898, 2705 University Ave., waterloo, la
Address: 50704
Project Officer: Thomas J. Noonan
Phone Number: 319-235-6294
Email: noonan@wcesinc.com
Project Identification: Audubon Heights 6th Addition
Estimated Start Date*: April, 2017 Estimated Completion Date: Sept., 2017
PLEASE RESPOND TO ALL QUESTIONS
1. Has an engineering report, facilities plan or other information previously been submitted for this project?
If Yes: Project Identity: Date Submitted:
2. Does the project and construction permit application, as submitted, follow the recommendations, design loadings, ❑ ❑
construction schedule, permit limits, and conclusions of the approved engineering report or facilities plan?
If No: Provide the design basis and technical information justifying all changes.
3. Are there three complete sets of plans and specifications accompanying this application?
Yes No
® ❑
For a minor gravity sewer extension within the meaning of 4556.183.3 Code of Iowa and Design Standard 11.1, two complete
sets will be adequate for expeditious approval. For more complex projects, three sets of plans and specifications may be
requested.
4. Are approved standard specifications a part of this application?
If Yes: Approved Standard Specifications of
(municipality or firm): Date Approved:
5. Does each set of plans and specifications or engineering report accompanying this application contain a
"professional engineering seal" executed in conformance with 5426.16, Code of Iowa?
If No: Processing will be delayed pending receipt of applicable design schedules and certified plans, specifications or
engineering report.
6. Is this a joint wastewater and water supply project?
® ❑
® ❑
D
If Yes: A construction permit application for the water supply project should be submitted separately to the Water Supply
Section. A Water Supply permit fee may be required.
7. Is the applicant to provide treatment of effluent resulting from this construction?
E
If No: A Sewage Treatment Agreement executed by the authority providing treatment must accompany this form.
8. Is a new or amended operation permit necessary to use the facilities described in this application?
If Yes: A new or amended permit to operate may be requested prior to the receipt of a construction permit.
9. Is any waterline located within 10 feet; or any private or public well, lake, or public recreation area located within
400 feet of the proposed construction?
If Yes: Identify and locate the facility(ies) relative to the proposed construction.
10. Will construction inspection be conducted by a licensed engineer employed by the applicant?
If No: Name of Engineering Firm Conducting Inspection: Wayne Claassen Engineering and Surveying, Inc.
11. Will this project utilize CWSRF loan funds?
CERTIFICATION
O El
El
-/
APPLICANT
I certify that I am the authorized representative of the owner
and state that the project identified above is approved by the
owner.
Signature
Date
1, 21 Li'l
*Estimated Construction Start Date: Complete applications must be submitted at least 1
construction in accordance with Rules 567 IAC 60.4 and 64.2
ENGINEER
I certify that all aspects of the design included in this application
conform to applicable standards contained in Chapter 567 IAC
64, or that an explanation and justification for any proposed
variations from such standards is attached. I am familiar with the
information contained in this application and, to the best of my
knowledge, suc, nforma.io' '/: complete and accurate.
Signature '� I Grp Date i �15'-./ 2
day in advance of the date for starting
04/2016 cmc
DNR Form 542-3129: 28A
Please complete the Schedule Checklist on the following page of this form.
DOCUMENT CHECKLIST
Identify all categories included in this project. Also, identify schedules attached to this application.
Schedule
B Collection System
C Lateral Sewer Extension
D Trunk & Interceptor Sewer
E Wastewater Pump Station
F Treatment Project Site Selection
G Treatment Project Design Data
H1 Schematic Flow Diagram
H2 Treatment Process Loading and Removal Efficiency
H3 Mechanical Plant Reliability
Screening, Grit Removal and Flow Measurement
J Septic Tank System
K1 Controlled Discharge Pond
K2 Aerated Pond
K3 Anaerobic Lagoon
L Setting Tanks
M Fixed Film Reactor -Stationary Media
N Rotating Biological Contactor
O Aeration Tanks or Basins
P Gas Chlorination
Q Sludge Digestion and Holding
R1 Sludge Dewatering and Disposal
R2 (A&B) Low Rate Land Application of Sludge
R3 Land Application of Sewage Sludge (To be developed)
S Land Application of Wastewater (To be developed)
Sewage Treatment Agreement
Title Attached Included in Project Submittal Date
E
0
❑ ❑
0
0
Identify any categories included in this project which are not provided in the above list of schedules.
04/2016 cmc
DNR Form 542-3129; 28A
Iowa Department of Natural Resources
Wastewater Section
Construction Permit Application
SCHEDULE B, Collection System
Date Prepared
Date Revised
Project Identity
Audubon Heights 6th Addition
DNR USE ONLY
Project No.
Permit No.
1. Identify proposed construction which is subject to flooding and explain what is proposed to prevent water from entering the
system. If no portion is subject to flooding, state none.
Segment
Flooding Protection
*2. Indicate hydraulic capacity of: 1) the nearest downstream main or interceptor; 2) the nearest downstream lift station; and 3) all
downstream segments where flow restriction may occur. Indicate the source and accuracy of numerical data.
Location
Design Capacity, MGD
Peak Hourly Dry weather Flow MGD (actual)
Peak Hourly Wet weather Flow MGD (actual)
Segment Segment Segment
Sergeant Rd.
21" Home
Sergeant Rd.
Park
48"
Day
3.24
16.35
60+
0.76
2.0
2.92
8.85
*3. Identify treatment facility, the design loadings and present raw waste loadings. Indicate source and accuracy of numerical data.
Facility Name and Number Waterloo Water Pollution Control Plant IA 079001 FED 0042650
Facility Loading
Design
Average Wet Weather (actual)
Peak Hourly Wet Weather (actual)
MGD #BODs/da
34.8
•
88,000
31,500 Avg
24.53
Day
48,000 Peak
60+
Day
Provide projected design loading increase, which will be added to this facility as a result of this project.
Design Loading Initial Design Year (2037)
Residential Service Area 0 Acres 24 Acres
Population 0 Persons 172 Persons
Flow (100 GPCD) 0 GPD 17,200 GPD
BODS (0.17/#/d/cap) 0 #/day 29.24 #/day
Industrial Service Area 0 Acres 0 Acres
Rated Flow 0 GPD 0 GPD
BODS 0 #/day 0 #/day
Other 0 0 Acres 0 Acres
Rated Flow 0 GPD 0 GPD
BODS 0 #/day 0 #/day
Total BODS 0 #/day 29.24 #/day
Total Flow 0 GPD 17,200 GPD
11/2015 cmc
DNR Form 542-3095; 28B
Peak Hourly Flow 0 GPD 68,800 GPD
*Include a written explanation of items 2 and 3 if the sewer system and/or treatment facility are overloaded.
11/2015 cmc
DNR Form 542-3095; 28B
Iowa Department of Natural Resources
Wastewater Section
Construction Permit Application
SCHEDULE C, Lateral Sewer Extension
Date Prepared
Date Revised
Project Identity
Audubon heights 6th Addition
DNR USE ONLY
Project No.
Permit No.
1. Design Basis
Residential Service Area
Population
Flow (100 GPCD)
BODS (0.17/#/d/cap)
Industrial Service Area
Rated Flow
BO D5
Other
Initial
0 Acres 24 Acres
0 Persons 172 Persons
0 GPD 17,200 GPD
0 #/day 29.24 #/day
0 Acres 0 Acres
0 GPD 0 GPD
0 #/day 0 #/day
0 Acres 0 Acres
Rated Flow 0 GPD 0 GPD
BOD5 0 #/day 0 #/day
Total BOD5 0 #/day 29.24 #/day
Total Flow 0 GPD 17,200 GPD
Peak Hourly Flow 0 GPD 68,800 GPD
2. Pipe Diameter 8 Inch 10 Inch 12 Inch
Material PVC PVC
Joint Rubber Rubber
Minimum Slope 0.40 % % 0.22
Maximum Manhole Space 285 ft. ft. 400 ft.
Total Sewer Length 1519 ft. ft. 606 ft.
Maximum Cover 13.0 ft. ft. 14.4 ft.
Minimum Cover 9.8 ft. ft. 11.5 ft.
3. Construction specifications (indicate ASTM Number or other standard included in the specifications). A brief description is
required in each part.
A. Bedding class Class 1A, 95% STD
Design Year (2037)
B. Pipe laying
C. Compaction
D. Manhole
D3034, D2321
D698, 95%
C476, C433
E. Specified maximum infiltration/exfiltration rate 200 GPDPMPI
F. Infiltration/exfiltration test procedures Air
G. Alignment & grade test procedures
(1) During construction Stake & batterboard Laser X
(2) After construction Lamping X Other TV
H. Deflection test procedures NA
4. Are detailed manhole drawings included: ® Yes ❑ No Typical frame and cover assembly Neenah R-1642
Are manhole covers nonvented: // Yes ❑ No Manhole diameter 48 in.
Manhole opening diameter 24 In Material Precast PCC, Cast iron
5. Minimum sewer & water main separation: Horizontal 10 ft. Vertical 18
Are specifications included Yes
in.
6. Stream, road, or railroad crossing protection No
Are specifications included NA
11/2015 cmc
DNR Form 542-3096; 28C