HomeMy WebLinkAboutJasper Construction Services-3/20/2017CHANGE ORDER NO. 6-1 Owner: City of Waterloo Date: 3-14-17 Project: Repairs to 6th St, 18th St, and Ansborouoh Avenue Owner's Contract No. 916 Contractor: Jasper Construction Services Date of Contract Start: 9-17-16 $ 223,910.00 You are directed to make the following changes in the Contract Documents. Description: Replace southwest expansion joint, repair southwest backwall concrete, clean south abutment seat, provide partial depth sidewalk patching, remove and replace southwest approach pavement, remove one damaged lateral bracing, and provide traffic control on the Park Avenue Bridge over the Cedar River as shown in attached sheets V.24 and V.25. Reason for Change Order: The abutment backwall supporting the expansion joints are failing at the southwest corner and sidewalk concrete is spalled. CONTRACT PRICE To substantial completion Original: $223,910.00 Previous CIO's (ADD/DEDUCT): $8,352.04 This C.O. (ADD/DEDUCT): $ 53,065.50 Contract Price with all approved Change Orders: $285,327.54 CONTRACT TIMES (Calendar Days) To final completion Original Completion Date: 06-02-17 (All Items) Previous CIO's (ADD/DEDUCT): N/A This C.O. (ADD/DEDUCT): N/A REVISED: N/A Revised Completion Date: 06-30-17 It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s) ordered herein, including all impact, delays, and acceleration costs. Other than the dollar amount and time allowance listed above, there shall be no further time or dollar compensation as a result of this Change Order. THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO. APPROVED: By: 14'i 3 /t "� / Date OWNER (Authorized Signature) ACCEPTED: By: 'y_ e ,% CONTRA T uthorized Signature) Date 3// eip 7 CHANGE ORDER FORM AECOM 60521749 AECOM, Inc. 60521749 / 6-1 Project Change Number Order No. Page CO -1 Item Coversheet Page 1 of 1 CITY OF WATERLOO Council Communication Motion to approve Change Order No. 6-1 for a net increase of $53,065.50 for the FY 2017 Bridge Repairs; 6th Street, 18th Street, and Ansborough Avenue, Contract No. 916, and authorize the Mayor and City Clerk to execute said document. City Council Meeting: 3/20/2017 Prepared: 3/15/2017 REVIEWERS: Department Reviewer Action Date Engineering Thorson, Eric Approved 3/15/2017 - 11:05 AM Clerk Office Even. LeAnn Approved 3/15/2017 - 2:32 PM ATTACHMENTS: Description Type t] Change Order 6-1 Cover Memo Submitted by: Submitted By: Wayne Castle, PLS, PE, Associate Engineer Summary Statement: Expenditure Required: Source of Funds: Background Information: $53,065.50 G.O. Bonds The temporary plates covering the failed expansion joint on the Park Ave. Bridge are working loose and are hard to keep attached. Therefore, a repair to the expansion joint is necessary to avoid continuous work on the plates to keep them attached. Also, since the contractor will be working on the bridge, some sidewalk is being patched to make it safer. http://waterloo.novusagenda.com/AgendaWeb/CoverSheet.aspx?ItemID=7835 3/17/2017 SEE DETAIL A REMOVE AND REPLACE REINFORCED APPROACH PAVEMENT SAWCUT DETAIL A 'E' JOINT EMOVE AND REPLACE EXISTING EXPANSION DEVICE SAWCUT SECTION B -B FLOORBEAM (UAC) EXISTINGAPLATES SHALL REMAIN PROPERTY OF THE CITY.(TO BE REMOVED AND HAULED OFF BY THE CITY.) TOP OF DECK OR BACKWALL SITUATION PLAN END OF STEEL EXTRUSION & CURBS END OF CONCRETE DECK & BACKWALL EXPANSION OPENING DETAIL A THIS DIMENSION MAY VARY SLIGHTLY DEPENDING ON MANUFACTURER FURNISHING THE JOINT. USED FOR ALL OUT TO OUT DIMENSIONS OF SLAB. AA THE DIMENSION MAY VARY SLIGHTLY DEPENDING ON MANUFACTURER FURNISHING THE JOINT. t EXPANSION JOINT SETTINGS STEEL EXTRUSION -Jf da1 2-R I11xex0'-8 TABLE OF APPROVED EXPANSION DEVICES - •, .-...r_____ TYPE OF STEEL EXTRUSION NEOPRENE GLAND TRAFFIC 0 - N A V PARK AVENUE SE -500 ., 80° F. !::::;) E Steel Extrusion Joint With Neoprene V O v N A w d LF Safety Closure (Includes Sidewalks) 8 TRAFFIC Traffic Control 1 LS Mobilization 1 y y 1 REMOVE AND REPLACE REINFORCED APPROACH PAVEMENT SAWCUT DETAIL A 'E' JOINT EMOVE AND REPLACE EXISTING EXPANSION DEVICE SAWCUT SECTION B -B FLOORBEAM (UAC) EXISTINGAPLATES SHALL REMAIN PROPERTY OF THE CITY.(TO BE REMOVED AND HAULED OFF BY THE CITY.) TOP OF DECK OR BACKWALL SITUATION PLAN END OF STEEL EXTRUSION & CURBS END OF CONCRETE DECK & BACKWALL EXPANSION OPENING DETAIL A THIS DIMENSION MAY VARY SLIGHTLY DEPENDING ON MANUFACTURER FURNISHING THE JOINT. USED FOR ALL OUT TO OUT DIMENSIONS OF SLAB. AA THE DIMENSION MAY VARY SLIGHTLY DEPENDING ON MANUFACTURER FURNISHING THE JOINT. t EXPANSION JOINT SETTINGS STEEL EXTRUSION -Jf da1 2-R I11xex0'-8 TABLE OF APPROVED EXPANSION DEVICES MANUFACTURER TYPE OF STEEL EXTRUSION NEOPRENE GLAND MINIMUM OPENING FOR GLAND INSTALLATION CORRESPONDING MAXIMUM DECK TEMPERATURE WATSON-BOWMAN & ACME CORP. A SE -500 2 IN. 80° F. 550 LB Steel Extrusion Joint With Neoprene 30 LF APPROVED EQUAL 30 LF Safety Closure (Includes Sidewalks) 8 EA Traffic Control 1 LS Mobilization Is AT 90° F. 28 AT 50° F. 41,6 AT 10° F. TOP OF DECK OR BACKWALL ANCHORAGE SYSTEM AT I'-6 MAX. SECTION THROUGH JOINT NOTEzJOINT SETTINGS FOR OTHER TEMPERATURES ARE PROPORTIONAL. TEMPERATURES SHOWN ARE CONCRETE DECK TEMPERATURES ON THE UNDERSIDE OR SHADED PORTION OF THE DECK. PARK AVENUE BRIDGE OVER CEDAR RIVER CITY BRIDGE N0. T FHWA NO.011831 LOCATION MAP (NOT TO SCALE) NOTES: CHANGE ORDER 6-1 INLCUDES ALL MATERIAL LABOR AND EQUIPMENT NECESSARY TO COMPLETE THE WORK DETAILED ON SHEETS V.24 AND V.25. PAY ITEM IS 'MISCELLANEOUS REPAIRS'. METHOD OF MEASUREMENT AND BASIS OF PAYMENT 15 LUMP SUM.REFER TO OTHER NOTES IN THESE PLANS FOR MATERIAL SPECIFICATIONS AND PROCEDURES SUCH AS NEOPRENE GLAND INSTALLATION AND WATER TESTING. BACKWALL AND DECK CONCRETE SHALL BE REMOVED TO SOUND CONCRETE, TO THE EXTENT THAT THE EXISTING EXPANSION DEVICE CAN BE REMOVED AND THE NEW EXPANSION DEVICE INSTALLED. ALL CONCRETE REMOVALS SHALL BE INITIATED WITH SAWCUTS TO PREVENT SPALLING. STRIAGHTEN CLEAN AND RE -USE LONGITUDINAL REINFORCEMENT AND HOOPS.SUPPLEMENT DAMAGED BARS WITH DRILLED -IN AND EPDXIED DOWELS AS DIRECTED BY THE ENGINEER.NEW TRANSVERSE BARS SHALL MATCH EXISTING SIZE AND SPACING. ALL SUPPLEMENTAL REINFORCEMENT SHALL BE EPDXY COATED. SIDEWALK PATCHING REMOVALS SHALL INCLUDE ALL LOOSE MATERIAL BY HAND AND COMPRESSED AIR METHODS.REMOVALS DOWN TO SOUND CONCRETE IS NOT REQUIRED. RAIL REMOVAL AND REPLACEMENT IS NOT REQUIRED TO FACILITATE ACCESS FOR REPAIRS.REMOVAL MATERIAL SHALL BE DISPOSED OF OFF-SITE BY THE CONTRACTOR. CONCRETE FOR SIDEWALK PATCHES SHALL BE DESIGNED FOR USE IN THIN SURFACE PATCH APPLICATIONS.PATCHES MAY BE HAND FINISHED BUT SHALL HAVE A NEAT SURFACE PROFILE THAT DRAINS WATER.CONCRETE PATCHES MAY TAPER FROM THE RAIL GUTTERLINE TO THE EDGE OF DECK AS REQUIRED TO ELIMINATE THE NEED FOR FORMING AT THE EDGE OF DECK. SEE SHEET V.25 FOR PATCH LOCATIONS. DEBRIS SHALL BE REMOVED FROM THE ABUTMENT SEATS AT THE SOUTH ABUTMENT WITH HAND AND COMPRESSED AIR METHODS. THE DAMAGED LATERAL BRACING SHALL BE REMOVED AND DISPOSED OF OFF-SITE.THE BRACING SHALL BE CUT OFF AT THE NEAREST JOINT LOCATION AS DIRECTED BY THE ENGINEER. SIDEWALK CLOSURES AND TRAFFIC CONTROL SHALL BE SIMILAR TO OTHER BRIDGE SITES ON THE PROJECT. Park Ave Bridge Repairs Item Quantity Unit Removals, As Per Plan 1 LS Structural Concrete (Misc.) 5 CY Reinforcing Steel, Epoxy Coated 550 LB Steel Extrusion Joint With Neoprene 30 LF Neoprene Gland Installation and Testing 30 LF Safety Closure (Includes Sidewalks) 8 EA Traffic Control 1 LS Mobilization 1 L5 Remove Lateral Bracing 1 EA Clean Abutment Seat 1 L5 Partial Depth Sidewalk Patching 275.1 SF Bridge Approach Pavement Remove and Replace 1 LS PARK AVENUE BRIDGE MISCELLANEOUS REPAIRS MAY, 2017 CITY OF WATERLOO, IOWA DESIGN TEAM AECOM CITY OF WATERLOO CONTRACT NUMBER 916 SHEET NUMBER V.24 L:\PROJECTS\Park Ave Patching\PARK AVE BRIDGE PATCHING.dwg 2/28/2017 1:18 PM N n 11 0 Not shown: Roughly 100 spot patches generally 0.25 SF in area H Areas roughly 1.0 SF to patch - 41 total -14 west side and 27 east side A n N N N(O 0, (D ,' CD -41 W b N 0. TI N O �a N N-1. 0 N 3 a' w o N rt CO d y � -n N CO co O V co -n N C) co cn TI '.7 0 0 A r NI m o co hs Cedar River 1, r co rt -u O 0 0 ITY OF WATERLOO, IOWA ENGINEERING DEPARTMENT 715 MULBERRY STREET WATERLOO, IOWA 50703 (319) 291-4312 PHONE (319) 291-4262 FAX sa;eld Iaa;S 'X3 { 0 FY2017 6th St, 18th St, & Ansborough Ave Bridge Repairs CONTRACT #916 ESTIMATED QUANTITIES PARK AVE BRIDGE SIDEWALK PATCHING