Loading...
HomeMy WebLinkAboutAspro Inc-5/22/2017CITY OF WATERLOO, IOWA CHANGE or EXTRA WORK ORDER NO. 2 PROJECT: F.Y. 2016 STREET RECONSTRUCTION PROGRAM, CONTRACT NO. 898 Date Prepared: November 15, 2016 AMOUNT: $ 109,888.00 INCREASE TO: ASPRO, INC. , Contractor You are hereby ordered to make the following changes from the plans and specifications or perform the following extra work on your contract dated April 4, 2016 A. Description of change to be made or extra work to be done: 2001-2008 Add construction of 30" storm sewer to the 700 block of Starlite Blvd. which is being reconstructed under this contract. B. Reason for ordering change or extra work: 2001-2008 Starlite Blvd. contains an outlet for storm sewer from University Avenue. Preliminary design o University Avenue storm sewer system indicates the need to increase the size of the storm sewer in this block to 30". This extra work order is to increase the size of the storm sewer with the street reconstruction, so this block of Starlite Blvd. will not be impacted with the University Ave. project. C. Settlement for cost of work to be made as follows: Item Description 2001 STORM SEWER, 2000D, 30" LF ...... w $136.40 .....tea. v,ay 525.00 , vaal $71,610.00 2002 SW -401, 60" DIA. EACH $6,710.00 2.00 $13,420.00 2003 TYPE E -2—C INLET, USE EXISTING CASTING EACH $3,300.00 3.00 $9,900.00 2004 FILL EXISTING AND PLUG 12 STORM SEWER EACH $324.50 2.00 $649.00 2005 COLLAR PIPE, SW -211 EACH $1,320.00 2.00 $2,640.00 2006 CORE DRILL MANHOLE FOR 30" DIA. PIPE EACH $3,420.00 2.00 $6,840.00 2007 ADDITIONAL STARLITE BLVD. SURVEY LS $1,309.00 1.00 $1,309.00 2008 ADDITIONAL STARLITE BLVD. TRAFFIC CONTROL LS $3,520.00 1.00 $3,520.00 TOTAL $109,888.00 CITY OF WATERLOO TOTAL INCREASE = //1 1 Date CONTRACTOR %a BY: / (11-7A—? 1) ASPRO, INC. $109,888.00 Change Order No. 2 PRINTED NAME: Milt Dakovich 5/// Date TITLE: President APPROVED: City EngineerDate Contract No. 898 5-JI5J/7 Page 1/1 Item Coversheet CITY OF WATERLOO Council Communication Page 1 of 1 Motion approving Change Order No. 2 for a net increase of $109.888.00 for the F.Y. 2016 Street Reconstruction Program, Contract No. 898; and authorize the Mayor and City Clerk to execute said document. City Council Meeting: 5/22/2017 Prepared: 5/17/2017 ATTACHMENTS: Description Cont 898 CO #2 SUBJECT: Submitted by: Recommended Action: Summary Statement: Source of Funds: Background Information: Type Motion approving Change Order No. 2 for a net increase of $109,888.00 for the F.Y. 2016 Street Reconstruction Program, Contract No. 898, and authorize the Mayor and City Clerk to execute said document. Submitted By: Dennis Gentz, PE, Assistant City Engineer Approve change order. Local Option Sales "fax Funds Starlite Blvd. contains an outlet for storm sewer from University Avenue. Preliminary design of University Avenue storm sewer system indicates the need to increase the size of the storm sewer in this block to 30". This extra work order is to increase the size of the storm sewer with the street reconstruction, so this block of Starlite Blvd. will not be impacted with the University Ave. project. https://waterloo.novusagenda.com/AgendaWeb/CoverSheet.aspx?ItemID=8491 5/17/2017