HomeMy WebLinkAboutPella Roofing - CO#1 Hangar 5 Rehab-8/7/2017Please return this copy to: City Clerk & Finance Dept. 715 Mulberry St. Waterloo, '4 50703 CHANGE ORDER NO. 1 Owner Waterloo Regional Airport, City of Waterloo, Iowa Date August 1 2017 Project Hangar 5 Rehabilitation Owner's Contract No. State Contract No. 18516 Contractor Pella Roofing & Insulation, Inc. Date of Contract Start July 17, 2017 You are directed to make the following changes in the Contract Documents. Description: ITEM NO. DESCRIPTION UNIT UNIT PRICE QUANTITY AMOUNT 3 Remove Existing Metal Roofing SFT $ 1.00 2,000 $ 2,000.00 4 Install New Metal Roofing— 24 GA SFT $ 3.00 2,000 $ 6,000.00 101 Reuse Existing Metal Gutter LS $ 2,450.00 (1) ($ 2,450.00) TOTALS $ 5,550.00 Reason for Change Order: Items 3& 4 — During detailed review of the existing metal roof by the contractor it was determined that replacement of additional metal roof panels beyond the contracted amount would be required because of an additional amount of metal panels that were determined to be in need of replacement because of the panel conditions. This change order will allow for an removal and replacement of an additional 2,000 square foot of metal roof panels. Item 101 — The contractor provided a value engineering item to reduce cost of the project. The existing gutter system was reviewed in the field and determined to be in excellent condition. The contractor will remove the existing gutter system, provide sealant material behind the existing gutter, reattach the existing gutter and provide 2 additional open downspouts on each side of the hangar. Hangar 45 Rehabilitation CO -1 Project No -- 60532584 1 CONTRACT PRICE Original: $ 65,994.99 Previous C.O.s (ADD): $ 0.00 This C.O. (ADD): $ 5,550.00 Contract Price with all approved Change Orders: $ 71,544.99 CONTRACT TIMES (Calendar Date) Substantial Final completion completion Original: 09/15/2017 Previous C.O.s (ADD): 0 This C.O. (ADD): 0 REVISED: 09/15/2017 It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s) ordered herein, including all impact, delays, and acceleration costs. Other than the dollar amount and time allowance listed above, there shall be no further time or dollar compensation as a result of this Change Order. THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO. RECOMMENDED: By:' 3 [•W�^---- Engineer (Authorized Signature) APPROVED: By: Owner (Authorized Signa e) ACCEPTED. By; ontractor (Authorized Signature) ell() L7 Date 4.pr-,,v-c_Q Date .F//// D e Hangar #5 Rehabilitation CO -1 Project No — 60532584 2