CHANGE ORDER NO. 1
Owner Waterloo Regional Airport, City of Waterloo, Iowa Date August 1 2017
Project Hangar 5 Rehabilitation
Owner's Contract No. State Contract No. 18516 Contractor Pella Roofing & Insulation, Inc.
Date of Contract Start July 17, 2017
You are directed to make the following changes in the Contract Documents. Description:
ITEM
NO.
DESCRIPTION
UNIT
UNIT
PRICE
QUANTITY
AMOUNT
3
Remove Existing Metal Roofing
SFT
$ 1.00
2,000
$ 2,000.00
4
Install New Metal Roofing— 24 GA
SFT
$ 3.00
2,000
$ 6,000.00
101
Reuse Existing Metal Gutter
LS
$ 2,450.00
(1)
($ 2,450.00)
TOTALS $ 5,550.00
Reason for Change Order:
Items 3& 4 — During detailed review of the existing metal roof by the contractor it was determined that
replacement of additional metal roof panels beyond the contracted amount would be required because of an
additional amount of metal panels that were determined to be in need of replacement because of the panel
conditions. This change order will allow for an removal and replacement of an additional 2,000 square foot of
metal roof panels.
Item 101 — The contractor provided a value engineering item to reduce cost of the project. The existing gutter
system was reviewed in the field and determined to be in excellent condition. The contractor will remove the
existing gutter system, provide sealant material behind the existing gutter, reattach the existing gutter and provide
2 additional open downspouts on each side of the hangar.
Hangar 45 Rehabilitation
CO -1 Project No -- 60532584
1
CONTRACT PRICE
Original: $ 65,994.99
Previous C.O.s (ADD): $ 0.00
This C.O. (ADD): $ 5,550.00
Contract Price with all
approved Change Orders: $ 71,544.99
CONTRACT TIMES (Calendar Date)
Substantial Final
completion completion
Original: 09/15/2017
Previous C.O.s (ADD): 0
This C.O. (ADD): 0
REVISED: 09/15/2017
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the
change(s) ordered herein, including all impact, delays, and acceleration costs. Other than the dollar amount and time
allowance listed above, there shall be no further time or dollar compensation as a result of this Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO.
RECOMMENDED:
By:' 3 [•W�^----
Engineer (Authorized Signature)
APPROVED:
By:
Owner (Authorized Signa e)
ACCEPTED.
By;
ontractor (Authorized Signature)
ell() L7
Date
4.pr-,,v-c_Q Date
.F////
D e
Hangar #5 Rehabilitation CO -1 Project No — 60532584