HomeMy WebLinkAbout11/13/2017-Supplemental AttachmentsWWII-SiusidA ?Ataffilib - 3:50 p .
Presented by:
Steve Hoambrecker
and John Lapointe:
11/13/2017
1
IN THE UNITED STATES DISTRICT COURT
FOR THE NORTHERN DISTRICT OF IOWA
EASTERN DIVISION
11/13/2017
2
, o/ (jet to that point?
EPA did an Extensive Collection System Inspection in November 2010
at w� e0utcome?
Jaw
EPA said City Failed to
✓ Provide collection system physical
characteristics
✓ Report basement backups
✓ Footage of lines cleaned and
televised
✓ Not appropriate funding to
administer and maintain SS system
✓ Act and take necessary measure to
address 1/1
✓ Maintain physical LS structures
✓ Provide alternative LS power
backup
✓ Provide LS alarm system
✓ Evaluate collection system hydraulic
loading
✓ Develop written procedures for
administering collection system
The city said that
➢ Was not aware that Basement backups
counted as SSO's
➢ Had info on lines televised and cleaned
from previous years
> Had spent funding just needed to
identify projects
> Had identified problem areas and will
identify needed improvements
➢ Had identified potential I/1 footing
drains, but need policy changes
> Agreed LS needed upgrading,
questioned structural integrity
➢ Had portable pumps for LS emergency
operations
y Stated each LS had alarms, in process of
including w SCADA system
• Explained private sources of I/1(footing
drains) working on other sources
11/13/2017
3
A lot of 1/1 Bypasses Reported
!..oni 13 to Consent Decree
o Hired CMOM Specialist
o Hired CMOM Technician
Developed FOG ordinance and hired FOG
inspector
o Developed Footing Drain program and hired
inspector
o Incorporated sanitary sewer maps into GIS
Data Base
a Updated SSO Reporting
o Expanded TV and cleaning program
11/13/2017
4
onsent Decree Discussions Begin
In the End
The City Agreed
and Signed the
Consent Decree
And accepted the $272,000 Penalty with
$136,00 owed to the State of Iowa deferred
for Environment Beneficial Reuse Project
I
11/13/2017
5
[i terIoo Iowa Consent
o Issued October 26, 2015
• Civil Penalty 5272,000
States portion, $136,000 could he spent on an Environmental
• Stipulated specified tasks to be competed by 12-31-17
• Required to Develop Master Plan
• SSO Signage
• implement CMOM Program
• ImplenientSSORP
• Collect Rainfall -flow Monitoring for Hydraulic Modeling
• Complete Condition Assessment of Sewer System
• Develop Hydraulic Sanitary Sewer System Model
• Develop Capacity Assessment
• Submit Sanitary Sewer System Master Plan
• Reporting Requirements
• Subunit Status report To EPA and IDNR annually each 12-31 until termination of
Consent Decree
a Stipulated Penalties
• Daily fines for failure to subunit timely or complete reports
• Satisfy remedial requirements
• Each 550 or Prohibited Bypasses
• Failure to comply with Reporting Requirements
Decree
Beneficial Reuse Project
r
Penalty Details
to submit timely and complete re
'" Day $200/day
01" Day $400/day
y's $600/day
ial Requirements
'" Day $500/day
11111 • 31'4 to 601" Day $1000/day
• > 60 Day's $2000/day
o SSO's and Prohibited Bypasses
• Prior to Master Plan $0
• Master Plan through 2020
• Calendar years 2021 through 2023
• Calendar years 2024 through 2026
• Calendar years 2027 through 2029
• Calendar years 2030 through 2032
a Reporting Requirements
• 19' to 30111 Day
• 3191 to 60t" Day
• > 60 Day's
$200/day
$400/day
$600/day
$800/day
$1000/day
$200/day
$400/day
$600/day
orts
11/13/2017
6
talus of Penalty Fines
ate we have met all the reporting
requirements and Paid no fines
On Target to meet
2017 Required Deadlines
NTARGET
Beginning in 2018, will be subject to fines
for SSO's with exemptions for excessive rains
and flood levels in Blackhawk Creek or Cedar River
Overall Goal
System I/1 Prevent SSO's
Seel
Se
11/13/2017
7
Footing Drain Program
Ordinance 5248 - Purpose
Tr;undation Drains from Sanitary Sewer
District 1, SA 15 & SA 16
✓ Adopted October 27, 2014
✓ Effective January 1, 2015
✓ Initially 2 years, now thin 2017
"im'imi6161a
Conducted a special flow test following a
heavy rain in August16 and discovered
that flow increased an
average of 619'%,
Presently 20 homes have a flow monitor to
estimate an overall total of flow being diverted
d
J
11/13/2017
8
Excessive 1/1 Thru Footing
Drains
Thru September 2017
Of approximately 4000 homes
3,694 are considered compliant
2,384 have been disconnected
•h
Foundation Drains pouring water
into the sanitary sewer system
Footing Drain Comparisons
LLL
6 z 32. 2 -, z Si
MG Reduced
Inches precipitation
Ave River Cage Height
River Levels and Precipitation Amounts Greatly Effect the Amount of Water Removed
11/13/2017
9
1
oting
•
'ains Peak Flows
Footing Drain Flows Peak w Rainfall, August 2016
AFD GPD —Rain
1000 1 day flow jumps to 936 GPD
900
5 800
700
q 600
a 500
p 400 4 Days 306 GPD
.0 300
0
200
100
0
1.59 lnches of Rain
1.44 Inches of Rain
7 days 155 GPD
O,Sb Otib Otib Otib Otib Orb O4b �to Oyb dtito OSb
What does that Mean?
With 2500 homes and a flow to just that area
Previous 7 days at a flow of 387,000 GPD of I/I
Increasing almost 2,000,000 to 2,340,000 GPD
1.8
1.6
1.4
1.2
1 e
0.8
0.6
0.4
0.2
0
1
atus Footing Drain Program
SA 15 and SA 16
City Agreed to pay up to $2,000
per house hold disconnected
Expected 4,000 Households
3,694 Determined Compliant
2,384 have been Disconnected
Cost to the City to Date
$252,972 Inspection $$
$4,668,258 for Disconnects
Oct -16 Nov -16 Dec -16 Jan -17 Feb -17 Mar -17 Apr -17 May -17 Jun -17 Jul -17 Aug -17 Sep -17
Total Compliant-. 2994 3060 3117 3152 3198 3268 3328 3423 3481 3521 3624 3694
Total Disconnects: 2172 2207 2253 2272 2280 2304 2312 2330 2338 2340 2365 2384
7
11/13/2017
10
Summary Footing Drain
nects Total Compliant
4000
3500
3000
2500
2000
1500
1000
Target 4000 Households
3774 Compliant thru Oct 17
- Total Comp
� Tntal Discnnno(Ls
An Estimated 325-350 Outstanding to Achieve Total Compliance
to
mmTme
District 1 Passed Properties
(As of September 30, 2017)
Thru September 2017 r
p
3,694 Properties Passed YYFYi g, pe.
� r
2,384 Properties Corrected 5k•�, w liA,di� �
'''
' ,� 611HEyfIP,JA
11/13/2017
11
Hangers being Delivered
City of Waterloo
FOUNDATION DRAIN
COMPLIANCII
INSPECTION REQUIRED
ADDRESS
se call the Building Inspection
Department 319-291.4318
• between 7:30— B:30 am
3:00 —4:00 pm
and schedule a time
Your cooperation is expected
and appreciated.
Building Inspector
s of Footing Drain Program
Presently required compliance by 12/31/17
■ Ordinance 5248, passed 10/27/14 Program to end 12/16
■ Ordinance 5364, 8/22/16 extended completion to 12/31/17
■ Non compliant subject to $50/month penalty fee
■ October 2017, door hangers being placed on remaining 350
Continuance of Program??
■ Program effectively removing peak flows
■ Expensive program
■ Continue at lower city contribution
a Options for possible continuance
■ Continue for high flow households
■ Require for POS, Point of Sale
11/13/2017
12
[-(fir r
o r) r'a
Yearly Pounds of Grease
2016
. fi?I ,U.
1,392,102 _--=
87043 ; 64 182%
481,758 76%01
Monthly Pound of Grease by Year
200,000
150,000
100,000 - —
■ 2014
50,000 i1i111lid11
■ 2015
0 ■ 2016
ca R'i u cv `��' 5 t
¢,O o j
CD
zQ
FOG)
dTS
IL -G
Approach Taken
City Responsible for CONDITION ASSESSMENT
AECOM preparing MASTER PLAN
I
AECOM Responsible for CAPACITY ASSESSMENT
11/13/2017
13
Equipment Purchases
has invested in over $2 Million in.
rre\A/ and equipment upgrades
Description
PELCO NETWORK VIDEO RECORDER
ALUMINUM CAMERA TRANSPORTER
2015 FORD E450 SUPER DUTY
2015 KENWORTH HIGH PRESSURE SEWER
TRUCK
2015 VACALL COMBO JET VAC TRUCK
2015 VACALL COMBO JET VAC TRUCK
RETROFIT SEWER TRUCK
RETROFIT SEWER TRUCK
CLEANER
Acquisition
Date Purchase Price
8/17/2015 59,201.59
12/21/2015 513,219.00
12/21/2015 5506,267.00
10/5/2015
10/19/2015
10/19/2015
12/14/2015
12/14/2015
TOTALS
5252,212.42
5384,721.88
5384,721.88
5285,206.00
5299,567.00
$2,135,117
;erit Decree SSCP Requirements
Signage, Sampling and Disinfection
11/13/2017
14
Consent: Decree Requires Condition
a. n d[
Assessments be Completed
If
OIL AMMM4
Areas 15 & 16
Submitted 12/31/16
14
22
Areas 10,11,12,13 ,18 & 19
Submitted by 12/31/17
23
-Cb0cCC0000O000 000=0 0000
x bbbbbb== ==00C bcbobCc
lagvr'UgWKMgrnNanbC`4
11/13/2017
15
OOOOOO'OOOLG000e'0•t.D•Dv:.O•G'V •O •000'0 •D 0000000 LSA OL GNB
FIUUgFFa9F4aaa ogoF19,9a 9,9o95Tgaga,9
`a����a^ is_t t°'^ia`nqFis-lila° MT".:3"�.c�iMC.55
—� INfi j'mmmf��C•d T'�muu i, WW.. .MMW �NPQ.O
ource of Excessive Inflow
�► Operators Started Seeing Fish in Bar Screen
Afterword's we Discovered the Source
11/13/2017
16
With River Low
Some Tv'ing
Attempted on
Larger Mains Along
the River
Major Effort Spent on
ling Pipes and Manhol ehab
11/13/2017
17
Manhole Evaluations
A Total of 7,843 System Manholes
2,526 Manholes Inspected 32.2%
4L3%
25.4%
No Work
33.3%
Repaired
Of the 2,526 Manholes Inspected
640, (25.4%), no work needed
841, (33.3'%x), have been repaired
1,041 (41.3%), need future work
11/13/2017
18
Initially Cleaned the Suspect Sewers
Assemble, Bid and Inspect Project
11/13/2017
19
Layout of Sanitary Sewer
Service Areas
(IPP Lining Program
Waterloo Sanitary Sewer Totals
SMO SA11 SA12 SA13 SA14
Total Feet 190,837 213,120 63,535 76,719 159,
Total Miles 36.1 40.4 12.0 14.5 30.1
SA15 SA16
69,045 182,163
13.1 34.5
SA 15 & SA16 determined
to be wettest areas and
areas to be addressed
5A17 SA18 5A19 5A20 SA2I SA22 SA23 SA99 'Totals
120,475 227,965 313,422 33,309 54,396 52,116 230,287 29,262 2,015,693
22.8 43.2 59.4 6.3 10.3 9.9 43.6 5,5 381.8
✓ Have Completed
✓ CIPP 1, 2 and 3A
✓ Yet to Complete
✓ CIPP 3B and 3C
✓ Master Plan
✓ Outlining Future projects
11/13/2017
20
110
IProgram SA 1
69,045 Total Feet of Pipe
All 69,045 Video Inspected
All 69,045 Rated
21,120 Feet lined to date (30.6%)
470 Feet remain to be repaired
".r t 470 Ft remain to be Iined (0.6%)
P Lining Program SA 16
182,163 Total Feet of Pipe
A11 182,163 Video Inspected
All 182,163 Rated
87,867Feet lined to date (48.2°
1,100 Feet to be repaired
11/13/2017
21
raI Steps to CIPP Process
Initially clean pipe
D Cut out roots if necessary
o Identify active laterals
o Verify size of Pipe
o Line pipe
o Re -televise pipe
o Cut Out Laterals
o Grout laterals
Qr
00
AcrCi-ee I< Presented Dual Issues
11/13/2017
22
astewater was discharging into the creek
Inng non -high flow time
•
311M11: 25.19.75 ," ^ . 12711 ft.
0titi.:21-45-04 7,
avmslroanillir
t671-706 - 115.17414k
•
14,6 C
/
• IN
).111,17
air.- Mira,
99511111 21-1 7-05-
6.17.06 . 20.17.0
1
e •
•
-
•
20.0 ft.
41/•,1 417
Excessive 1/I was being collected for treatment
A
11/13/2017
23
SMN: 25-11.0
6ownstiowl
No excessive flow IN or OUT
"Distance:
Condition:
Remarks:
76.0 ft.
Tap Break -In
NIA
Grade:
0
Pre Lining
`Distance: 78.0 3
Condition: Tap Rehabilitated
Remarks: N/A
Grade: 0
Post Lining
11/13/2017
24
After Lining, Identified Laterals were Cut Out
Grout hardens and seals
the annual space between
the pipe and the lateral
Grouting Laterals
Insert Plug in Lateral, Seal
off each Side of Pipe and
Inject Grout Sealant
Not done in the earlier phases
Has greatly reduced the inflow
in the annular space between
the lining and lateral
•
11/13/2017
25
Lining and Manhole
Project Costs
CIPP 1 $769,391
CIPP 2 $1,734,591
CIPP 3 $1,593,491
TOTAL $4,097,473
ivironmental Beneficial Project
Permeable Paving Program
City uses Block Pavers
vrs Permeable Pavers
Apply State's $136K
Toward cost of Project
11/13/2017
26
[nviroiimentai Beneficial Projec
'1ieable Paving Program
Cracks will Fill
with Debris
a s,
Consent Decree Requires Purchasing
of a Vacuum Device
Evaluating Options to:
Perform Water Flow Testing
Contracting out Cleaning
Eventually Purchase a Street Sweeper
Capable of Cleaning
at's the Cost to Date
Cost Items Costs
Equipment $2,135,117
CIPP Projects $4,097,473
Footing Drain $4,668,258
Env Beneficial Project $180,000
TOTAL $11,080,848
11/13/2017
27
::Or Pfau
[Rion Assessment Work performed by WM
All 3
Due
12/31/17
Capacity Assessment Work Performed by AECOM
T[ I }'S CONSENT
R: iJ[ MEi TS
DIES:
SANITARY SEWER SYSTEM HYDRAULIC
MODEL
SANITARY SEWER AND PUMPING
STATIONS CONDITION ASSESSMENT
SANITARY SEWER SYSTEM CAPACITY
ASSESSMENT
MASTER PLAN OF IMPROVEMENTS
11/13/2017
28
WATERLOO'S CONSENT
DECREE REQUIREMENTS
SANITARY SEWER SYSTEM HYDRAULIC
MODEL:
A. FIELD WORK CONDUCTED IN 2015
B. MODEL COMPLETED IN 2016
c. MODEL USED TO IDENTIFY AREAS OF
EXCESSIVE INFILTRATION & INFLOW
AND EVALUATE THE CAPACITY OF THE
SANITARY SEWER COLLECTION AND
PUMPING SYSTEMS
WATERLOO'S CONSENT
',REE REQUIREMENTS
CONDITION ASSESSMENT:
A. MUST ADDRESS STRUCTURAL DEFECTS
WHICH CAUSE OR SIGNIFICANTLY
CONTRIBUTE TO SSOs, BUILDING BACKUPS
AND PROHIBITED DISCHARGES
SANITARY SEWERS
y PUMPING STATIONS
FORCEMAINS
B. MUST IDENTIFY STORM SEWER CROSS -
CONNECTIONS AND OTHER UNAUTHORIZED
DIRECT CONNECTIONS TO SANITARY
SYSTEM
11/13/2017
29
WATERLOO'S CONSENT
D*REE REQUIREMENTS
CAPACITY ASSESSMENT:
A. IDENTIFY EXISTING SANITARY SEWER
SYSTEM BOTTLENECKS
B. IDENTIFY FUTURE (GROWTH -RELATED)
SANITARY SEWER SYSTEM
BOTTLENECKS
-AssixeVaimilik
Imp
ATERLOO'S CONSENT
CREE REQUIREMENTS
ASTER PLAN OF IMPROVEMENTS:
A. PRELIMINARY DESIGNS
B. COST ESTIMATES
c. TIMETABLES
11/13/2017
30
'AT RWO'S CONSENT
[E R[OUIR M N t S
�JT O ELATED
MOVEMENTS:
CIDP LINING PROGRAM
MANFIOLE REHABILITATIONS
LIFT STATION & FORCEMAIN
REHABILITATION / REPLACEMENT
PROJECTS
D. ADDITIONAL STUDIES
➢ EAST SIDE INTERCEPTOR SEWER
r WEST SIDE INTERCEPTOR SEWER
r! W4 ; Q'S CONSENT
KkE UFRE EE TS
"RELATED IMPROVEMENTS:
A. FOUNDATION N DRAINS REMOVAL
PROGRAM
DRY RUN CREEK LIFT STATION &
INTERCEPTOR PROJECT
NORTHWEST INTERCEPTOR PROJECT
TITUS (MIDLAND ST) LIFT STATION AND
FOITCEMAIN PROJECT
STORM SEWER CROSS CONNECTION
REMOVAL PROJECTS
F. ELIMINATION OF CROSS CONNECTIONS
IDENTIFIED BY SMOKE TESTING
11/13/2017
31
WATERLOO'S CONSENT
DECREE REQUIREMENTS
COST CONSIDERATIONS:
r. TOTAL COST OF PROJECTS WHICH ARE NECESSARY
TO MEET THE MINIMUM CONSENT DECREE
REQUIREMENTS CONCERNING SSOs, BYPASSES AND
PROHIBITED DISCHARGES:
$17,904,000
n TOTAL COST OF PROJECTS WHICH ARE NEEDED TO
ASSURE LONG-TERM COMPLIANCE WITH CONSENT
DECREE REQUIREMENTS:
$64,727,000
m. TOTAL INFRASTRUCTURE INVESTMENT
(PROJECTED OVER 15 YEARS):
$82,631,000
11/13/2017
32
11/13/2017
Bent Decree Bucket
Projects
Projects that are due to lack of
Adequate Capacity or caused
by Deficiencies in O&M.
•
Consent
Decree
17,904,000
Such Projects are Generally Underway
✓ Dry Run Creek LS
✓ CIPP 3 B & C
✓ NW Interceptor/Hackett LS Demo
✓ Titus LS and Force Main
v' Footing Drain Removal Program
Possibly done with
3-5 Years
df+
ration and Elimination of Overflows
the Citan
enw nstrate or l 1 ear that:
s, :tri - n;' : ac ''ups and Prohibited -Bypasses
caused by a lack of Adequate Capacity or by
deficiencies in O&M have been eliminated.,
ffpr or to aster Plan reme a a '.1t1°
The City concludes improvements made to eliminate
SSQ's, Building backups and Prohibited Bypasses
The City rrati submit Request for Termination
za.t does this mean?.
otentially in as early as 3-5 years the city
could petition to get out from under the
Requirements of the Consent Decree
El 1 Year demonstration period
No SSO's, Building Backups or Prohibited
Bypasses caused by a lack of adequate
capacity or by deficiencies in O&M.
We Can Request to get out from Under the
CONSENT DECREE
erloo will be Ahead of the Game
Tie n noni or pay me later"
By making improvements
today, 1 will be
ahead of the game
tomorrow
ending$10 Million today
jLa(pr� 4/ce
10,,,.P!,
(i
Spending $15 Million tomorrow
Admittedly we are spending a lot today
on improvements that would have been
needing to be done tomorrow and by
spending those $$ today we will save
money in the long run
11/13/2017
34
-MOM Bucket
Projects that are required to Maintain
Capacity within the system and an
w! &M to program to prevent the
urrence of SSO's, Building
ckups and Prohibited Bypasses
$64,997,000
These Projects will become part
of the City's CIP process over the
NEXT 15 YEARS
11/13/2017
35
in Conclusion
Paid 1/2 of Original Fine, put the other 1/2 toward a
Environmentally Beneficial Project
Have met all Required Reporting Requirements
Have Paid NO MORE Penalty fines
Efforts to date have reduce system I/I and
associated SSO's.
*Need to decide future of Footing Drain Program
y Are Scheduled to submit final documents as
required by 12/31/17
Possibly positioned to be able to request
termination of Consent Decree early
Need to maintain a proactive CMOM Program to
facilitate ongoing Compliance
11/13/2017
36
,)V AECOM
DRAFT
SANITARY SEWER SYSTEM
MASTER PLAN
PROJECTS SUMMARY
Presented at Waterloo City Council Workshop
November 13, 2017
Sanitary Sewer System Master Plan
Waterloo, Iowa
11.0 Overall Master Plan
11.1 MASTER PLAN PROJECT LIST
Table 11-1, below and on the following pages, contains a summary of all anticipated sanitary sewer system
condition and capacity remediation measures to be conducted during the Master Plan time period (2018-2032).
Table 11-1 also identifies the estimated cost of each project.
The projects with estimated costs highlighted in red have been determined by means of Hydraulic Modelling and the
Condition and Capacity Assessments to be necessary to meet the minimum Consent Decree requirements
concerning SSOs, Bypasses and Prohibited Discharges. The project with estimated costs highlighted in yellow are
needed to assure Tong -term compliance with Consent Decree requirements.
Most of the projects highlighted in red are currently under design or implementation. The City of Waterloo is
committed to completion of these projects by the end of the year 2020. The projects highlighted in yellow will be
conducted in accordance with the City's Capacity Management Operation and Maintenance (CMOM) Program
according to the timeframes presented in Table 11-1 as funding allows.
TABLE 11-1
MASTER PLAN PROJECT LIST AND COST ESTIMATE
60532599/400/401/Sanitary Sewer Mester Plan/MP Text.doex
DRAFT - November 13, 2017
TIMEFRAME:
2018 - 2020
Project Name
Completion
Date
Service
Areas
Project Description
Estimated
Cost
Consent
Decree
Estimated
Cost
CMOM
Program
Dry Run Creek Lift Station and
Interceptor
2018
19
New Lift Station to supply capacity
for growth in area served, and new
interceptor to divert flows away from
91" Street corridor.
83,605,004
CIPP and Remedial Measures,
Phase IIIB
2018
11, 15, 16,
17 & 19
Installation of +1- 2,900 LF of Cured-
In -Place Pipe (CIPP).
8515,000
CIPP and Remedial Measures,
Phase IIIC
2018
11, 15, 16,
17 & 19
Installation of +1- 7,300 LF of Cured-
In -Place Pipe (CIPP).
8409,000
CIPP and Remedial Measures
Phase IV
2018
12 & 19
Installation of +1- 50,000 LF of
Cured -In -Place Pipe (CIPP) and
rehabilitation of +1- 500 manholes to
restore condition of deteriorated
sewer segments and manholes.
$6,153,000
Northwest Interceptor
2018 - 2020
15 & 16
Extension of an existing intercepter
to provide gravity flow sanitary
sewer capacity to areas currently
served by Hackett Lift Station and
Cattle Congress Lift Station
86,635,000
Smoke Testing Identified
Deficiencies — Service
Area 18
2018 - 2020
18
Elimination of storm water inflow
sources. Field work conducted by
WMSD staff.
$265,000
Removal of Storm Sewer Intakes
Connected To Sanitary Sewers:
• Kingbard Blvd,
• Woodstock Rd.
City Engr. Projects
2018
10, 12, 18
& 99
Disconnection of storm sewer
intakes from sanitary sewer system
included with 2018 - 2020 Street
Reconstruction projects.
$807,000
Removal of Storm Sewer Intakes
Connected To Sanitary Sewers:
• West Mitchell Ave. (at
Derbyshire)
WMSD Projects
2020
19
Disconnection of storm sewer cross
connection from sanitary sewer
system, performed by WMSD staff.
S68.000
Demolition of Hackett Lift Station
2018 - 2020
15 & 16
Demolition of Hackett Lift Station
after NW Interceptor Sewer project
is complete.
$212,000
60532599/400/401/Sanitary Sewer Mester Plan/MP Text.doex
DRAFT - November 13, 2017
Sanitary Sewer System Master Plan
Waterloo, Iowa
60532599/400/401/Sanitary Sewer Mester Plan/MP Textdocx 11-2
DRAFT - November 13, 2017
TIMEFRAME:
(Continued)_
2018 - 2020
Project Name
Completion
Date
Service
Areas
Project Description
Estimated
Cost
Consent
Decree
Estimated
Cost
CMOM
Pro ram
Titus (Midland) Lift Station and
Force Main
2018 — 2020
10
New Lift Station to supply capacity
for growth in area served, and new
force main to transfer flow to Park
Road Lift Station.
$6,128,000
Douglas Lift Station and Force Main
Replacement
2018 - 2020
11
Replace Douglas Lift Station and
Force Main With a New Lift Station
and Force Main
$875,000
Additional Study: Field Assessment2018
of East Side Interceptor Sewer
gg
Internal/CCTV inspection and
external pipe structural testing.
$300,000
Foundation Drains Removal
Program
2018
15 & 16
Disconnect Foundation Drains
Discharging to Sanitary Sewer
S stem
$400,000
TOTAL ESTIMATED
MEASURES
COST -
2018 - 2020:
MASTER
$26,372,000
PLAN REMEDIAL
$17,904,000
$8,468,000
TIMEFRAME:
2021 - 2023
Project Name
Completion
Date
Service
Areas
Project Description
Estimated
Cost
Consent
Decree
Estimated
Cost
CMOM
Program
East Side Interceptor Sewer, Phase2021
1— Wet Side to Dry Side
2023
gg
5,625 LF of new 54 -inch dia.
prestressed concrete pipe.
$8,400,000
CIPP and Remedial Measures,
Phase V
2021 - 202313
10,11 &
Installation of +1- 50,000 LF of
Cured -In -Place Pipe (CIPP) and
rehabilitation +1- 500 manholes to
restore condition of deteriorated
sewer segments and manholes.
$10,162,000
Removal of Storm Sewer Intakes
Connected To Sanitary Sewers:
• Courtland St.
City Engineering Project
2021 - 2023
12
Disconnection of storm sewer
intakes from sanitary sewer system
included with 2021 - 2023 Street
Reconstruction projects.
$945,000
Removal of Storm Sewer Intakes
Connected To Sanitary Sewers:
• Drexel Ave. & Reber Ave.
• Kothe Ave.
• West Parker St.
• Marlin Ct.
WMSD Projects
2021 - 2023
10, 11, 18
Disconnection of storm sewer cross
connections from sanitary sewer
system, performed by WMSD staff
or by low bid contractor.
$1,322,000
Cattle Congress Lift Station and
Force Main
2021 — 2023
2021 — 2023
16
10
New lift station to supply capacity to
area served, and new force main to
transfer flow to Northwest
Interceptor
Replace the existing Park Road Lift
Station and Force Main with a new
lift station and force main.
,
$1,304,000
$1,782,000
Park Road Lift Station and Force
Main
TOTAL ESTIMATED COST -
MEASURES 2021 - 2023:
MASTER PLAN REMEDIAL
$23,875,000
$D
$23,875,000
60532599/400/401/Sanitary Sewer Mester Plan/MP Textdocx 11-2
DRAFT - November 13, 2017
Sanitary Sewer System Master Plan
Waterloo, Iowa
Project Name
TIMEFRAME:
Completion
Date
Service
Areas
2024 - 2026
Project Description
Estimated
Cost
Consent
Decree
Estimated
Cost
CMOM
Program
East Side Interceptor Sewer,
Phase II - Wet Side to Dry Side
2024 — 2026
99
5,625 LF of 54 -inch dia.
prestressed concrete pipe.
Removal of Storm Sewer Intakes
Connected To Sanitary Sewers:
• Columbia Cr.
City Engr. Projects
$8,400,000
Removal of Storm Sewer Intakes
Connected To Sanitary Sewers:
• Dearborn Ave. (at Indiana St.)
• State St. (Archer Ave. to
Butler Ave.)
• Blowers Ave. (at Wyoming St.)
• Blowers Ave. (at California St.)
• 300 Block Indiana St.
• 300 Block Butler Ave.
WMSD Projects
2024 - 2026
Disconnection of storm sewer
cross connections from sanitary
sewer system, performed by
WMSD staff or by low bid
contractor.
Removal of Storm Sewer Intakes
Connected To Sanitary Sewers: I
• Cornwall Ave.
WMSD Projects
$2,172,000
Garden Ave. Lift Station and
Force Main
2024 — 2026
16
Replace the existing Garden
Avenue Lift Station and Force
Main with a new lift station and
force main.
Hawkeye Lift Station and Force
Main Rehabilitation
$1,625,000
Highway 63 South Lift Station and
Force Main
2024 — 2026
18
Replace the existing Highway 63
South Lift Station and Force Main
with a new lift station and force
main.
Webster Lift Station and Force
Main
$1,380,000
TOTAL ESTIMATED COST —
MEASURES 2024 - 2026:
MASTER PLAN REMEDIAL
$13,577,000
$o
$13,577,000
60532599/400/404/Sanitary Sewer Master Plan/MP Text docx 11-3
DRAFT - November 13, 2017
TIMEFRAME: 2027 - 2029
Project Name
Completion
Date
Service
Areas
Project Description
Estimated
Cost
Consent
Decree
Estimated
Cost
CMOM
Program
Removal of Storm Sewer Intakes
Connected To Sanitary Sewers:
• Columbia Cr.
City Engr. Projects
2027-2029
Disconnection of storm sewer
cross connections from sanitary
sewer system, performed by
WMSD staff or by low bid
contractor.
$1,051,000
Removal of Storm Sewer Intakes
Connected To Sanitary Sewers: I
• Cornwall Ave.
WMSD Projects
2027 — 2029
Disconnection of storm sewer
cross connections from sanitary
sewer system, performed by
WMSD staff or by low bid
contractor.
$108,000
Hawkeye Lift Station and Force
Main Rehabilitation
2027 - 2029
23
Rehabilitate existing Hawkeye Lift
Station and Force Main with new
pumps, HVAC, electrical and
controls.
Include on-site emergency
generator.
$3,114,000
Webster Lift Station and Force
Main
2027 — 2029
11
Rehabilitate existing Webster Lift
Station.
1
$1,463,000
Cedar Terrace Lift Station and
Force Main
2027 — 2029
23
Replace the existing Cedar
Terrace Lift Station and Force
Main with a new lift station and
force main.
$1,910,000
Service Area 18 Sewer Segments
Along Highway 63 South Corridor
2024 - 2026 1
18
Installation of 23,000 LF of 36-
inch diameter sanitary sewer.
9,800,000
TOTAL ESTIMATED COST —
MEASURES 2027 - 2029:
MASTER
$17,446,000
PLAN REMEDIAL
$o
$17,446.000
60532599/400/404/Sanitary Sewer Master Plan/MP Text docx 11-3
DRAFT - November 13, 2017
Sanitary Sewer System Master Plan
Waterloo, Iowa
Project Name
TIMEFRAME:
Completion
Date
Service
Areas
2030 - 2032
Estimated Estimated
Project Description Cost Cost
Consent CMOM
Decree Program
Greenbrier Lift Station and Force
Main
2030 — 2032
10
New lift station to supply capacity
for area served, and new force $1,361,000
main to transfer flow to Virginia
Lift Station,
TOTAL ESTIMATED COST - MASTER PLAN REMEDIAL
MEASURES 2030 - 2032: $1,361,000
$o
$1,361,000
OVERALL COST ESTIMATE BREAKDOWN FOR COMPLETE MASTER PLAN TIMEFRAME - 2018 - 2032:
Timeframe: 2018 — 2032
Estimated Cost
Consent Decree
Estimated Cost
CMOM Program
TOTAL ESTIMATED COST - ALL MASTER PLAN REMEDIAL
MEASURES 2018 - 2032: $82,631,000
$17,904,000 $64,727,000
60532599/400/401/Sanitary Server MasterPlan/MP Text.dacx
11-4 DRAFT - November 13, 2017