HomeMy WebLinkAboutWoodruff Construction - CO#2 Hangar No. 4 Rehab - 3/12/2018CHANGE ORDER NO. 2
Owner Waterloo Regional Airport, City of Waterloo, Iowa Date March 5, 2018
Project Hangar No. 4 Rehabilitation
Owner's Contract No. State Contract No. 19599 Contractor Wood Construction, Inc.
Date of Contract Start November 29, 2017
You are directed to make the following changes in the Contract Documents. Description:
ITEM
DESCRIPTION
UNIT
UNIT
QUANTITY
AMOUNT
NO.
PRICE
105
Replace Steel Entrance Door
T&M
$ 1,200.00
1
$ 1,200.00
TOTALS
S 1,200.00
Reason for Change Order:
Item 105 — The entrance door to the maintenance shop office area is of original construction and is in poor
condition and in need of replacement. The door, door hardware, threshold, and weather stripping will be
replaced. The door, frame and wall will be painted upon installation. Work will be completed at a time and
materials cost not to exceed for this item.
Hangar #4 Rehabilitation
CO -2
1
Project No — 60555170
CONTRACT PRICE
Original:
Previous C.O.s (ADD):
This C.O. (ADD):
Contract Price with all
approved Change Orders: $ 75,176.00
CONTRACT TIMES (Calendar Date)
Substantial Final
completion completion
$ 65,522.00 Original:
$ 8,454.00 Previous C.O.s (ADD):
$ 1 200.00 This C.O. (ADD):
REVISED:
4/20/2018
0
0
4/20/2018
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the
change(s) ordered herein, including all impact, delays, and acceleration costs. Other than the dollar amount and time
allowance listed above, there shall be no further time or dollar compensation as a result of this Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO.
RECO
By:
MENDED:
Engi er (Authorized Signature)
APPROVED:
By:
Owner (Authorized Signature)
ACCEPTED:
By: /14
Contractor (Authorized ture)
31/4/aorg"
Date
Date
ate
Hangar #4 Rehabilitation CO -2 Project No — 60555170