Loading...
HomeMy WebLinkAboutMidAmerican - Distribution Extension Agmnt - 1/16/2018MidAmerican Energy Company ELECTRIC DISTRIBUTION EXTENSION AGREEMENT NON-REFUNDABLE CONTRIBUTION IN AID OF CONSTRUCTION Energy Company, anCorporation,_ . MidAmerican Com an Iowa its successors and assigns, (Company), and City of Waterloo, 325 Sycamore St, Waterloo, Ia 50704 its successors and assigns, (Applicant) agree as follows: 1. Company will extend its electric distribution system as required to make electric service available to the following platted and described area: ............. 80 W Mullan Ave, Waterloo, Ia - South Pump Station 2. The Company shall: a. Install, own, operate and maintain the electric distribution system and reserves the right to extend or alter the system in the future if necessary. b. Furnish all necessary labor and materials required for the construction of such distribution system. c. Schedule such installation with Applicant so as to provide timely service. 3. The Applicant shall: a. Provide, without cost to the Company, such easements as are necessary for the construction, operation and maintenance of the electric distribution system. b. Provide easement areas: 1) cleared of all obstructions; 2) within 4" of final grade over the route of the distribution system; 3) with streets finished to local specifications; and 4) with sewer and water installed. c. Place visible stakes, including lot numbers, on all lot corners and easement lines. d. Provide drawings showing the location of all present and future underground facilities. e. Provide the concrete transformer pads, conduit systems, and other facilities where required by the Company's tariffs and electric service manual (includes an inspection by a Company representative prior to pouring the pads or covering the conduit system). f. Locate all underground facilities such as storm sewers, sanitary sewers, septic lines and water lines that are not located by members of a one -call locating system. g. Indemnify, protect and hold harmless the Company from and against all liability, damage, loss, claims and actions any nature whatsoever which arise out of damage to underground facilities resulting from the customer's failure to correctly locate such facilities as required under this agreement. h. Hold Company harmless for any loss, cost or damage caused by delays in construction of the distribution system and services. 4. Applicant agrees to pay $;12,767.18 ? as a contribution in aid of construction in accordance with Company's tariff. The cash contribution in aid of construction shall be due when this Agreement is signed by Applicant. If Applicant requires that the installation be completed during the winter construction season, or when adverse working conditions impede construction, Applicant shall pay an additional non-refundable sum of $ 4.84 per foot. The Company reserves the right to determine when such winter construction season conditions exist. Within the area described above, Company will provide electric service to customers in accordance with Company's tariffs andre=:s•. requirements. MIDAMERICAN ENERGY ;I/ PA ► i APPLICANT / By Q vcr k -+n {-io•.r t - Title MUy r Date Wanted .. 5. By Adam Streeter Title Engineering Supervisor WMIS # 2671605 District North Date Signed J O.n v41 ..11e a° k $ .ptpp,ro+rco� vo�+t 2-2 5/18/11