Loading...
HomeMy WebLinkAboutCroell, Inc. - CO #3 - Reconstruct Taxiway C - 7/9/2018 CHANGE ORDER NO. 3 Owner Waterloo Reeional Airport City of Waterloo Iowa Date June 26,2018 Project Reconstruct Taxiway C—North of Runway 12/30 Reconstruct Taxiway C South of Runway 12/30 Owner's Contract No.FAA AIP Project No 3-19-0094-045 Contractor Croell,Inc. Date of Contract Start July 17,2017 You are directed to make the following changes in the Contract Documents. Description: Item No. Description Unit Unit Price Quantity Amount 29 Electrical Handhole,L-868 EA $712.02 1 $ 712.02 110 Directional Bore for 2-2 Inch Conduits LF $ 13.20 190 $2,508.00 111 2-Inch Schedule 40 HDPE LF $0.94 400 $376.00 112 Equipment Mobilization for Directional Bore LS $550.00 1 $550.00 113 Manhole Adjustment EA $3,500.00 1 $3,500.00 Total Change Order $ 7,646.02 Reason for Change Order: The existing conduit under Runway 12-30 was found to be filled with sand. New conduit installed adjacent to existing conduit will be used to convey new electrical cable. Existing manhole containing FAA cable located in pavement taper of Taxiway C requires adjustment to final paving grade. Reconstruct Taxiway C—North of Runway 12/30 CO-3 Project No—60550592 Reconstruct Taxiway C—South of Runway 12/30 1 CONTRACT PRICE CONTRACT TIMES(Calendar Days) To substantial To final completion completion Original: $_ 2,128,833.19 Original: 150 Previous C.O.s(DEDUCT):$-----7,.940.10 Previous C.O.s(ADD): 4 This C.O. (ADD): $ 7,642.02 This C.O. (ADD): 4 Contract Price with all REVISED: 158 approved Change Orders: $ 2,144,415.31 It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s)ordered herein,including all impact,delays,and acceleration costs. Other than the dollar amount and time allowance listed above,there shall be no further time or dollar compensation as a result of this Change Order. THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO. REC MENDED: M o B 1/115 Engi er(Authorized 'gnature) Date APPROVED: Owner(Authorized Signature) Date AC;ontractor((AAuthhoriiz,.e.,di T By: I lol Signature) Date Reconstruct Taxiway C—North of Runway 12/30 CO-3 Project No—60550592 Reconstruct Taxiway C—South of Runway 12/30 2 Letter of Transmittal AECOM DATE: July 9, 2018 JOB ID NO. 60550592 TO: Mr. Keith Kaspari ATTENTION: Director of Aviation RE: Reconstruct Taxiway C - North of Runway 12/30 Waterloo Regional Airport Reconstruct Taxiway C - South of Runway 12/30 2790 Livingston Lane FAA AlP #3-19-0094-045 Waterloo, Iowa 50703 WE ARE SENDING YOU: • Attached ❑ Prints ❑ Under Separate Cover Via the following items: ❑ Shop Drawings ❑ Change Order ❑ Plans ❑ Samples ❑ Specifications ❑ Copy of Letter ❑ ❑ COPIES DATE NO. DESCRIPTION 5 Wet-Signed Copies of Change Order No. 3 for Above-Referenced Project THESE ARE TRANSMITTED AS CHECKED BELOW: ❑ For Approval ❑ Approved as Submitted ❑ Resubmit Copies for Approval ❑ For Your Use ❑ Approved as Noted ❑ Submit Copies for Distribution ❑ As Requested 0 Returned ❑ Return Corrected Prints ❑ For Review and 0 For Mayor's Signature Comment ❑ For Bids Due 20 ❑ Prints Returned After Loan to Us REMARKS: Keith --Attached please find five (5) copies of Change Order No. 3 for the Reconstruct Taxiway C project at the Waterloo Regional Airport. After review and approval, please have Mayor Hart sign all five (5) copies. The City and the Airport should each keep one copy for their files, and the remaining three (3) copies should be returned to AECOM for further distribution. If you have any questions, please let us know. Thank you. COPY TO: David Hughes (w/enclosure) SIGNED: (kf. DWS:bIcouglas W. Schindel, PE If enclosures are not as noted,kindly notify us at once. 501 Sycamore Street,Suite 222 • P.O.Box 1497 • Waterloo, Iowa 50704-1497 • (319)232-6531 • Fax: (319)232-0271