HomeMy WebLinkAboutCroell, Inc. - CO #3 - Reconstruct Taxiway C - 7/9/2018 CHANGE ORDER NO. 3
Owner Waterloo Reeional Airport City of Waterloo Iowa Date June 26,2018
Project Reconstruct Taxiway C—North of Runway 12/30 Reconstruct Taxiway C South of Runway 12/30
Owner's Contract No.FAA AIP Project No 3-19-0094-045 Contractor Croell,Inc.
Date of Contract Start July 17,2017
You are directed to make the following changes in the Contract Documents. Description:
Item
No. Description Unit Unit Price Quantity Amount
29 Electrical Handhole,L-868 EA $712.02 1 $ 712.02
110 Directional Bore for 2-2 Inch Conduits LF $ 13.20 190 $2,508.00
111 2-Inch Schedule 40 HDPE LF $0.94 400 $376.00
112 Equipment Mobilization for Directional Bore LS $550.00 1 $550.00
113 Manhole Adjustment EA $3,500.00 1 $3,500.00
Total Change Order $ 7,646.02
Reason for Change Order:
The existing conduit under Runway 12-30 was found to be filled with sand. New conduit installed
adjacent to existing conduit will be used to convey new electrical cable.
Existing manhole containing FAA cable located in pavement taper of Taxiway C requires adjustment to
final paving grade.
Reconstruct Taxiway C—North of Runway 12/30 CO-3 Project No—60550592
Reconstruct Taxiway C—South of Runway 12/30
1
CONTRACT PRICE CONTRACT TIMES(Calendar Days)
To substantial To final
completion completion
Original: $_ 2,128,833.19 Original: 150
Previous C.O.s(DEDUCT):$-----7,.940.10 Previous C.O.s(ADD): 4
This C.O. (ADD): $ 7,642.02 This C.O. (ADD): 4
Contract Price with all REVISED: 158
approved Change Orders: $ 2,144,415.31
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the
change(s)ordered herein,including all impact,delays,and acceleration costs. Other than the dollar amount and time
allowance listed above,there shall be no further time or dollar compensation as a result of this Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO.
REC MENDED: M o
B 1/115
Engi er(Authorized 'gnature) Date
APPROVED:
Owner(Authorized Signature) Date
AC;ontractor((AAuthhoriiz,.e.,di
T
By: I lol
Signature) Date
Reconstruct Taxiway C—North of Runway 12/30 CO-3 Project No—60550592
Reconstruct Taxiway C—South of Runway 12/30
2